Amazon Region Protected Areas Program Phase II (GEF)

Abstract*

The objective of the Second Phase of the Amazon Region Protected Areas (ARPA) Program Project (GEF) for Brazil is to expand and consolidate the system of protected areas in the Amazon region, and to strengthen the mechanisms for its financial sustainability. Project has four components. Component 1: Creation of approximately an additional thirteen million five hundred thousand hectares of new protected areas in the Amazon region to those created under...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Global Environmental Objective is the same as the Project Development Objective (PDO), which is to expand and consolidate the system of Protected Areas in the Brazilian Amazon region and to strengthen mechanisms for its financial sustainability.

Key Details

Project Details

  • P114810

  • Closed

  • Adriana Goncalves Moreira

  • Brazilian Biodiversity Fund - FUNBIO

  • Brazil

  • April 16, 2010

  • (as of board presentation)

    February 23, 2012

  • June 19, 2012

  • US$ 85.89 million

  • Brazilian Ministry of Environment (MMA)

  • Latin America and Caribbean

  • 2012

  • US$ 55.89 million

  • B

  • N/A

  • July 31, 2017

  • Yes

  • BANK APPROVED

  • March 15, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Environment Facility (GEF) 15.89
Borrower/Recipient 30.00
World Wildlife Fund 10.00
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) 30.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 55.89
Total Project Cost** 85.89

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2017-06-28
Overall Implementation Progress (IP) Satisfactory 2017-06-28
Procurement Satisfactory 2017-06-28
Financial Management Satisfactory 2017-06-28
Summary Global Objective Rating Satisfactory 2017-06-28
Counterpart Funding Satisfactory 2017-06-28
Monitoring and Evaluation Satisfactory 2017-06-28
Overall Safeguards Rating Satisfactory 2017-06-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-23-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualityModestN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Existing Protected Areas consolidatedValue8500000.0032000000.0033888828.00
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • Areas brought under enhanced biodiversity protection (ha)Value8500000.0024000000.0033888828.00
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • ARPA Protected Areas Fund increased by 150% above its current level of fundsValue27200000.0042800000.00121301000.00
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • New Protected Areas created in Amazon.Value24000000.0013500000.003753366.00
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area studied for the creation of PAsValue5000000.0030000000.0030000000.00
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • At least 20 PA Action Plans implemented with communities and indigenous peoples in accordance with IPPF and RF.Value0.0020.0023.00
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • Consolidated Capacity Building Plan prepared and at least 80% of activities successfully executed.Value0.0080.00100.00
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • Map of Priority Areas updatedValue200712302017073120160530
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • Consolidation of 23 million hectares in consolidation stage 1 and 9 million hectares in stage 2.Value8500000.0032000000.0038888828.00
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • At least three PA management models tested and described in case studiesValue0.003.007.00
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • Strategy for Conservation and Investment (ECI) applied and information updated in FAUC.ValueQuality assessment of strategyEIC and FAUC being used to guide operations.ECI and FAUC updated annually and being used to gu
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • 6 strategic studies and 4 PA financial sustainability plans implemented.Value0.006.0010.00
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • Environment and Social Monitoring Framework developed and being updated on an annual basis including in situ information for PAs inStage 2 of consolidation.ValueEnvironmental framework developed.Environmental and Social Monitoring Framework deveEnvironmental and social monitoring framework deve
    DateJanuary 27, 2012July 31, 2017June 9, 2016
    Comment
  • Project management efficiency improved with real time tracking system (Cerebro II) implemented.ValueCerebro II tracking system in place.Survey results used to improved management efficieCerebro II tracking system fully operational.
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • Program Communication Strategy developed and at least 80% of planned activities executed.ValueARPA Phase 1 communication strategyAt least 80 percent of planned activitiesCommunication Strategy 100% implemented.
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment
  • FAP Operational and making annual disbursements to selected PAsValueZero100 percent of FAP's approved budget100% of annual disbursements
    DateJanuary 27, 2012July 31, 2017June 6, 2017
    Comment