Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 15.89 |
Borrower/Recipient | 30.00 |
World Wildlife Fund | 10.00 |
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) | 30.00 |
P114810
Closed
Adriana Goncalves Moreira
Brazilian Biodiversity Fund - FUNBIO
April 16, 2010
(as of board presentation)
February 23, 2012
June 19, 2012
US$ 85.89 million
Brazilian Ministry of Environment (MMA)
2012
US$ 55.89 million
B
N/A
July 31, 2017
Yes
BANK APPROVED
March 15, 2022
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 15.89 |
Borrower/Recipient | 30.00 |
World Wildlife Fund | 10.00 |
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) | 30.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 55.89 |
Total Project Cost** | 85.89 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2017-06-28 |
Overall Implementation Progress (IP) | Satisfactory | 2017-06-28 |
Procurement | Satisfactory | 2017-06-28 |
Financial Management | Satisfactory | 2017-06-28 |
Summary Global Objective Rating | Satisfactory | 2017-06-28 |
Counterpart Funding | Satisfactory | 2017-06-28 |
Monitoring and Evaluation | Satisfactory | 2017-06-28 |
Overall Safeguards Rating | Satisfactory | 2017-06-28 |
INDICATOR | ICR REVIEW: 04-23-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Modest | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Existing Protected Areas consolidated | Value | 8500000.00 | 32000000.00 | 33888828.00 |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
Areas brought under enhanced biodiversity protection (ha) | Value | 8500000.00 | 24000000.00 | 33888828.00 |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
ARPA Protected Areas Fund increased by 150% above its current level of funds | Value | 27200000.00 | 42800000.00 | 121301000.00 |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
New Protected Areas created in Amazon. | Value | 24000000.00 | 13500000.00 | 3753366.00 |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Area studied for the creation of PAs | Value | 5000000.00 | 30000000.00 | 30000000.00 |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
At least 20 PA Action Plans implemented with communities and indigenous peoples in accordance with IPPF and RF. | Value | 0.00 | 20.00 | 23.00 |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
Consolidated Capacity Building Plan prepared and at least 80% of activities successfully executed. | Value | 0.00 | 80.00 | 100.00 |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
Map of Priority Areas updated | Value | 20071230 | 20170731 | 20160530 |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
Consolidation of 23 million hectares in consolidation stage 1 and 9 million hectares in stage 2. | Value | 8500000.00 | 32000000.00 | 38888828.00 |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
At least three PA management models tested and described in case studies | Value | 0.00 | 3.00 | 7.00 |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
Strategy for Conservation and Investment (ECI) applied and information updated in FAUC. | Value | Quality assessment of strategy | EIC and FAUC being used to guide operations. | ECI and FAUC updated annually and being used to gu |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
6 strategic studies and 4 PA financial sustainability plans implemented. | Value | 0.00 | 6.00 | 10.00 |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
Environment and Social Monitoring Framework developed and being updated on an annual basis including in situ information for PAs inStage 2 of consolidation. | Value | Environmental framework developed. | Environmental and Social Monitoring Framework deve | Environmental and social monitoring framework deve |
Date | January 27, 2012 | July 31, 2017 | June 9, 2016 | |
Comment |
Project management efficiency improved with real time tracking system (Cerebro II) implemented. | Value | Cerebro II tracking system in place. | Survey results used to improved management efficie | Cerebro II tracking system fully operational. |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
Program Communication Strategy developed and at least 80% of planned activities executed. | Value | ARPA Phase 1 communication strategy | At least 80 percent of planned activities | Communication Strategy 100% implemented. |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |
FAP Operational and making annual disbursements to selected PAs | Value | Zero | 100 percent of FAP's approved budget | 100% of annual disbursements |
Date | January 27, 2012 | July 31, 2017 | June 6, 2017 | |
Comment |