Financier | Commitments |
---|---|
IDA Credit | 40.00 |
P115592
Closed
Junko Onishi , Nancy Banegas Raudales
The Republic of Honduras
March 19, 2010
(as of board presentation)
June 29, 2010
October 29, 2010
US$ 40.00 million
Secretary of Development and Social Inclusion
2010
US$ 40.00 million
C
Not Applicable
December 31, 2018
BANK APPROVED
September 12, 2023
Financier | Commitments |
---|---|
IDA Credit | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 40.00 |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 40.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 15, 2019 | IDA-56030 | Int Charges | 164,829.80 |
Feb 15, 2019 | IDA-56030 | Int Charges | 156,825.64 |
Dec 15, 2018 | IDA-47740 | Int Charges | 4,308.70 |
Dec 15, 2018 | IDA-47740 | Int Charges | 4,308.70 |
Oct 15, 2018 | IDA-52940 | Int Charges | 68,344.12 |
Oct 15, 2018 | IDA-52940 | Int Charges | 42,867.42 |
Oct 15, 2018 | IDA-52940 | Int Charges | 42,867.42 |
Oct 15, 2018 | IDA-52940 | Loan Repay | 188,786.17 |
Nov 7, 2018 | IDA-47740 | Loan Cancel | 122,984.57 |
Sep 27, 2018 | IDA-52940 | Loan Disb | -1.86 |
Sep 27, 2018 | IDA-52940 | Loan Disb | -40,045.65 |
Jul 1, 2019 | IDA-56030 | Loan Disb | -14,280.15 |
Mar 19, 2019 | IDA-56030 | Loan Disb | 115,728.73 |
Oct 15, 2018 | IDA-52940 | Loan Repay | 342.93 |
Jul 1, 2019 | IDA-56030 | Loan Disb | -17,479.08 |
Apr 15, 2019 | IDA-52940 | Int Charges | 3,085.31 |
Jun 15, 2019 | IDA-47740 | Int Charges | 1,871.22 |
Jun 15, 2019 | IDA-47740 | Int Charges | 1,871.22 |
Jun 15, 2019 | IDA-47740 | Int Charges | 135,138.95 |
Jun 15, 2019 | IDA-47740 | Int Charges | 135,138.95 |
Apr 10, 2019 | IDA-56030 | Loan Disb | 703,602.30 |
Apr 15, 2019 | IDA-52940 | Int Charges | 41,813.82 |
Apr 15, 2019 | IDA-52940 | Int Charges | 68,834.97 |
Oct 15, 2017 | IDA-52940 | Int Charges | 747.10 |
Oct 15, 2017 | IDA-52940 | Int Charges | 43,401.47 |
Oct 15, 2017 | IDA-52940 | Int Charges | 43,401.47 |
Nov 6, 2017 | IDA-56030 | Loan Disb | 301,950.03 |
Jun 13, 2017 | IDA-56030 | Loan Disb | 9,974,717.00 |
Jun 15, 2017 | IDA-47740 | Int Charges | 3,811.79 |
Jun 15, 2017 | IDA-47740 | Int Charges | 3,811.79 |
Oct 15, 2017 | IDA-52940 | Int Charges | 71,725.67 |
Aug 30, 2017 | IDA-56030 | Loan Disb | 6,460,915.00 |
Sep 20, 2017 | IDA-47740 | Loan Disb | 503,000.00 |
Aug 15, 2017 | IDA-56030 | Int Charges | 53,362.34 |
Aug 15, 2017 | IDA-56030 | Int Charges | 1,068.48 |
Aug 15, 2017 | IDA-56030 | Int Charges | 55,813.71 |
Aug 15, 2017 | IDA-56030 | Int Charges | 55,813.71 |
Aug 7, 2017 | IDA-56030 | Loan Disb | 150,609.20 |
Apr 15, 2018 | IDA-52940 | Int Charges | 627.20 |
Feb 15, 2017 | IDA-56030 | Int Charges | 18,877.93 |
Feb 15, 2017 | IDA-56030 | Int Charges | 18,877.93 |
Feb 15, 2017 | IDA-56030 | Int Charges | 17,011.79 |
Apr 15, 2017 | IDA-52940 | Int Charges | 1,368.47 |
Apr 15, 2017 | IDA-52940 | Int Charges | 40,767.36 |
Apr 15, 2017 | IDA-52940 | Int Charges | 40,767.36 |
Apr 15, 2017 | IDA-52940 | Int Charges | 67,228.17 |
Jun 15, 2017 | IDA-47740 | Int Charges | 129,394.31 |
Jun 15, 2017 | IDA-47740 | Int Charges | 129,394.31 |
Jun 23, 2017 | IDA-47740 | Loan Disb | -1,089.48 |
Dec 28, 2015 | IDA-47740 | Loan Disb | 80,766.46 |
Oct 15, 2015 | IDA-52940 | Int Charges | 1,188.93 |
Oct 15, 2015 | IDA-52940 | Int Charges | 1,188.93 |
Oct 15, 2015 | IDA-52940 | Int Charges | 17,918.17 |
Oct 15, 2015 | IDA-52940 | Int Charges | 17,918.17 |
Oct 15, 2015 | IDA-52940 | Int Charges | 25,328.48 |
Dec 15, 2015 | IDA-47740 | Int Charges | 2,946.82 |
Dec 15, 2015 | IDA-47740 | Int Charges | 2,946.82 |
Dec 15, 2015 | IDA-47740 | Int Charges | 133,125.30 |
Dec 15, 2015 | IDA-47740 | Int Charges | 133,125.30 |
Nov 6, 2015 | IDA-47740 | Loan Disb | 291,416.30 |
Dec 4, 2015 | IDA-52940 | Loan Disb | 79,535.10 |
Jan 4, 2016 | IDA-52940 | Loan Disb | 53,718.15 |
Dec 4, 2015 | IDA-52940 | Loan Disb | 69,554.37 |
Feb 11, 2016 | IDA-56030 | Loan Disb | 1,000,000.00 |
Nov 12, 2015 | IDA-47740 | Loan Disb | 128,835.77 |
Feb 25, 2016 | IDA-52940 | Loan Disb | 48,702.49 |
Sep 16, 2016 | IDA-56030 | Loan Disb | 119,279.69 |
Apr 4, 2016 | IDA-47740 | Loan Disb | 16,834.45 |
Apr 4, 2016 | IDA-47740 | Loan Disb | 5,265.18 |
Feb 25, 2016 | IDA-52940 | Loan Disb | 90,281.19 |
Apr 15, 2016 | IDA-52940 | Int Charges | 6,460.02 |
Apr 15, 2016 | IDA-52940 | Int Charges | 24,774.65 |
Apr 15, 2016 | IDA-52940 | Int Charges | 24,774.65 |
Apr 15, 2016 | IDA-52940 | Int Charges | 40,912.27 |
Oct 15, 2016 | IDA-52940 | Int Charges | 371.54 |
Oct 15, 2016 | IDA-52940 | Int Charges | 25,740.68 |
Oct 15, 2016 | IDA-52940 | Int Charges | 25,740.68 |
Jun 15, 2016 | IDA-47740 | Int Charges | 2,018.78 |
Jun 15, 2016 | IDA-47740 | Int Charges | 2,018.78 |
Jun 15, 2016 | IDA-47740 | Int Charges | 135,682.97 |
Jun 15, 2016 | IDA-47740 | Int Charges | 135,682.97 |
Dec 15, 2014 | IDA-47740 | Int Charges | 723.18 |
Dec 15, 2014 | IDA-47740 | Int Charges | 723.18 |
Dec 15, 2014 | IDA-47740 | Int Charges | 132,604.58 |
Dec 15, 2014 | IDA-47740 | Int Charges | 132,604.58 |
Aug 11, 2014 | IDA-47740 | Loan Disb | 1,508,443.90 |
Sep 4, 2014 | IDA-47740 | Loan Disb | 246,046.95 |
Aug 5, 2014 | IDA-52940 | Loan Disb | 846,325.70 |
Jun 15, 2015 | IDA-47740 | Int Charges | 2,007.29 |
Jun 15, 2015 | IDA-47740 | Int Charges | 2,007.29 |
Jun 15, 2015 | IDA-47740 | Int Charges | 126,193.18 |
Jun 15, 2015 | IDA-47740 | Int Charges | 126,193.18 |
Sep 2, 2015 | IDA-52940 | Loan Disb | 177,233.31 |
Aug 19, 2015 | IDA-52940 | Loan Disb | 1,786,966.00 |
Aug 19, 2015 | IDA-47740 | Loan Disb | 976,228.00 |
Jul 9, 2015 | IDA-47740 | Loan Disb | 81,335.69 |
Apr 30, 2015 | IDA-52940 | Loan Disb | 45,411.45 |
Apr 15, 2015 | IDA-52940 | Int Charges | 183.77 |
Apr 15, 2015 | IDA-52940 | Int Charges | 183.77 |
Apr 15, 2015 | IDA-52940 | Int Charges | 14,084.96 |
Apr 15, 2015 | IDA-52940 | Int Charges | 14,084.96 |
Apr 15, 2015 | IDA-52940 | Int Charges | 23,781.14 |
Dec 28, 2015 | IDA-47740 | Loan Disb | 88,073.22 |
Dec 28, 2015 | IDA-47740 | Loan Disb | 58,995.36 |
Oct 15, 2014 | IDA-52940 | Int Charges | 2,287.84 |
Oct 15, 2014 | IDA-52940 | Int Charges | 2,287.84 |
Oct 15, 2014 | IDA-52940 | Int Charges | 3,813.06 |
Nov 14, 2014 | IDA-52940 | Loan Disb | 3,308,394.00 |
Dec 2, 2014 | IDA-47740 | Loan Disb | 314,607.44 |
Mar 3, 2014 | IDA-47740 | Loan Disb | 3,768,992.00 |
Feb 25, 2014 | IDA-47740 | Loan Disb | 310,903.62 |
Dec 17, 2013 | IDA-47740 | Int Charges | 3,157.82 |
Dec 17, 2013 | IDA-47740 | Int Charges | 3,157.82 |
Dec 17, 2013 | IDA-47740 | Int Charges | 112,288.22 |
Dec 17, 2013 | IDA-47740 | Int Charges | 112,288.22 |
Oct 25, 2013 | IDA-47740 | Loan Disb | 446,388.47 |
Jan 29, 2014 | IDA-47740 | Loan Disb | 530,497.94 |
Nov 19, 2013 | IDA-47740 | Loan Disb | 1,070,000.00 |
Apr 15, 2020 | IDA-52940 | Int Charges | 66,195.36 |
Apr 15, 2020 | IDA-52940 | Int Charges | 39,717.19 |
Apr 15, 2020 | IDA-52940 | Int Charges | 39,717.19 |
Apr 15, 2020 | IDA-52940 | Loan Repay | 783.23 |
Apr 15, 2020 | IDA-52940 | Loan Repay | 183,073.44 |
Jun 15, 2020 | IDA-47740 | Int Charges | 135,341.98 |
Jun 15, 2020 | IDA-47740 | Int Charges | 135,341.98 |
Oct 15, 2020 | IDA-52940 | Loan Repay | 189,707.80 |
Oct 15, 2020 | IDA-52940 | Int Charges | 40,310.30 |
Oct 15, 2020 | IDA-52940 | Int Charges | 40,310.30 |
Oct 15, 2020 | IDA-52940 | Loan Repay | 190.82 |
Jun 15, 2020 | IDA-47740 | Int Charges | 1,318.70 |
Jun 15, 2020 | IDA-47740 | Int Charges | 1,318.70 |
Aug 15, 2020 | IDA-56030 | Loan Repay | 410,955.53 |
Aug 15, 2020 | IDA-56030 | Int Charges | 176,835.40 |
Aug 15, 2020 | IDA-56030 | Int Charges | 169,363.50 |
Aug 15, 2020 | IDA-56030 | Int Charges | 176,835.40 |
Oct 15, 2020 | IDA-52940 | Int Charges | 66,796.18 |
Feb 15, 2021 | IDA-56030 | Int Charges | 166,569.00 |
Feb 15, 2021 | IDA-56030 | Loan Repay | 410,955.53 |
Feb 15, 2021 | IDA-56030 | Int Charges | 173,917.62 |
Feb 15, 2021 | IDA-56030 | Int Charges | 173,917.62 |
Dec 15, 2020 | IDA-47740 | Int Charges | 104,835.14 |
Nov 29, 2018 | IDA-56030 | Loan Disb | 236,890.97 |
Nov 5, 2018 | IDA-52940 | Loan Cancel | 63,213.50 |
Dec 20, 2018 | IDA-56030 | Loan Disb | 150,135.89 |
Aug 15, 2018 | IDA-56030 | Int Charges | 156,083.38 |
Aug 15, 2018 | IDA-56030 | Int Charges | 156,083.38 |
Aug 15, 2018 | IDA-56030 | Int Charges | 149,078.34 |
Jan 16, 2019 | IDA-56030 | Loan Disb | 179,433.55 |
Dec 15, 2018 | IDA-47740 | Int Charges | 132,508.97 |
Dec 15, 2018 | IDA-47740 | Int Charges | 132,508.97 |
Dec 14, 2018 | IDA-56030 | Loan Disb | 281,749.12 |
Oct 31, 2018 | IDA-52940 | Loan Disb | 3,199.85 |
Dec 14, 2018 | IDA-56030 | Loan Disb | 492,260.00 |
Sep 27, 2018 | IDA-47740 | Loan Disb | -44,783.52 |
Sep 27, 2018 | IDA-47740 | Loan Disb | -68,768.91 |
Feb 15, 2019 | IDA-56030 | Int Charges | 409.94 |
Feb 15, 2019 | IDA-56030 | Int Charges | 164,829.80 |
Apr 15, 2018 | IDA-52940 | Int Charges | 44,617.82 |
Apr 15, 2018 | IDA-52940 | Int Charges | 44,617.82 |
Feb 15, 2018 | IDA-56030 | Int Charges | 93.04 |
Feb 15, 2018 | IDA-56030 | Int Charges | 147,257.75 |
Feb 15, 2018 | IDA-56030 | Int Charges | 147,257.75 |
Feb 15, 2018 | IDA-56030 | Int Charges | 141,035.61 |
Dec 15, 2017 | IDA-47740 | Int Charges | 2,368.27 |
Dec 15, 2017 | IDA-47740 | Int Charges | 2,368.27 |
Dec 15, 2017 | IDA-47740 | Int Charges | 139,496.73 |
Dec 15, 2017 | IDA-47740 | Int Charges | 139,496.73 |
Apr 15, 2018 | IDA-52940 | Int Charges | 74,363.04 |
Dec 8, 2017 | IDA-56030 | Loan Disb | 153,464.77 |
Jul 27, 2018 | IDA-56030 | Loan Disb | 294,924.56 |
Jun 15, 2018 | IDA-47740 | Int Charges | 71.22 |
Jun 15, 2018 | IDA-47740 | Int Charges | 71.22 |
Jun 15, 2018 | IDA-47740 | Int Charges | 140,113.05 |
Jun 15, 2018 | IDA-47740 | Int Charges | 140,113.05 |
May 23, 2018 | IDA-56030 | Loan Disb | 972,270.00 |
Oct 15, 2016 | IDA-52940 | Int Charges | 41,512.52 |
Aug 23, 2016 | IDA-56030 | Int Charges | 157.78 |
Aug 23, 2016 | IDA-56030 | Int Charges | 157.78 |
Aug 23, 2016 | IDA-56030 | Int Charges | 151.11 |
Aug 23, 2016 | IDA-56030 | Int Charges | 7,099.98 |
Aug 23, 2016 | IDA-56030 | Int Charges | 7,099.98 |
Aug 23, 2016 | IDA-56030 | Int Charges | 6,799.98 |
Jan 27, 2017 | IDA-52940 | Loan Disb | 67,239.14 |
Feb 2, 2017 | IDA-56030 | Loan Disb | 400,662.70 |
Nov 2, 2016 | IDA-56030 | Loan Disb | 2,592,098.00 |
Nov 2, 2016 | IDA-52940 | Loan Disb | 1,788,900.00 |
Sep 29, 2016 | IDA-52940 | Loan Disb | 2,520,595.00 |
Dec 15, 2016 | IDA-47740 | Int Charges | 57.87 |
Dec 15, 2016 | IDA-47740 | Int Charges | 57.87 |
Dec 15, 2016 | IDA-47740 | Int Charges | 131,361.84 |
Dec 15, 2016 | IDA-47740 | Int Charges | 131,361.84 |
Dec 19, 2016 | IDA-56030 | Loan Disb | 154,069.66 |
Oct 31, 2016 | IDA-52940 | Loan Disb | 280,000.00 |
Mar 30, 2017 | IDA-56030 | Loan Disb | 203,393.12 |
Jun 23, 2017 | IDA-47740 | Loan Disb | -7,651.85 |
Mar 30, 2017 | IDA-52940 | Loan Disb | 17,063.38 |
Jun 26, 2014 | IDA-52940 | Loan Disb | 500,000.00 |
Jun 15, 2014 | IDA-47740 | Int Charges | 1,785.52 |
Jun 15, 2014 | IDA-47740 | Int Charges | 1,785.52 |
Jun 15, 2014 | IDA-47740 | Int Charges | 128,889.35 |
Jun 15, 2014 | IDA-47740 | Int Charges | 128,889.35 |
Apr 15, 2024 | IDA-52940 | Int Charges | 54,907.00 |
Feb 15, 2024 | IDA-56030 | Loan Repay | 410,955.53 |
Feb 15, 2024 | IDA-56030 | Int Charges | 156,410.92 |
Feb 15, 2024 | IDA-56030 | Int Charges | 156,410.92 |
Feb 15, 2024 | IDA-56030 | Int Charges | 149,802.00 |
Jun 15, 2024 | IDA-47740 | Int Charges | 42,165.18 |
Jun 15, 2024 | IDA-47740 | Int Charges | 42,165.18 |
Jun 15, 2024 | IDA-47740 | Int Charges | 83,055.12 |
Jun 15, 2024 | IDA-47740 | Int Charges | 83,055.12 |
Jun 15, 2024 | IDA-47740 | Loan Repay | 1,740,027.10 |
Mar 31, 2015 | IDA-56030 | Loan Commitment | 25,000,000.00 |
Aug 8, 2013 | IDA-52940 | Loan Commitment | 12,300,000.00 |
Jun 29, 2010 | IDA-47740 | Loan Commitment | 40,000,000.00 |
Dec 15, 2021 | IDA-47740 | Loan Repay | 1,844,247.50 |
Dec 15, 2021 | IDA-47740 | Int Charges | 124,486.68 |
Dec 15, 2021 | IDA-47740 | Int Charges | 124,486.68 |
Oct 15, 2022 | IDA-52940 | Loan Repay | 164,616.56 |
Oct 15, 2022 | IDA-52940 | Int Charges | 33,878.39 |
Oct 15, 2022 | IDA-52940 | Int Charges | 33,878.39 |
Oct 15, 2022 | IDA-52940 | Int Charges | 56,463.99 |
Oct 15, 2022 | IDA-52940 | Loan Repay | 7,117.16 |
Dec 15, 2022 | IDA-47740 | Int Charges | 29,422.59 |
Dec 15, 2022 | IDA-47740 | Int Charges | 29,422.59 |
Dec 15, 2022 | IDA-47740 | Loan Repay | 1,708,868.60 |
Dec 15, 2022 | IDA-47740 | Loan Repay | 48,576.97 |
Apr 15, 2023 | IDA-52940 | Loan Repay | 173,228.56 |
Feb 15, 2023 | IDA-56030 | Loan Repay | 410,955.53 |
Feb 15, 2023 | IDA-56030 | Int Charges | 162,246.48 |
Feb 15, 2023 | IDA-56030 | Int Charges | 162,246.48 |
Feb 15, 2023 | IDA-56030 | Int Charges | 155,391.00 |
Apr 15, 2023 | IDA-52940 | Int Charges | 35,267.51 |
Apr 15, 2023 | IDA-52940 | Int Charges | 35,267.51 |
Apr 15, 2023 | IDA-52940 | Loan Repay | 9,010.98 |
Apr 15, 2023 | IDA-52940 | Int Charges | 55,268.98 |
Aug 15, 2023 | IDA-56030 | Int Charges | 152,596.50 |
Aug 15, 2023 | IDA-56030 | Loan Repay | 410,955.53 |
Aug 15, 2023 | IDA-56030 | Int Charges | 159,328.69 |
Aug 15, 2023 | IDA-56030 | Int Charges | 159,328.69 |
Jun 15, 2023 | IDA-47740 | Loan Repay | 1,762,490.20 |
Jun 15, 2023 | IDA-47740 | Int Charges | 99,140.08 |
Aug 15, 2024 | IDA-56030 | Int Charges | 147,007.50 |
Aug 15, 2024 | IDA-56030 | Loan Repay | 410,955.53 |
Aug 15, 2024 | IDA-56030 | Int Charges | 153,493.12 |
Aug 15, 2024 | IDA-56030 | Int Charges | 153,493.12 |
Apr 15, 2024 | IDA-52940 | Int Charges | 32,944.19 |
Apr 15, 2024 | IDA-52940 | Int Charges | 32,944.19 |
Apr 15, 2024 | IDA-52940 | Loan Repay | 4,602.83 |
Jun 15, 2023 | IDA-47740 | Int Charges | 99,140.08 |
Jun 15, 2023 | IDA-47740 | Int Charges | 76,242.34 |
Jun 15, 2023 | IDA-47740 | Int Charges | 76,242.34 |
Dec 15, 2023 | IDA-47740 | Loan Repay | 1,741,643.20 |
Dec 15, 2023 | IDA-47740 | Int Charges | 50,051.13 |
Dec 15, 2023 | IDA-47740 | Int Charges | 50,051.13 |
Dec 15, 2023 | IDA-47740 | Loan Repay | 28,981.77 |
Oct 15, 2023 | IDA-52940 | Int Charges | 3,394.45 |
Oct 15, 2023 | IDA-52940 | Loan Repay | 176,229.88 |
Oct 15, 2023 | IDA-52940 | Int Charges | 33,443.62 |
Oct 15, 2023 | IDA-52940 | Int Charges | 33,443.62 |
Oct 15, 2023 | IDA-52940 | Int Charges | 55,739.40 |
Apr 15, 2024 | IDA-52940 | Loan Repay | 172,494.80 |
Dec 15, 2020 | IDA-47740 | Int Charges | 104,835.14 |
Dec 15, 2020 | IDA-47740 | Int Charges | 1,328.15 |
Dec 15, 2020 | IDA-47740 | Int Charges | 1,328.15 |
Dec 15, 2020 | IDA-47740 | Loan Repay | 1,898,972.50 |
Jun 15, 2021 | IDA-47740 | Int Charges | 37,618.88 |
Jun 15, 2021 | IDA-47740 | Int Charges | 37,618.88 |
Jun 15, 2021 | IDA-47740 | Loan Repay | 1,900,544.00 |
Jun 15, 2021 | IDA-47740 | Int Charges | 120,184.35 |
Jun 15, 2021 | IDA-47740 | Int Charges | 120,184.35 |
Apr 15, 2021 | IDA-52940 | Loan Repay | 192,196.47 |
Apr 15, 2021 | IDA-52940 | Int Charges | 40,077.34 |
Apr 15, 2021 | IDA-52940 | Int Charges | 40,077.34 |
Apr 15, 2021 | IDA-52940 | Int Charges | 66,795.54 |
Apr 15, 2021 | IDA-52940 | Int Charges | 392.35 |
Oct 15, 2021 | IDA-52940 | Loan Repay | 2,546.88 |
Oct 15, 2021 | IDA-52940 | Loan Repay | 187,400.17 |
Oct 15, 2021 | IDA-52940 | Int Charges | 38,896.00 |
Oct 15, 2021 | IDA-52940 | Int Charges | 38,896.00 |
Oct 15, 2021 | IDA-52940 | Int Charges | 64,826.64 |
Aug 15, 2021 | IDA-56030 | Loan Repay | 410,955.53 |
Aug 15, 2021 | IDA-56030 | Int Charges | 170,999.84 |
Aug 15, 2021 | IDA-56030 | Int Charges | 170,999.84 |
Aug 15, 2021 | IDA-56030 | Int Charges | 163,774.50 |
Apr 15, 2022 | IDA-52940 | Loan Repay | 1,761.75 |
Jun 15, 2022 | IDA-47740 | Loan Repay | 1,736,991.90 |
Jun 15, 2022 | IDA-47740 | Int Charges | 112,122.20 |
Jun 15, 2022 | IDA-47740 | Int Charges | 112,122.20 |
Jun 15, 2022 | IDA-47740 | Loan Repay | 21,787.48 |
Apr 15, 2022 | IDA-52940 | Loan Repay | 182,066.66 |
Apr 15, 2022 | IDA-52940 | Int Charges | 36,953.71 |
Apr 15, 2022 | IDA-52940 | Int Charges | 36,953.71 |
Apr 15, 2022 | IDA-52940 | Int Charges | 61,589.50 |
Feb 15, 2022 | IDA-56030 | Loan Repay | 410,955.53 |
Feb 15, 2022 | IDA-56030 | Int Charges | 168,082.08 |
Feb 15, 2022 | IDA-56030 | Int Charges | 168,082.08 |
Feb 15, 2022 | IDA-56030 | Int Charges | 160,980.00 |
Aug 15, 2022 | IDA-56030 | Int Charges | 158,185.50 |
Aug 15, 2022 | IDA-56030 | Loan Repay | 410,955.53 |
Aug 15, 2022 | IDA-56030 | Int Charges | 165,164.28 |
Aug 15, 2022 | IDA-56030 | Int Charges | 165,164.28 |
Dec 15, 2021 | IDA-47740 | Int Charges | 14,778.28 |
Dec 15, 2021 | IDA-47740 | Int Charges | 14,778.28 |
Apr 15, 2019 | IDA-52940 | Loan Repay | 187,072.05 |
Apr 15, 2019 | IDA-52940 | Int Charges | 41,813.82 |
Oct 15, 2019 | IDA-52940 | Loan Repay | 184,410.94 |
Oct 15, 2019 | IDA-52940 | Int Charges | 40,528.51 |
Oct 15, 2019 | IDA-52940 | Int Charges | 40,528.51 |
Oct 15, 2019 | IDA-52940 | Int Charges | 67,547.49 |
Aug 15, 2019 | IDA-56030 | Int Charges | 1,039.51 |
Aug 15, 2019 | IDA-56030 | Int Charges | 175,324.12 |
Aug 15, 2019 | IDA-56030 | Int Charges | 175,324.12 |
Aug 15, 2019 | IDA-56030 | Int Charges | 167,916.10 |
Oct 15, 2019 | IDA-52940 | Int Charges | 842.60 |
Jul 1, 2019 | IDA-56030 | Loan Cancel | 93,604.92 |
Feb 15, 2020 | IDA-56030 | Int Charges | -57.20 |
Feb 15, 2020 | IDA-56030 | Int Charges | 57.20 |
Feb 15, 2020 | IDA-56030 | Int Charges | 107.90 |
Feb 15, 2020 | IDA-56030 | Int Charges | 107.90 |
Feb 15, 2020 | IDA-56030 | Int Charges | 176,727.50 |
Feb 15, 2020 | IDA-56030 | Int Charges | 176,727.50 |
Feb 15, 2020 | IDA-56030 | Int Charges | 169,363.50 |
Dec 15, 2019 | IDA-47740 | Int Charges | 135,051.10 |
Dec 15, 2019 | IDA-47740 | Int Charges | 135,051.10 |
Dec 15, 2019 | IDA-47740 | Int Charges | 711.13 |
Dec 15, 2019 | IDA-47740 | Int Charges | 711.13 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2018-12-24 |
Financial Management | Moderately Satisfactory | 2018-12-24 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2018-12-24 |
Procurement | Moderately Satisfactory | 2018-12-24 |
Project Management | Satisfactory | 2018-12-24 |
Monitoring and Evaluation | Satisfactory | 2018-12-24 |
Overall Safeguards Rating | Moderately Satisfactory | 2018-12-24 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 08-07-2019 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 01-10-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |