Afghanistan Rural Access Project

Development Objective

The PDO is to enable (a) rural communities to benefit from all-season road access to basic services and facilities and (b) an earlyemergency response in the event of an eligible crisis or emergency.

Key Details

Project Details

  • P125961

  • Closed

  • Mohammad Ajmal Askerzoy , Abdul Khalili

  • Islamic Republic of Afghanistan

  • Afghanistan

  • May 22, 2012

  • (as of board presentation)

    June 26, 2012

  • August 12, 2012

  • US$ 325.00 million

  • Ministry of Transport,Ministry of Rural Reconstruction and Development

  • South Asia

  • 2012

  • US$ 325.00 million

  • B

  • August 1, 2023

  • December 31, 2020

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Afghanistan Resilience Trust Fund 200.00
IDA Grant 125.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 125.00
IBRD + IDA Commitment 125.00
Lending Instrument
Grant Amount 200.00
Total Project Cost** 325.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 4, 2014 IDA-H7920 Loan Disb 3,348,646.50
Jun 11, 2014 IDA-H7920 Loan Disb 1,643,181.60
Dec 22, 2014 IDA-H7920 Loan Disb 999,923.94
Jan 5, 2015 IDA-H7920 Loan Disb 937,491.94
Sep 2, 2014 IDA-H7920 Loan Disb 1,351,637.10
Sep 22, 2014 IDA-H7920 Loan Disb 914,543.06
Dec 15, 2014 IDA-H7920 Loan Disb 5,609,025.50
Feb 10, 2015 IDA-H7920 Loan Disb 10,619.00
Dec 23, 2014 IDA-H7920 Loan Disb 3,390,946.80
Nov 5, 2014 IDA-H7920 Loan Disb 1,917,260.90
Nov 5, 2014 IDA-H7920 Loan Disb 433,189.03
Nov 4, 2014 IDA-H7920 Loan Disb 928,034.50
Sep 30, 2014 IDA-H7920 Loan Disb 3,056,320.00
Sep 3, 2013 IDA-H7920 Loan Disb 2,715,762.50
Jul 15, 2013 IDA-H7920 Loan Disb 598,457.56
Dec 2, 2014 IDA-H7920 Loan Disb 999,691.70
Nov 24, 2014 IDA-H7920 Loan Disb 2,000,000.00
Dec 26, 2013 IDA-H7920 Loan Disb 5,000,000.00
Aug 7, 2013 IDA-H7920 Loan Disb 595,307.90
Nov 5, 2013 IDA-H7920 Loan Disb 1,000,000.00
Aug 20, 2013 IDA-H7920 Loan Disb 22,541.08
Sep 17, 2013 IDA-H7920 Loan Disb 612,771.75
Nov 5, 2013 IDA-H7920 Loan Disb 3,000,000.00
Jan 28, 2014 IDA-H7920 Loan Disb 784,506.00
Jun 26, 2012 IDA-H7920 Loan Commitment 125,000,000.00
Jun 30, 2021 IDA-H7920 Loan Cancel 207,850.22
Mar 16, 2020 IDA-H7920 Loan Disb -5,318.10
Dec 26, 2019 IDA-H7920 Loan Disb -194,515.12
Jul 12, 2016 IDA-H7920 Loan Disb 91,680.36
Aug 11, 2016 IDA-H7920 Loan Disb -504,175.30
Aug 12, 2015 IDA-H7920 Loan Disb 2,594,205.00
Nov 23, 2015 IDA-H7920 Loan Disb 1,057,940.00
Dec 30, 2015 IDA-H7920 Loan Disb 2,750,012.80
Oct 21, 2015 IDA-H7920 Loan Disb 260,100.00
Oct 21, 2015 IDA-H7920 Loan Disb 2,492,239.00
Oct 19, 2015 IDA-H7920 Loan Disb 347,391.00
Sep 8, 2015 IDA-H7920 Loan Disb 1,550,408.40
Dec 2, 2015 IDA-H7920 Loan Disb 2,948,025.00
Nov 9, 2015 IDA-H7920 Loan Disb 2,510,756.80
Nov 10, 2015 IDA-H7920 Loan Disb 1,257,830.40
Sep 26, 2016 IDA-H7920 Loan Disb 506,093.20
Sep 22, 2014 IDA-H7920 Loan Disb 8,000,000.00
Jul 22, 2014 IDA-H7920 Loan Disb 2,642,491.20
Mar 30, 2015 IDA-H7920 Loan Disb 1,606,268.80
Mar 31, 2015 IDA-H7920 Loan Disb 3,920,740.00
May 6, 2015 IDA-H7920 Loan Disb 1,271,607.00
Jun 24, 2015 IDA-H7920 Loan Disb 2,776,036.20
May 18, 2015 IDA-H7920 Loan Disb 877,808.90
Aug 27, 2015 IDA-H7920 Loan Disb 822,889.70
Jul 14, 2015 IDA-H7920 Loan Disb 1,090,500.00
Apr 13, 2015 IDA-H7920 Loan Disb 4,463,609.00
Jun 17, 2015 IDA-H7920 Loan Disb -1,271,454.90
Sep 29, 2015 IDA-H7920 Loan Disb 1,327,325.20
Nov 16, 2015 IDA-H7920 Loan Disb 1,607,665.10
Jun 8, 2015 IDA-H7920 Loan Disb 3,201,358.50
Aug 3, 2015 IDA-H7920 Loan Disb 1,271,607.00
Jan 9, 2014 IDA-H7920 Loan Disb 1,000,000.00
Apr 15, 2014 IDA-H7920 Loan Disb 2,500,000.00
Apr 9, 2014 IDA-H7920 Loan Disb 2,000,000.00
Apr 29, 2014 IDA-H7920 Loan Disb 1,206,061.40
Jan 27, 2014 IDA-H7920 Loan Disb 3,823,866.80
Mar 10, 2014 IDA-H7920 Loan Disb 2,337,643.50
Apr 16, 2014 IDA-H7920 Loan Disb 1,998,641.00
Jul 9, 2014 IDA-H7920 Loan Disb 491,589.94
May 27, 2014 IDA-H7920 Loan Disb 513,884.97
Jun 2, 2014 IDA-H7920 Loan Disb 1,371,086.40

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Satisfactory 2020-08-13
Procurement Satisfactory 2020-08-13
Project Management Satisfactory 2020-08-13
Overall Implementation Progress (IP) Moderately Satisfactory 2020-08-13
Progress towards achievement of PDO Satisfactory 2020-08-13
Monitoring and Evaluation Satisfactory 2020-08-13

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-17-2021
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Share of rural population with access to an all-season roadValue58.0065.000.00
    DateDecember 15, 2012August 4, 2021
    Comment
  • Number of rural people with access to an all-season roadValue13500000.0014900000.000.00
    DateDecember 15, 2012June 21, 2018
    Comment
  • Percent reduction in travel time by a 4-wheel drive vehicle along roads improved under the projectValue0.0030.000.00
    DateAugust 4, 2021August 4, 2021
    Comment
  • Increased frequency of trips to nearest essential services (including town markets, schools and health facilities) connected by the roads improved under the projectValue0.0015.000.00
    DateAugust 4, 2021August 4, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Km of gravel surfaced secondary roads rehabilitatedValue0.001000.000.00
    DateAugust 4, 2021August 4, 2021
    Comment
  • Km of gravel surfaced tertiary roads rehabilitatedValue0.001420.000.00
    DateAugust 4, 2021August 4, 2021
    Comment
  • Complete Road InventoryValue0.00100.000.00
    DateAugust 4, 2021August 4, 2021
    Comment
  • No of emergencies addressedValue0.000.000.00
    DateAugust 4, 2021August 4, 2021
    Comment
  • Km of asphalt surfaced secondary roads rehabilitatedValue0.00250.000.00
    DateAugust 4, 2021August 4, 2021
    Comment
  • Construction of bridges on tertiary roadsValue0.001800.000.00
    DateAugust 4, 2021August 4, 2021
    Comment
  • Improved Network Management system in placeValueNoYes
    DateAugust 4, 2021August 4, 2021
    Comment
  • Roads constructed, RuralValue0.002670.000.00
    DateAugust 4, 2021August 4, 2021
    Comment
  • Km of tertiary roads under routine and periodic maintenance schemeValue0.003750.000.00
    DateAugust 4, 2021August 4, 2021
    Comment
  • Design standards developed and adoptedValueNoYes
    DateAugust 4, 2021August 4, 2021
    Comment
  • Construction of bridges on secondary roadsValue0.001351.000.00
    DateAugust 4, 2021August 4, 2021
    Comment
  • Cost estimation system developed and fully functionalValueNoYes
    DateAugust 4, 2021August 4, 2021
    Comment
  • Km of secondary roads under routine and periodic maintenance schemeValue0.001870.000.00
    DateAugust 4, 2021August 4, 2021
    Comment
  • Financial Management System in MRRD and MPW developed and functionalValueNoYes
    DateAugust 4, 2021August 4, 2021
    Comment
  • No. of Jobs created along the project roads (labor days)Value0.002800000.000.00
    DateAugust 4, 2021August 4, 2021
    Comment