Skip to Main Navigation

Balochistan Disaster Management Project

Development Objective

The objective of the project is to strengthen the capacity of PDMA Balochistan to prepare for and respond to natural disasters.

Key Details

Project Details

  • P127253

  • Closed

  • Haris Khan

  • Economic Affairs Division

  • Pakistan

  • June 27, 2012

  • (as of board presentation)

    June 27, 2012

  • July 19, 2012

  • US$ 5.00 million

  • Provincial Disaster Management Authority (PDMA) Balochistan

  • South Asia

  • 2012

  • US$ 5.00 million

  • C

  • Not Applicable

  • June 12, 2016

  • BANK APPROVED

  • August 15, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
MDTF for Crisi Affected Areas of NWFP/FATA/Balochistan 5.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 5.00
Total Project Cost** 5.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2015-12-22
Progress towards achievement of PDO Satisfactory 2015-12-22
Procurement Satisfactory 2015-12-22
Monitoring and Evaluation Satisfactory 2015-12-22
Project Management Satisfactory 2015-12-22
Financial Management Satisfactory 2015-12-22

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-12-2017
OutcomesSubstantial
Risk to Development OutcomeHigh
Bank PerformanceSubstantial
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-20-2017PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualityModestN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Enhanced capacity at PDMA Balochistan for implementing CBDRM initiativesValue0.000.000.00
    Date
    Comment
  • Improved disaster response mechanism at PDMA Balochistan, evidenced by:Value
    Date
    Comment
  • Increased awareness of the hazard and risk environment in Quetta, evidenced by:Value
    Date
    Comment
  • Number of Master trainers trainedValue0.0020.0015.00
    DateJuly 19, 2012December 15, 2015June 12, 2016
    Comment
  • Number of training sessions for responders in selected union councils in QuettaValue0.005.005.00
    DateJuly 19, 2012December 15, 2015June 12, 2016
    Comment
  • Instruction materials on CBDRM available for dissemination to communitiesValue0.0020000.0010000.00
    DateJuly 19, 2012December 15, 2015June 12, 2016
    Comment
  • SOPs for disaster response prepared and operationalizedValueResponse SOPs 2008SOPs for emergency response were prepared and testFinal SOPs approved and implemented
    DateDecember 15, 2015June 12, 2016
    Comment
  • Number of drills / simulation exercises completed to assess operational coordination, preparedness and emergency protocolsValue012
    DateJuly 19, 2012December 15, 2015June 12, 2016
    Comment
  • DMIS database established and populated by data collected during hazard and risk assessmentValueZeroData generated from the hazard and risk assessmentCollection in DMIS of data generated through hazar
    DateJuly 19, 2012December 15, 2015June 12, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increased capacity of PDMA Balochistan to engage with local communities for improved preparednessValue0.000.000.00
    Date
    Comment
  • Enhanced capacity at PDMA Balochistan to collect, manage and communicate informationValue
    DateJune 12, 2016
    Comment
  • Development and effective implementation of disaster response procedures at PDMAValue
    Date
    Comment
  • Increased technical capacity at PDMA to manage the implementation and dissemination of hazard and risk assessmentsValue
    Date
    Comment
  • Number of CBDRM training sessions conducted by master trainers in selected union councils in QuettaValue0.005.005.00
    DateDecember 15, 2015June 12, 2016
    Comment
  • Number of pilot stockpiles established in Quetta based on Logistics PlanValue0.001.002.00
    DateDecember 15, 2015June 12, 2016
    Comment
  • Instruction materials on CBDRM available for dissemination to communitiesValue0.0020000.0010000.00
    DateDecember 15, 2015June 12, 2016
    Comment
  • Provincial CBDRM Plan developedValueNo CBDRM Plan availableThe draft CBDRM program is currently being finaliz
    Date
    Comment
  • Logistics Plan developed for emergency stockpiles in selected districtsValueNo logistics plan availableIn May 2014, PDMA awarded the contract to a consul
    Date
    Comment
  • DMIS database establishedValueZeroData generated from the hazard and risk assessmentDMIS database set up
    DateJuly 19, 2012December 15, 2015June 12, 2016
    Comment
  • Enhanced communications systems in place at the Provincial Emergency Operations Center (PEOC)ValueBasic SystemsImproved communications systems are in place, inclEmergency communications equipment operationalized
    DateJuly 19, 2012December 18, 2015June 12, 2016
    Comment
  • Number of exposure visits by PDMA Balochistan staff undertaken and knowledge products producedValue04 exposure visits completed4
    DateJuly 19, 2012December 15, 2015June 12, 2016
    Comment
  • Balochistan DRM Plan 2008 reviewed and updatedValueBalochistan DRM Plan 2008Balochistan DRM Plan (2014 – 2019) has been preparDraft strategic updates agreed after discussion wi
    DateJuly 19, 2012December 18, 2015June 30, 2015
    Comment
  • PDMA capacity assessment undertaken and enhancement plan preparedValueNo capacity assessment availableCapacity assessment completed and capacity enhanceCapacity enhancement plan discussed with stakehold
    DateJuly 19, 2012December 15, 2015June 12, 2016
    Comment
  • Number of drills / simulation exercises completed to assess operational coordination, preparedness and emergency protocolsValue012
    DateJuly 19, 2012December 15, 2015June 12, 2016
    Comment
  • SOPs for PDMA on disaster response preparedValueNoneSOPs for emergency response were prepared and testFinal SOPs approved and implemented
    DateJuly 19, 2012December 15, 2015June 12, 2016
    Comment
  • Scoping exercise completed and methodology for hazard and risk assessment finalizedValueZeroHazard and Risk Assessment of Quetta City completeScoping excersie completed and methodology finaliz
    DateDecember 15, 2015June 12, 2016
    Comment
  • Data collected and collated in the DMIS repositoryValueNo system availableData generated from the hazard and risk assessmentCollection in the DMIS of data generated through h
    DateDecember 15, 2015June 12, 2016
    Comment
  • Information collected during the hazard and risk assessment on sources of risk available to all departments and agencies responsible for development planning in the provincial capitalValueNo risk assessment availableThe hazard and risk assessment of Quetta has been Results from hazard and risk assessment published
    DateDecember 15, 2015June 12, 2016
    Comment