| Financier | Commitments | 
|---|---|
| Borrower/Recipient | 63.70 | 
| EC: European Commission | 16.40 | 
| IDA Credit | 144.90 | 
P149610
Active
Bakyt Arystanov , Shavkat Rakhmatullaev
Republic of Uzbekistan
November 18, 2015
(as of board presentation)
June 30, 2017
December 29, 2017
US$ 225.00 million
Project Implementation Unit under the Ministry of Water of Uzbekistan
2017
US$ 161.30 million
B
Not Applicable
June 30, 2026
TBD
Bank Approved
February 1, 2024
| Financier | Commitments | 
|---|---|
| Borrower/Recipient | 63.70 | 
| EC: European Commission | 16.40 | 
| IDA Credit | 144.90 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | N/A | 
| IDA Commitment | 144.90 | 
| IBRD + IDA Commitment | 144.90 | 
| Lending Instrument | |
|---|---|
| Grant Amount | 16.40 | 
| Total Project Cost** | 225.00 | 
| Name | Review | Date | 
|---|---|---|
| Counterpart Funding | Moderately Satisfactory | 2025-08-19 | 
| Financial Management | Satisfactory | 2025-08-19 | 
| Monitoring and Evaluation | Satisfactory | 2025-08-19 | 
| Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-08-19 | 
| Procurement | Satisfactory | 2025-08-19 | 
| Progress towards achievement of PDO | Moderately Satisfactory | 2025-08-19 | 
| Project Management | Satisfactory | 2025-08-19 | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Improved quality of irrigation and drainage service delivery | Value | 1.50 | 2.10 | 2.50 | 
| Date | January 29, 2016 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| Irrigation efficiency (Water withdrawn used for crop production) | Value | 30.00 | 35.00 | 35.00 | 
| Date | January 29, 2016 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| Relative irrigation deficit (water deficit/water demand) | Value | 30.00 | 25.00 | 20.00 | 
| Date | January 29, 2016 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Area provided with new/improved irrigation or drainage services | Value | 0.00 | 48410.00 | 103000.00 | 
| Date | January 29, 2016 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| Asset management processes established by project BAISs, AISs and WCAs | Value | 0 | 1 | 49 | 
| Date | January 29, 2016 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| Farmers adopting improved agricultural technology | Value | 0.00 | 4630.00 | 1000.00 | 
| Date | January 29, 2016 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| Farmers adopting improved agricultural technology - Female | Value | 0.00 | 0.00 | 250.00 | 
| Date | January 29, 2016 | January 12, 2018 | August 31, 2024 | |
| Comment | 
| Female beneficiaries | Value | 0.00 | 20.00 | 20.00 | 
| Date | January 29, 2016 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| Grievances registered related to delivery of project benefits that are resolved | Value | 0.00 | 80.00 | 80.00 | 
| Date | January 29, 2016 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| Increased collection rate by the WCAs in the project area | Value | 40.00 | 55.00 | 60.00 | 
| Date | March 24, 2017 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| Land area under sustainable landscape management practices | Value | 0.00 | 5800.00 | 103000.00 | 
| Date | March 24, 2017 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| Number of people receiving rural advisory services | Value | 0.00 | 10090.00 | 2000.00 | 
| Date | March 24, 2017 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| Operational water user associations created and/or strengthened (number) | Value | 0.00 | 8.00 | 12.00 | 
| Date | January 29, 2016 | December 18, 2023 | August 31, 2024 | |
| Comment | 
| Percentage of beneficiaries reporting improved engagement (in planning and feedback) and responsiveness to Farmer Field Schools (Citizen Engagement Indicator) | Value | 0.00 | 94.00 | 100.00 | 
| Date | March 24, 2017 | December 18, 2023 | August 31, 2024 | |
| Comment |