EC Guayaquil Wastewater Management Project

Abstract*

The project development objective for the Guayaquil Wastewater Management Project for Ecuador is to increase access to improved sanitation services and to reduce wastewater pollution in selected areas of the City of Guayaquil. The proposed Project will benefit over one million residents in the southern districts of Guayaquil and riparian districts of the Estero Salado where sewer mains will be rehabilitated and new household connections will be installed...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to increase access to improved sanitation services and to reduce wastewater pollution inselected areas of the City of Guayaquil.

Key Details

Project Details

  • P151439

  • Active

  • Malva Baskovich , Berenice Flores Arias Uijtewaal

  • EMAPAG EP

  • Ecuador

  • December 19, 2014

  • (as of board presentation)

    April 22, 2015

  • September 15, 2015

  • US$ 205.00 million

  • A

  • Not Applicable

  • April 30, 2026

  • TBD

  • Bank Approved

  • February 14, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 42.80
EC: European Investment Bank 102.50
International Bank for Reconstruction and Development 102.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 102.50
IDA Commitment N/A
IBRD + IDA Commitment 102.50
Lending Instrument
Grant Amount 102.50
Total Project Cost** 247.80

Summary Status of World Bank Financing (US$ Millions) as of October 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of October 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Moderately Satisfactory 2025-06-27
Financial Management Satisfactory 2025-06-27
Monitoring and Evaluation Satisfactory 2025-06-27
Overall Implementation Progress (IP) Moderately Satisfactory 2025-06-27
Procurement Moderately Satisfactory 2025-06-27
Progress towards achievement of PDO Moderately Unsatisfactory 2025-06-27
Project Management Moderately Satisfactory 2025-06-27

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.001100000.002000000.00
    DateSeptember 15, 2015November 30, 2023April 30, 2026
    Comment
  • Female beneficiariesValue0.0050.0050.00
    DateSeptember 15, 2015September 15, 2017April 28, 2023
    Comment
  • People in urban areas provided with access to improved sanitation services under the projectValue0.00137765.00139680.00
    DateSeptember 15, 2015November 30, 2023April 30, 2026
    Comment
  • Share of poor people in urban areas provided with access to improved sanitation services under the projectValue0.000.0020.00
    DateSeptember 15, 2015September 15, 2017April 28, 2023
    Comment
  • Volume(mass) of BOD pollution load removed by treatment plant under the projectValue0.005412.0012000.00
    DateSeptember 15, 2015November 30, 2023April 30, 2026
    Comment
  • Water & sanitation utility operating ratioValue0.810.830.83
    DateSeptember 15, 2015November 30, 2023April 30, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Citizen Engagement: Number of beneficiary households that sign a certification that they are satisfied with the works conducted in their houses.Value0.008995.0013700.00
    DateSeptember 15, 2015November 30, 2023April 30, 2026
    Comment
  • Commissioning of Las Esclusas WWTPValueNoNoYes
    DateSeptember 15, 2015November 30, 2023April 30, 2026
    Comment
  • Commissioning of Los Merinos WWTPValueNoNoYes
    DateFebruary 14, 2018November 30, 2023April 30, 2026
    Comment
  • Meters of sewers mains rehabilitated under the projectValue0.0038804.0038804.00
    DateSeptember 15, 2015November 30, 2023April 30, 2023
    Comment
  • New household sewer connections constructed under the projectValue0.0028701.0029100.00
    DateSeptember 15, 2015November 30, 2023April 30, 2026
    Comment
  • Percentage of women that works in social-related activitiesValue0.0039.4040.00
    DateFebruary 21, 2018November 30, 2023April 30, 2026
    Comment
  • Share of surveyed beneficiaries (gender disaggregated) that feel project investments reflect their needsValue0.000.0085.00
    DateSeptember 15, 2015November 30, 2023April 30, 2026
    Comment
  • Share of the monthly average effluent from Las Esclusas WWTP outlet discharged into the Guayas River is compliant with regulatory quality standard for BDO, TSS and total coliformsValue0.00100.00100.00
    DateSeptember 15, 2015November 30, 2023April 30, 2026
    Comment
  • Share of the monthly average effluent from Los Merinos WWTP outlet discharged into the Daule River is compliant with regulatory quality standard for BDO, TSS and total coliformsValue0.000.00100.00
    DateFebruary 14, 2018November 30, 2023April 30, 2026
    Comment
  • Start of Construction of Las Esclusas WWTPValueNoYesYes
    DateSeptember 15, 2015November 30, 2023April 30, 2023
    Comment
  • Start of Construction of Los Merinos WWTPValueNoYesYes
    DateFebruary 14, 2018November 30, 2023April 30, 2026
    Comment
  • The Los Merinos WWTP Forest Compensation Plan has being developed and approved by National Environmental AuthoritiesValueNoYesYes
    DateApril 30, 2018November 30, 2023April 30, 2026
    Comment
  • Water quality Monitoring System for the Daule finalized and system operationalValueNoYesYes
    DateSeptember 15, 2015November 30, 2023April 30, 2026
    Comment