Financier | Commitments |
---|---|
Africa Catalytic Growth Fund (ACGF) | 3.50 |
IDA Grant | 10.00 |
P151443
Closed
Philippe Auffret
N/A
April 14, 2016
(as of board presentation)
May 10, 2016
July 11, 2016
US$ 13.50 million
N/A
2016
US$ 13.50 million
B
Not Applicable
September 20, 2019
TBD
BANK APPROVED
January 17, 2024
Financier | Commitments |
---|---|
Africa Catalytic Growth Fund (ACGF) | 3.50 |
IDA Grant | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 10.00 |
IBRD + IDA Commitment | 10.00 |
Lending Instrument | |
---|---|
Grant Amount | 3.50 |
Total Project Cost** | 13.50 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Students enrolled in classrooms built/rehabilitated by the Project | Value | 0.00 | 11029.00 | 20000.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
Direct project beneficiaries | Value | 0.00 | 85147.00 | 137000.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 55597.00 | 100000.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
Beneficiaries from hydro-agricultural systems improved by the Project | Value | 0.00 | 3786.00 | 3800.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
People with access to an all-season road build/rehabilitated by the Project | Value | 0.00 | 11250.00 | 73000.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
No interruption of the 2013/14 or 2014/15 school year due to the non payment of current salaries from Project effectiveness until the end of the 2014/15 school year with gradations | Value | 0.00 | 0.00 | 0.00 |
Date | May 7, 2014 | December 31, 2015 | September 20, 2019 | |
Comment | The First Additional Financing became effective on May 7, 2014 | Highly Satisfactory – Teachers were on strike for 2 days (May 15 and May 16, 2014) form Project effectiveness until the end of the2013/14 school year | The proposed Additional Financing would not finance teachers’ and health workers’ salaries. |
Female beneficiaries | Value | 0.00 | 49.00 | 50.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
1.1 Community-Development Plans completed | Value | 0.00 | 140.00 | 180.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
1.2 Tabancas with a Community-Development Plans completed | Value | 0.00 | 708.00 | 850.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. | In Guinea Bissau, communities are called Tabancas. These tabancas may be small. In practice, for the implementation of theProject,several tabancas group together to define their development plans and select a micro-project. |
1.3 Population with a Community-Development Plans completed | Value | 0.00 | 167244.00 | 200000.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
2.1 Community-based sub-projects initiated | Value | 0.00 | 252.00 | 355.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
2.2 Community-based sub-projects completed | Value | 0.00 | 225.00 | 355.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 165.00 | 270.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
Roads constructed, Rural | Value | 0.00 | 0.00 | 0.00 |
Date | August 4, 2009 | December 31, 2015 | December 31, 2017 | |
Comment | The Project became effective on August 4, 2009. | No new feeder road has been completed yet. | The Project does not expect to finance the construction of new rural roads. |
2.3 Community-based sub-projects functional and properly maintained two years after completion | Value | 0.00 | 87.00 | 75.00 |
Date | August 4, 2009 | December 31, 2015 | December 31, 2017 | |
Comment | Not applicable when the Project became effective on August 4, 2009. | At least 75% of community-based micro-projects are expected to be functional and properly maintained 2 years after completion. |
Roads rehabilitated, Rural | Value | 0.00 | 34.50 | 230.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions. | Value | 0.00 | 150.00 | 275.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | The Project became effective on August 4, 2009. |
2.8. Land benefiting from hydro-agricultural systems improved by the Project | Value | 0.00 | 635.00 | 659.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment |
3.1 Operating ratio | Value | 0.00 | 13.00 | 20.00 |
Date | August 4, 2009 | December 31, 2015 | December 31, 2017 | |
Comment | The operational ratio is expected to be below 20% at Project completion. |
3.2 Technical audit of community-based sub-projects completed | Value | 0.00 | 1.00 | 3.00 |
Date | August 4, 2009 | December 31, 2015 | September 20, 2019 | |
Comment | A first technical audit was completed in February 2014. | Three technical audits are expected to be completed during Project implementation. The second technical audit is expected to becompleted in 2016. A last Technical Audit could take place in early 2019 |
Percentage of teachers on the Folha Única whose salary has been paid by the Project | Value | 0.00 | 100.00 | 90.00 |
Date | February 12, 2014 | December 31, 2015 | September 20, 2019 | |
Comment | The PPA became effective on February 12, 2014. | The proposed Additional Financing would not finance teachers’ and health workers’ salaries. |
Percentage of health workers on the Folha Única whose salary has been paid by the Project | Value | 0.00 | 100.00 | 90.00 |
Date | February 12, 2014 | December 31, 2015 | September 20, 2019 | |
Comment | The PPA became effective on February 12, 2014. | The proposed Additional Financing would not finance teachers’ and health workers’ salaries. |
5.1 Number of community health agents who receive training on Ebola prevention | Value | 0.00 | 63.00 | 1000.00 |
Date | August 31, 2014 | December 31, 2015 | September 20, 2019 | |
Comment | The proposed Additional Financing would not the Ebola prevention component. |
Beneficiaries of Safety Nets programs (number) | Value | 0.00 | 0.00 | 0.00 |
Date | March 31, 2016 | December 31, 2015 | September 20, 2019 | |
Comment |
Beneficiaries of Safety Nets programs - Female (number) | Value | 0.00 | 0.00 | 0.00 |
Date | March 31, 2016 | December 31, 2015 | September 20, 2019 | |
Comment |
Beneficiaries of Safety Nets programs - Unconditional cash transfers (number) | Value | 0.00 | 0.00 | 2000.00 |
Date | March 31, 2016 | December 31, 2015 | September 20, 2019 | |
Comment |