Financier | Commitments |
---|---|
Japan Social Development Fund | 2.80 |
P153986
Closed
Sean Bradley
Solomon Islands
July 20, 2015
(as of board presentation)
September 18, 2017
April 10, 2018
US$ 2.80 million
Ministry of Mines, Energy & Rural Electrification,Solomon Islands Electricity Authority
2018
US$ 2.80 million
N/A
Not Applicable
May 31, 2023
BANK APPROVED
October 10, 2023
Financier | Commitments |
---|---|
Japan Social Development Fund | 2.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 2.80 |
Total Project Cost** | 2.80 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2023-05-16 |
Overall | Moderable | 2023-05-16 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2023-05-16 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-29-2023 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Benefit sharing fund legally registered | Value | No | Yes | Yes |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 4200.00 | 4936.00 |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |
Percentage of target beneficiaries that participated in consultation meetings regarding benefit sharing institutional arrangements | Value | 0.00 | 60.00 | 76.00 |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |
Female beneficiaries | Value | 0.00 | 50.00 | 48.00 |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |
Percentage of target beneficiaries that participated in consultation meetings regarding benefit sharing institutional arrangements of which are women | Value | 0.00 | 50.00 | 55.00 |
Date | September 1, 2017 | June 30, 2021 | May 31, 2023 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of Knowledge dissemination events on the lessons of the benefit sharing pilot organized | Value | 0.00 | 1.00 | 0.00 |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |
Number of people in rural areas provided with access to Improved Water Sources under the project | Value | 0.00 | 4000.00 | 4360.00 |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |
Operations Manual for the benefit sharing fund developed | Value | No | Yes | Yes |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |
Transmission lines constructed or rehabilitated under the project | Value | 0.00 | 10.00 | 8.70 |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |
Number of mid-term and final impact assessment reports prepared | Value | 0.00 | 2.00 | 2.00 |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |
Beneficiaries of job-focused interventions | Value | 0.00 | 300.00 | 399.00 |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |
Percentage of people consulted during the project that feel their views are reflected in the design of the Community Benefit Sharing Fund | Value | 0.00 | 75.00 | 81.00 |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |
Beneficiaries of job-focused interventions - Female | Value | 0.00 | 150.00 | 169.00 |
Date | September 1, 2017 | December 31, 2022 | May 31, 2023 | |
Comment |