Abstract*

The development objective of the Punjab Cities Program for Pakistan is to strengthen the performance of participating urban local governments in urban management and service delivery.The proposed Punjab Cities Program (PCP) is aligned with the World Bank Group’s Pakistan Country Partnership Strategy (CPS) FY15-20.The operation is expected to contribute to the Bank’s overarching goals of ending extreme poverty and promoting shared prosperity by delivering...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Operation is to strengthen the performance of participating urban local governments in urban management and service delivery.

Key Details

Project Details

  • P156972

  • Active

  • Shahnaz Arshad

  • Economic Affairs Division

  • Pakistan

  • January 25, 2018

  • (as of board presentation)

    May 25, 2018

  • May 29, 2018

  • US$ 236.00 million

  • Punjab Municipal Development Funds Company,Planning and Development Board, Government of Punjab,Local Government and Community Development Department

  • South Asia

  • 2018

  • US$ 200.00 million

  • B

  • May 31, 2024

  • August 29, 2025

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 7.00
IDA Credit 200.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 200.00
IBRD + IDA Commitment 200.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 236.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 15, 2023 IDA-62430 Int Charges 652,733.60
Jun 21, 2023 IDA-62430 Loan Disb 41,386,088.00
Mar 17, 2023 IDA-62430 Loan Disb 9,182,048.00
Sep 7, 2023 IDA-62430 Loan Disb 202,766.69
Oct 15, 2023 IDA-62430 Int Charges 37,031.77
Oct 15, 2023 IDA-62430 Loan Repay 2,974,042.20
Oct 15, 2023 IDA-62430 Int Charges 535,190.40
Oct 15, 2023 IDA-62430 Int Charges 535,190.40
Oct 15, 2023 IDA-62430 Int Charges 891,983.94
Apr 15, 2024 IDA-62430 Loan Repay 75,564.92
Apr 15, 2020 IDA-62430 Int Charges 61,741.38
Oct 15, 2020 IDA-62430 Int Charges 65.07
Oct 15, 2020 IDA-62430 Int Charges 65.07
Oct 15, 2020 IDA-62430 Int Charges 147,815.16
Oct 15, 2020 IDA-62430 Int Charges 147,815.16
Oct 15, 2020 IDA-62430 Int Charges 245,952.94
Jun 19, 2020 IDA-62430 Loan Disb 500,951.38
Jun 19, 2020 IDA-62430 Loan Disb 42,644,304.00
Mar 11, 2021 IDA-62430 Loan Disb 491,067.34
Apr 15, 2021 IDA-62430 Int Charges 520.27
Apr 15, 2021 IDA-62430 Int Charges 209,682.12
Apr 15, 2021 IDA-62430 Int Charges 209,682.12
Apr 15, 2021 IDA-62430 Int Charges 349,470.16
Jun 23, 2021 IDA-62430 Loan Disb 53,933,856.00
Sep 15, 2021 IDA-62430 Loan Disb 1,645,630.00
Oct 15, 2021 IDA-62430 Int Charges 330,269.30
Oct 15, 2021 IDA-62430 Int Charges 330,269.30
Oct 15, 2021 IDA-62430 Int Charges 556,826.20
Oct 15, 2021 IDA-62430 Int Charges 3,826.42
Oct 15, 2021 IDA-62430 Int Charges 3,826.42
Apr 25, 2022 IDA-62430 Loan Disb 2,006,978.10
Apr 15, 2022 IDA-62430 Int Charges 2,612.86
Jun 13, 2019 IDA-62430 Loan Disb 9,524,053.00
Oct 15, 2019 IDA-62430 Int Charges 39,949.16
Oct 15, 2019 IDA-62430 Int Charges 23,969.50
Oct 15, 2019 IDA-62430 Int Charges 23,969.50
Feb 3, 2020 IDA-62430 Loan Disb 1,200,000.00
Apr 15, 2020 IDA-62430 Int Charges 170.68
Apr 15, 2020 IDA-62430 Int Charges 170.68
Apr 15, 2020 IDA-62430 Int Charges 36,874.14
Apr 15, 2024 IDA-62430 Int Charges 584,485.30
Apr 15, 2024 IDA-62430 Loan Repay 2,913,121.50
Apr 15, 2020 IDA-62430 Int Charges 36,874.14
Apr 15, 2024 IDA-62430 Int Charges 584,485.30
Apr 15, 2024 IDA-62430 Int Charges 974,142.25
Mar 6, 2024 IDA-62430 Loan Disb 1,530,828.50
Jun 21, 2024 IDA-62430 Loan Disb 13,117,941.00
May 25, 2018 IDA-62430 Loan Commitment 200,000,000.00
Apr 15, 2022 IDA-62430 Int Charges 2,612.86
Apr 15, 2022 IDA-62430 Int Charges 398,730.16
Apr 15, 2022 IDA-62430 Int Charges 398,730.16
Apr 15, 2022 IDA-62430 Int Charges 668,905.06
Oct 15, 2022 IDA-62430 Int Charges 354,666.12
Oct 15, 2022 IDA-62430 Int Charges 636,069.44
Oct 15, 2022 IDA-62430 Int Charges 26,975.51
Oct 15, 2022 IDA-62430 Int Charges 26,975.51
Oct 15, 2022 IDA-62430 Int Charges 354,666.12
Feb 24, 2023 IDA-62430 Loan Disb 3,481,155.50
Apr 15, 2023 IDA-62430 Int Charges 34,992.04
Apr 15, 2023 IDA-62430 Int Charges 34,992.04
Apr 15, 2023 IDA-62430 Int Charges 379,624.88
Apr 15, 2023 IDA-62430 Int Charges 379,624.88

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2025-01-07
Overall Implementation Progress (IP) Satisfactory 2025-01-07
Overall Safeguards Rating Satisfactory 2025-01-07
Progress towards achievement of PDO Satisfactory 2025-01-07

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Score in the APA for achievement of institutional performance measures, averaged across all MCs that qualify.Value0.0060.0070.00
    DateMay 29, 2018June 19, 2023June 28, 2024
    Comment
  • People living in targeted cities benefiting from municipal service delivery infrastructure created or rehabilitated under the Program.Value0.005398334.001000000.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • PDO Indicator 2.a. Of which female (Supplemental)Value0.0049.0050.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • MCs with the full set of enhanced e-governance systems operationalized.Value8.0016.0016.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • MCs with Infrastructure Maps updated under the Program.Value0.0016.0010.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • MCs with IDAMPs developed and adopted, ensuring consultation with women groups.Value0.0016.005.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • MCs with at least 10% increase in OSRs.Value0.0016.005.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • Annual performance assessment of Program MCs conducted on time.ValueNo APAs conductedAPA for the current FY is ongoing.APAs conducted per annual schedule.
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • MCs with timely audits conducted of annual financial statements and no adverse or disclaimed audit opinion.Value0.0016.0016.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • Percentage of local infrastructure targets as set out in the annual work plans delivered by MCs utilizing Program funds.Value0.000.0080.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • Percentage of infrastructure contracts with gender responsive working conditionsValue0.00100.0080.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • MCs that execute at least 80 percent of their annual O&M budget.Value0.000.0010.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • IR Indicator 1.1.a. Performance Management System (Supplemental)Value8.0016.0016.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • IR Indicator 1.1.b. Computerized Financial Management System (Supplemental)Value8.0016.0016.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment
  • IR Indicator 1.1.c. Complaint Tracking System (Supplemental)Value8.0016.0016.00
    DateMay 29, 2018May 15, 2024June 28, 2024
    Comment