Financier | Commitments |
---|---|
Borrower/Recipient | 7.00 |
IDA Credit | 200.00 |
P156972
Active
Shahnaz Arshad
Economic Affairs Division
January 25, 2018
(as of board presentation)
May 25, 2018
May 29, 2018
US$ 236.00 million
Punjab Municipal Development Funds Company,Planning and Development Board, Government of Punjab,Local Government and Community Development Department
2018
US$ 200.00 million
B
May 31, 2024
August 29, 2025
No
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 7.00 |
IDA Credit | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 200.00 |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 236.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 15, 2023 | IDA-62430 | Int Charges | 652,733.60 |
Jun 21, 2023 | IDA-62430 | Loan Disb | 41,386,088.00 |
Mar 17, 2023 | IDA-62430 | Loan Disb | 9,182,048.00 |
Sep 7, 2023 | IDA-62430 | Loan Disb | 202,766.69 |
Oct 15, 2023 | IDA-62430 | Int Charges | 37,031.77 |
Oct 15, 2023 | IDA-62430 | Loan Repay | 2,974,042.20 |
Oct 15, 2023 | IDA-62430 | Int Charges | 535,190.40 |
Oct 15, 2023 | IDA-62430 | Int Charges | 535,190.40 |
Oct 15, 2023 | IDA-62430 | Int Charges | 891,983.94 |
Apr 15, 2024 | IDA-62430 | Loan Repay | 75,564.92 |
Apr 15, 2020 | IDA-62430 | Int Charges | 61,741.38 |
Oct 15, 2020 | IDA-62430 | Int Charges | 65.07 |
Oct 15, 2020 | IDA-62430 | Int Charges | 65.07 |
Oct 15, 2020 | IDA-62430 | Int Charges | 147,815.16 |
Oct 15, 2020 | IDA-62430 | Int Charges | 147,815.16 |
Oct 15, 2020 | IDA-62430 | Int Charges | 245,952.94 |
Jun 19, 2020 | IDA-62430 | Loan Disb | 500,951.38 |
Jun 19, 2020 | IDA-62430 | Loan Disb | 42,644,304.00 |
Mar 11, 2021 | IDA-62430 | Loan Disb | 491,067.34 |
Apr 15, 2021 | IDA-62430 | Int Charges | 520.27 |
Apr 15, 2021 | IDA-62430 | Int Charges | 209,682.12 |
Apr 15, 2021 | IDA-62430 | Int Charges | 209,682.12 |
Apr 15, 2021 | IDA-62430 | Int Charges | 349,470.16 |
Jun 23, 2021 | IDA-62430 | Loan Disb | 53,933,856.00 |
Sep 15, 2021 | IDA-62430 | Loan Disb | 1,645,630.00 |
Oct 15, 2021 | IDA-62430 | Int Charges | 330,269.30 |
Oct 15, 2021 | IDA-62430 | Int Charges | 330,269.30 |
Oct 15, 2021 | IDA-62430 | Int Charges | 556,826.20 |
Oct 15, 2021 | IDA-62430 | Int Charges | 3,826.42 |
Oct 15, 2021 | IDA-62430 | Int Charges | 3,826.42 |
Apr 25, 2022 | IDA-62430 | Loan Disb | 2,006,978.10 |
Apr 15, 2022 | IDA-62430 | Int Charges | 2,612.86 |
Jun 13, 2019 | IDA-62430 | Loan Disb | 9,524,053.00 |
Oct 15, 2019 | IDA-62430 | Int Charges | 39,949.16 |
Oct 15, 2019 | IDA-62430 | Int Charges | 23,969.50 |
Oct 15, 2019 | IDA-62430 | Int Charges | 23,969.50 |
Feb 3, 2020 | IDA-62430 | Loan Disb | 1,200,000.00 |
Apr 15, 2020 | IDA-62430 | Int Charges | 170.68 |
Apr 15, 2020 | IDA-62430 | Int Charges | 170.68 |
Apr 15, 2020 | IDA-62430 | Int Charges | 36,874.14 |
Apr 15, 2024 | IDA-62430 | Int Charges | 584,485.30 |
Apr 15, 2024 | IDA-62430 | Loan Repay | 2,913,121.50 |
Apr 15, 2020 | IDA-62430 | Int Charges | 36,874.14 |
Apr 15, 2024 | IDA-62430 | Int Charges | 584,485.30 |
Apr 15, 2024 | IDA-62430 | Int Charges | 974,142.25 |
Mar 6, 2024 | IDA-62430 | Loan Disb | 1,530,828.50 |
Jun 21, 2024 | IDA-62430 | Loan Disb | 13,117,941.00 |
May 25, 2018 | IDA-62430 | Loan Commitment | 200,000,000.00 |
Apr 15, 2022 | IDA-62430 | Int Charges | 2,612.86 |
Apr 15, 2022 | IDA-62430 | Int Charges | 398,730.16 |
Apr 15, 2022 | IDA-62430 | Int Charges | 398,730.16 |
Apr 15, 2022 | IDA-62430 | Int Charges | 668,905.06 |
Oct 15, 2022 | IDA-62430 | Int Charges | 354,666.12 |
Oct 15, 2022 | IDA-62430 | Int Charges | 636,069.44 |
Oct 15, 2022 | IDA-62430 | Int Charges | 26,975.51 |
Oct 15, 2022 | IDA-62430 | Int Charges | 26,975.51 |
Oct 15, 2022 | IDA-62430 | Int Charges | 354,666.12 |
Feb 24, 2023 | IDA-62430 | Loan Disb | 3,481,155.50 |
Apr 15, 2023 | IDA-62430 | Int Charges | 34,992.04 |
Apr 15, 2023 | IDA-62430 | Int Charges | 34,992.04 |
Apr 15, 2023 | IDA-62430 | Int Charges | 379,624.88 |
Apr 15, 2023 | IDA-62430 | Int Charges | 379,624.88 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Satisfactory | 2025-01-07 |
Overall Implementation Progress (IP) | Satisfactory | 2025-01-07 |
Overall Safeguards Rating | Satisfactory | 2025-01-07 |
Progress towards achievement of PDO | Satisfactory | 2025-01-07 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Score in the APA for achievement of institutional performance measures, averaged across all MCs that qualify. | Value | 0.00 | 60.00 | 70.00 |
Date | May 29, 2018 | June 19, 2023 | June 28, 2024 | |
Comment |
People living in targeted cities benefiting from municipal service delivery infrastructure created or rehabilitated under the Program. | Value | 0.00 | 5398334.00 | 1000000.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
PDO Indicator 2.a. Of which female (Supplemental) | Value | 0.00 | 49.00 | 50.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
MCs with the full set of enhanced e-governance systems operationalized. | Value | 8.00 | 16.00 | 16.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
MCs with Infrastructure Maps updated under the Program. | Value | 0.00 | 16.00 | 10.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
MCs with IDAMPs developed and adopted, ensuring consultation with women groups. | Value | 0.00 | 16.00 | 5.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
MCs with at least 10% increase in OSRs. | Value | 0.00 | 16.00 | 5.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
Annual performance assessment of Program MCs conducted on time. | Value | No APAs conducted | APA for the current FY is ongoing. | APAs conducted per annual schedule. |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
MCs with timely audits conducted of annual financial statements and no adverse or disclaimed audit opinion. | Value | 0.00 | 16.00 | 16.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
Percentage of local infrastructure targets as set out in the annual work plans delivered by MCs utilizing Program funds. | Value | 0.00 | 0.00 | 80.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
Percentage of infrastructure contracts with gender responsive working conditions | Value | 0.00 | 100.00 | 80.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
MCs that execute at least 80 percent of their annual O&M budget. | Value | 0.00 | 0.00 | 10.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
IR Indicator 1.1.a. Performance Management System (Supplemental) | Value | 8.00 | 16.00 | 16.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
IR Indicator 1.1.b. Computerized Financial Management System (Supplemental) | Value | 8.00 | 16.00 | 16.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |
IR Indicator 1.1.c. Complaint Tracking System (Supplemental) | Value | 8.00 | 16.00 | 16.00 |
Date | May 29, 2018 | May 15, 2024 | June 28, 2024 | |
Comment |