Strategic Irrigation Modernization and Urgent Rehabilitation Project

Abstract*

The objective of the Strategic Irrigation Modernization and Urgent Rehabilitation Project for Indonesia is to improve irrigation services and strengthen accountability of irrigation schemes management in selected areas. There are three components to the project, the first component being urgent rehabilitation of irrigation and drainage system. Urgent Rehabilitation of Irrigation and Drainage System. this component will support the Institutional strengthening...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to improve irrigation services and strengthen accountability of irrigation schemes management in selected areas.

Key Details

Project Details

  • P157585

  • Closed

  • IJsbrand H. de Jong

  • Republic of Indonesia,Republic of Indonesia

  • Indonesia

  • March 30, 2017

  • (as of board presentation)

    June 21, 2018

  • August 23, 2018

  • US$ 578.00 million

  • Republic of Indonesia,Republic of Indonesia

  • East Asia and Pacific

  • 2018

  • US$ 491.00 million

  • B

  • Not Applicable

  • June 30, 2025

  • Yes

  • Bank Approved

  • June 5, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Asian Infrastructure Investment Bank 245.50
Asian Infrastructure Investment Bank 245.50
Borrower/Recipient 45.00
Borrower/Recipient 45.00
International Bank for Reconstruction and Development 245.50
International Bank for Reconstruction and Development 245.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 245.50
IDA Commitment N/A
IBRD + IDA Commitment 245.50
Lending Instrument
Grant Amount 245.50
Total Project Cost** 578.00

Summary Status of World Bank Financing (US$ Millions) as of October 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of October 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Moderately Satisfactory 2025-06-27
Counterpart Funding Moderately Satisfactory 2025-06-27
Financial Management Moderately Satisfactory 2025-06-27
Financial Management Moderately Satisfactory 2025-06-27
Monitoring and Evaluation Satisfactory 2025-06-27
Monitoring and Evaluation Satisfactory 2025-06-27
Overall Implementation Progress (IP) Moderately Satisfactory 2025-06-27
Overall Implementation Progress (IP) Moderately Satisfactory 2025-06-27
Procurement Moderately Satisfactory 2025-06-27
Procurement Moderately Satisfactory 2025-06-27
Progress towards achievement of PDO Satisfactory 2025-06-27
Progress towards achievement of PDO Satisfactory 2025-06-27
Project Management Satisfactory 2025-06-27
Project Management Satisfactory 2025-06-27

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area provided with new/improved irrigation or drainage servicesValue0.00225171.00253102.00
    DateJuly 2, 2018March 10, 2024June 30, 2024
    Comment
  • Area provided with new/improved irrigation or drainage servicesValue0.00225171.00253102.00
    DateJuly 2, 2018March 10, 2024June 30, 2024
    Comment
  • Number of asset management systems with transparent budget allocation operationalValue0.0015.009.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Number of asset management systems with transparent budget allocation operationalValue0.0015.009.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Number of irrigation service agreements with clear allocation of responsibilities implemented.Value0.0012.009.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Number of irrigation service agreements with clear allocation of responsibilities implemented.Value0.0012.009.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Percentage of crop intensity (paddy)Value180.00194.00200.00
    DateJuly 2, 2018March 10, 2024June 30, 2024
    Comment
  • Percentage of crop intensity (paddy)Value180.00194.00200.00
    DateJuly 2, 2018March 10, 2024June 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Annual performance report of irrigation service providers published (Component A)Value0.0011.008.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Annual performance report of irrigation service providers published (Component A)Value0.0011.008.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Annual performance report of irrigation service providers published (Component B)Value0.001.001.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Annual performance report of irrigation service providers published (Component B)Value0.001.001.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Establishment and operationalization of grievance mechanism for water users in delivery of irrigation services (Component A)Value0.0010.006.00
    DateJuly 1, 2018November 6, 2023June 30, 2024
    Comment
  • Establishment and operationalization of grievance mechanism for water users in delivery of irrigation services (Component A)Value0.0010.006.00
    DateJuly 1, 2018November 6, 2023June 30, 2024
    Comment
  • Establishment and operationalization of grievance mechanism for water users in delivery of irrigation services (Component B)Value0.001.001.00
    DateApril 5, 2022March 10, 2024June 30, 2024
    Comment
  • Establishment and operationalization of grievance mechanism for water users in delivery of irrigation services (Component B)Value0.001.001.00
    DateApril 5, 2022March 10, 2024June 30, 2024
    Comment
  • Irrigation Commission (KOMIR) established and operational (Component A)Value8.0027.0024.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Irrigation Commission (KOMIR) established and operational (Component A)Value8.0027.0024.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Irrigation Commission (KOMIR) established and operational (Component B)Value1.003.003.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Irrigation Commission (KOMIR) established and operational (Component B)Value1.003.003.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Number of WUAFs established and operational (Component A)Value0.00136.0090.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Number of WUAFs established and operational (Component A)Value0.00136.0090.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Number of WUAFs established and operational (Component B)Value0.00163.00160.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Number of WUAFs established and operational (Component B)Value0.00163.00160.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Number of farmer households provided with improved irrigation services (Component A)Value0.00407.00429.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Number of farmer households provided with improved irrigation services (Component A)Value0.00407.00429.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Number of farmer households provided with improved irrigation services (Component B)Value0.00295.00362.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Number of farmer households provided with improved irrigation services (Component B)Value0.00295.00362.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Participatory Irrigation Development and Management (PPISP) included in planning documents (Component A)Value9.0030.0019.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Participatory Irrigation Development and Management (PPISP) included in planning documents (Component A)Value9.0030.0019.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Participatory Irrigation Development and Management (PPISP) included in planning documents (Component B)Value1.004.002.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • Participatory Irrigation Development and Management (PPISP) included in planning documents (Component B)Value1.004.002.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • WUAs with trained members in decision making (Component B)Value0.001826.00480.00
    DateOctober 1, 2018March 10, 2024June 30, 2024
    Comment
  • WUAs with trained members in decision making (Component B)Value0.001826.00480.00
    DateOctober 1, 2018March 10, 2024June 30, 2024
    Comment
  • WUAs with trained female members in decision making (Component A)Value0.0066.0050.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • WUAs with trained female members in decision making (Component A)Value0.0066.0050.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • WUAs with trained female members in decision making (Component B)Value0.000.000.00
    Date
    Comment
  • WUAs with trained female members in decision making (Component B)Value0.000.000.00
    Date
    Comment
  • WUAs with trained members in decision making (Component A)Value0.001207.00390.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment
  • WUAs with trained members in decision making (Component A)Value0.001207.00390.00
    DateJuly 1, 2018March 10, 2024June 30, 2024
    Comment