Financier | Commitments |
---|---|
IDA Grant | 30.00 |
P157782
Closed
Dambudzo Muzenda , Karamoko Sanogo
Ministry of Energy, Hydraulics and Hydrocarbons (Ministère de l’Energie, de l’Hydraulique et des Hyd
May 11, 2016
(as of board presentation)
June 27, 2017
January 11, 2018
US$ 30.00 million
Guinea Water Company (Societe des Eaux de Guinee) (SEG),National Directorate of Territory Administration, Urban Planning, Roads and Infrastructures (DATU)
2017
US$ 30.00 million
B
Not Applicable
March 29, 2024
BANK APPROVED
March 28, 2024
Financier | Commitments |
---|---|
IDA Grant | 30.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 30.00 |
IBRD + IDA Commitment | 30.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 30.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 13, 2021 | IDA-D2140 | Loan Disb | 381,656.94 |
Jun 7, 2021 | IDA-D2140 | Loan Disb | 48,468.03 |
Jun 9, 2021 | IDA-D2140 | Loan Disb | 828,577.50 |
Jun 28, 2021 | IDA-D2140 | Loan Disb | 483,857.12 |
Aug 23, 2021 | IDA-D2140 | Loan Disb | 640,921.75 |
Feb 18, 2021 | IDA-D2140 | Loan Disb | 203,050.30 |
Feb 16, 2021 | IDA-D2140 | Loan Disb | 46,903.85 |
Jan 4, 2021 | IDA-D2140 | Loan Disb | 604,510.10 |
Dec 10, 2020 | IDA-D2140 | Loan Disb | 149,299.80 |
Dec 10, 2020 | IDA-D2140 | Loan Disb | 33,200.00 |
Jan 10, 2020 | IDA-D2140 | Loan Disb | 69,170.56 |
Dec 6, 2019 | IDA-D2140 | Loan Disb | 38,888.43 |
Mar 13, 2020 | IDA-D2140 | Loan Disb | 222,287.52 |
Dec 6, 2019 | IDA-D2140 | Loan Disb | 2,000.00 |
Jan 16, 2020 | IDA-D2140 | Loan Disb | 137,344.73 |
Feb 18, 2020 | IDA-D2140 | Loan Disb | 274,184.66 |
Apr 21, 2020 | IDA-D2140 | Loan Disb | 159,092.34 |
Jun 29, 2020 | IDA-D2140 | Loan Disb | 783,453.00 |
Jun 17, 2020 | IDA-D2140 | Loan Disb | 205,206.02 |
Jun 19, 2020 | IDA-D2140 | Loan Disb | 169,052.16 |
May 18, 2020 | IDA-D2140 | Loan Disb | 132,985.86 |
Jan 11, 2018 | IDA-D2140 | Loan Disb | 351,611.47 |
Jun 29, 2018 | IDA-D2140 | Loan Disb | 1,650,000.00 |
Nov 9, 2018 | IDA-D2140 | Loan Disb | 92,797.59 |
Oct 10, 2018 | IDA-D2140 | Loan Disb | 349,999.88 |
Jan 22, 2019 | IDA-D2140 | Loan Disb | 33,809.55 |
Jan 22, 2019 | IDA-D2140 | Loan Disb | 46,638.80 |
Mar 20, 2019 | IDA-D2140 | Loan Disb | 255,347.70 |
May 6, 2019 | IDA-D2140 | Loan Disb | 20,331.13 |
May 7, 2019 | IDA-D2140 | Loan Disb | 217,566.70 |
Mar 5, 2019 | IDA-D2140 | Loan Disb | 44,731.11 |
Mar 29, 2019 | IDA-D2140 | Loan Disb | 72,421.25 |
Mar 11, 2019 | IDA-D2140 | Loan Disb | 46,868.85 |
Dec 2, 2019 | IDA-D2140 | Loan Disb | 56,748.68 |
Sep 17, 2019 | IDA-D2140 | Loan Disb | 84,556.53 |
Jul 30, 2019 | IDA-D2140 | Loan Disb | 138,704.08 |
Jul 29, 2019 | IDA-D2140 | Loan Disb | 137,150.58 |
Jul 31, 2024 | IDA-D2140 | Loan Disb | 290,170.56 |
Feb 14, 2024 | IDA-D2140 | Loan Disb | 183,410.52 |
Jun 27, 2017 | IDA-D2140 | Loan Commitment | 30,000,000.00 |
Jan 31, 2024 | IDA-D2140 | Loan Disb | 1,174,943.50 |
Feb 13, 2024 | IDA-D2140 | Loan Disb | 755,845.50 |
Jul 31, 2024 | IDA-D2140 | Loan Disb | 51,171.76 |
Aug 2, 2024 | IDA-D2140 | Loan Disb | 29,672.22 |
Jul 31, 2024 | IDA-D2140 | Loan Disb | 15,537.15 |
Jul 31, 2024 | IDA-D2140 | Loan Disb | 51,171.76 |
Nov 27, 2023 | IDA-D2140 | Loan Disb | 187,443.28 |
Oct 16, 2023 | IDA-D2140 | Loan Disb | 331,229.03 |
Apr 3, 2024 | IDA-D2140 | Loan Disb | 813,116.40 |
Apr 3, 2024 | IDA-D2140 | Loan Disb | 1,005,629.50 |
Mar 15, 2024 | IDA-D2140 | Loan Disb | 149,686.30 |
Jan 29, 2024 | IDA-D2140 | Loan Disb | 857,537.80 |
Aug 3, 2023 | IDA-D2140 | Loan Disb | 866,016.00 |
Aug 14, 2023 | IDA-D2140 | Loan Disb | 519,236.66 |
Aug 16, 2023 | IDA-D2140 | Loan Disb | 474,970.34 |
Jul 17, 2023 | IDA-D2140 | Loan Disb | 183,064.83 |
Jun 22, 2023 | IDA-D2140 | Loan Disb | 188,276.19 |
Sep 19, 2023 | IDA-D2140 | Loan Disb | 468,846.30 |
Nov 10, 2023 | IDA-D2140 | Loan Disb | 1,100,023.00 |
May 23, 2023 | IDA-D2140 | Loan Disb | 1,616,620.10 |
May 22, 2023 | IDA-D2140 | Loan Disb | 214,534.27 |
Oct 18, 2023 | IDA-D2140 | Loan Disb | 449,485.50 |
Dec 8, 2023 | IDA-D2140 | Loan Disb | 1,314,520.80 |
May 16, 2023 | IDA-D2140 | Loan Disb | 242,952.66 |
May 16, 2023 | IDA-D2140 | Loan Disb | 128,577.39 |
Aug 1, 2023 | IDA-D2140 | Loan Disb | 1,072,840.80 |
Sep 18, 2023 | IDA-D2140 | Loan Disb | 406,315.72 |
Sep 19, 2022 | IDA-D2140 | Loan Disb | 49,399.74 |
Mar 13, 2023 | IDA-D2140 | Loan Disb | 583,324.30 |
Mar 9, 2023 | IDA-D2140 | Loan Disb | 75,362.32 |
Mar 9, 2023 | IDA-D2140 | Loan Disb | 18,555.04 |
Aug 3, 2022 | IDA-D2140 | Loan Disb | 142,937.61 |
Mar 25, 2022 | IDA-D2140 | Loan Disb | 648,608.80 |
Sep 2, 2022 | IDA-D2140 | Loan Disb | 327,832.78 |
Dec 28, 2022 | IDA-D2140 | Loan Disb | 271,884.25 |
Nov 21, 2022 | IDA-D2140 | Loan Disb | 58,651.19 |
Nov 14, 2022 | IDA-D2140 | Loan Disb | 401,753.56 |
Jun 1, 2022 | IDA-D2140 | Loan Disb | 298,573.88 |
Jun 1, 2022 | IDA-D2140 | Loan Disb | 233,868.69 |
Jun 29, 2022 | IDA-D2140 | Loan Disb | 194,072.36 |
Jun 22, 2022 | IDA-D2140 | Loan Disb | 582,908.30 |
Mar 22, 2021 | IDA-D2140 | Loan Disb | 182,547.45 |
Jun 30, 2021 | IDA-D2140 | Loan Disb | 252,041.38 |
Jul 23, 2021 | IDA-D2140 | Loan Disb | 46,294.86 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2024-03-29 |
Financial Management | Moderately Satisfactory | 2024-03-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-03-29 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-03-29 |
Procurement | Moderately Satisfactory | 2024-03-29 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-03-29 |
INDICATOR | ICR REVIEW: 04-08-2025 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people in urban areas provided with access to improved water sources under the project | Value | 0.00 | 30640.00 | 24000.00 |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
Number of people in urban areas already connected and provided with access to "enhanced water supply services " under the project. | Value | 0.00 | 17920.00 | 17000.00 |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
Percentage of female in urban areas provided with access to improved water sources under the project. | Value | 0.00 | 51.70 | 51.70 |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
Number of SEG sectors having completed a non revenue water reduction program | Value | 0.00 | 7.00 | 4.00 |
Date | January 3, 2023 | March 28, 2024 | March 29, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component 2- Urban Sanitation: Baseline study completed and informs new sanitation strategy | Value | No | Yes | Yes |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
Component 3 - Institutional Strengthening and Project Mgment: Tariff study for urban water completed. | Value | No | Yes | Yes |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
Component 2- Urban Sanitation: Sanitation strategy and action plan adopted | Value | No | Yes | Yes |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
Component 3 - Institutional Strengthening and Project Mgment: Adoption of a new Policy Letter for the urban water sector | Value | No | No | Yes |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
Component 1 - Urban Water: New piped household water connections that are resulting from Project interventions. | Value | 0.00 | 1532.00 | 1000.00 |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
Component 1 - Urban Water: Piped household water connections rehabilitated under the project | Value | 0.00 | 4622.00 | 5000.00 |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
Number of SEG staff having received training on technical and commercial aspects of water supply | Value | 0.00 | 188.00 | 88.00 |
Date | January 6, 2023 | March 28, 2024 | March 29, 2024 | |
Comment |
Component 1 - Urban Water: Length of feeder pipes constructed under the Project | Value | 0.00 | 23.91 | 26.00 |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
of which women | Value | 0.00 | 82.00 | 20.00 |
Date | January 6, 2023 | March 28, 2024 | March 29, 2024 | |
Comment |
Installation of a new cartographic system for SEG capable of georeferencing customers | Value | No | Yes | Yes |
Date | January 6, 2023 | March 28, 2024 | March 29, 2024 | |
Comment |
Number of water sector officials having received capacity building on groundwater resources | Value | 0.00 | 99.00 | 25.00 |
Date | January 2, 2023 | March 28, 2024 | March 29, 2024 | |
Comment |
Component 1 - Urban Water: Beneficiaries that feel project investments reflected their needs | Value | 0.00 | 94.80 | 80.00 |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
Component 1 - Urban Water: Registered grievances related to the project activities are appropriately responded within two weeks | Value | 0.00 | 100.00 | 80.00 |
Date | September 15, 2017 | March 28, 2024 | March 29, 2024 | |
Comment |
Number of new household meters installed | Value | 0.00 | 12192.00 | 12500.00 |
Date | April 1, 2020 | March 28, 2024 | March 29, 2024 | |
Comment |
Number of handwashing facilities constructed under the project | Value | 0.00 | 500.00 | 500.00 |
Date | April 1, 2020 | March 28, 2024 | March 29, 2024 | |
Comment |