Secondary Education Improvement Project

Abstract*

The objective of the Secondary Education Improvement Project (SEIP) is to expand lower secondary education to achieve minimum standards in target areas, and to provide immediate and effective response in case of an eligible crisis or emergency. There are three components to the project, the first component being improving lower secondary education to meet minimum standards. This component aims to support the goals of the ESP and TPAP through the establishment...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To expand lower secondary education to achieve minimum standards in target areas, and to provide immediate and effective response in case of an eligible crisis or emergency.

Key Details

Project Details

  • P157858

  • Closed

  • Simeth Beng

  • Royal Government of Cambodia

  • Cambodia

  • April 20, 2016

  • (as of board presentation)

    April 14, 2017

  • July 6, 2017

  • US$ 40.90 million

  • Ministry of Education, Youth and Sport

  • East Asia and Pacific

  • 2017

  • US$ 40.00 million

  • B

  • September 20, 2023

  • July 29, 2022

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 40.00
Borrower/Recipient 0.90

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 40.00
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 40.90

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 1, 2019 IDA-59780 Int Charges 447.74
May 1, 2019 IDA-59780 Int Charges 447.74
May 1, 2019 IDA-59780 Int Charges 40,493.58
May 1, 2019 IDA-59780 Int Charges 40,493.58
May 1, 2024 IDA-59780 Loan Repay 587,339.40
Apr 14, 2017 IDA-59780 Loan Commitment 40,000,000.00
Nov 1, 2023 IDA-59780 Int Charges 7,576.23
Nov 1, 2023 IDA-59780 Int Charges 7,576.23
Nov 1, 2023 IDA-59780 Loan Repay 596,673.00
Nov 1, 2023 IDA-59780 Int Charges 140,963.98
Nov 1, 2023 IDA-59780 Int Charges 140,963.98
May 1, 2024 IDA-59780 Int Charges 139,325.19
May 1, 2024 IDA-59780 Int Charges 139,325.19
May 1, 2024 IDA-59780 Loan Repay 11,908.83
Sep 30, 2022 IDA-59780 Loan Disb 1,854,444.00
Nov 29, 2022 IDA-59780 Loan Cancel 433,075.72
Nov 1, 2022 IDA-59780 Int Charges 130,614.42
Nov 1, 2022 IDA-59780 Int Charges 4,245.75
Nov 1, 2022 IDA-59780 Int Charges 4,245.75
Nov 1, 2022 IDA-59780 Int Charges 130,614.42
May 1, 2023 IDA-59780 Loan Repay 613,771.80
May 1, 2023 IDA-59780 Int Charges 139,621.23
May 1, 2023 IDA-59780 Int Charges 139,621.23
May 1, 2023 IDA-59780 Loan Repay 480.96
Mar 16, 2022 IDA-59780 Loan Disb 507,418.97
Dec 1, 2021 IDA-59780 Loan Disb 4,646,340.00
May 1, 2022 IDA-59780 Int Charges 1,050.58
May 1, 2022 IDA-59780 Int Charges 1,050.58
May 1, 2022 IDA-59780 Int Charges 127,182.57
May 1, 2022 IDA-59780 Int Charges 127,182.57
Apr 29, 2022 IDA-59780 Loan Disb 1,976,121.00
Dec 13, 2021 IDA-59780 Loan Disb 9,881.00
Nov 1, 2020 IDA-59780 Int Charges 7,979.28
Nov 1, 2020 IDA-59780 Int Charges 7,979.28
Nov 1, 2020 IDA-59780 Int Charges 118,887.08
Nov 1, 2020 IDA-59780 Int Charges 118,887.08
Apr 13, 2021 IDA-59780 Loan Disb 140,633.31
May 1, 2021 IDA-59780 Int Charges 119,921.51
May 1, 2021 IDA-59780 Int Charges 119,921.51
May 1, 2021 IDA-59780 Int Charges 1,069.47
May 1, 2021 IDA-59780 Int Charges 1,069.47
Nov 1, 2021 IDA-59780 Int Charges 7.46
Nov 1, 2021 IDA-59780 Int Charges 7.46
Nov 1, 2021 IDA-59780 Int Charges 119,332.84
Nov 1, 2021 IDA-59780 Int Charges 119,332.84
Nov 1, 2019 IDA-59780 Int Charges 80,420.54
Nov 1, 2019 IDA-59780 Int Charges 80,420.54
Nov 1, 2019 IDA-59780 Int Charges 7,586.67
Nov 1, 2019 IDA-59780 Int Charges 7,586.67
Mar 2, 2020 IDA-59780 Loan Disb 6,329,380.50
Feb 5, 2020 IDA-59780 Loan Disb 1,856,076.00
Apr 20, 2020 IDA-59780 Loan Disb 1,137,242.00
May 1, 2020 IDA-59780 Int Charges 745.37
May 1, 2020 IDA-59780 Int Charges 84,097.75
May 1, 2020 IDA-59780 Int Charges 84,097.75
May 1, 2020 IDA-59780 Int Charges 745.37
Oct 20, 2017 IDA-59780 Loan Disb 7,814,700.00
Jan 22, 2018 IDA-59780 Loan Disb 3,303,966.20
May 1, 2018 IDA-59780 Int Charges 1,820.78
May 1, 2018 IDA-59780 Int Charges 1,820.78
May 1, 2018 IDA-59780 Int Charges 36,573.57
May 1, 2018 IDA-59780 Int Charges 36,573.57
Nov 1, 2018 IDA-59780 Int Charges 240.05
Nov 1, 2018 IDA-59780 Int Charges 240.05
Nov 1, 2018 IDA-59780 Int Charges 40,456.41
Nov 1, 2018 IDA-59780 Int Charges 40,456.41
Mar 18, 2019 IDA-59780 Loan Disb 5,129,625.50
Apr 4, 2019 IDA-59780 Loan Disb 5,796,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Highly Satisfactory 2022-02-25
Progress towards achievement of PDO Highly Satisfactory 2022-02-25
Financial Management Highly Satisfactory 2022-02-25
Monitoring and Evaluation Highly Satisfactory 2022-02-25
Project Management Highly Satisfactory 2022-02-25
Counterpart Funding Highly Satisfactory 2022-02-25
Overall Implementation Progress (IP) Highly Satisfactory 2022-02-25

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 07-27-2023
OutcomesHighly Satisfactory
Risk to Development Outcome
Bank PerformanceHighly Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-04-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.00136871.0020810.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Number of target lower secondary schools that have achieved minimum standardsValue0.0094.0070.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Number of teachers who graduate from TUPValue0.002140.002000.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Female beneficiariesValue0.000.0050.00
    DateJuly 3, 2017May 30, 2018
    Comment
  • Number of enrolled students in newly constructed lower secondary schools (total)Value0.006175.005250.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Number of enrolled female students in newly constructed lower secondary schoolsValue0.000.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Students benefiting from direct interventions to enhance learningValue0.00453838.000.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • PISA For Development Report completedValueNoYesYes
    DateJuly 3, 2017July 29, 2022June 30, 2020
    Comment
  • Results of an independent SIF program impact evaluation are discussed in a policy meeting with MoEYS, MEF, MoPW, and relevant DPsValueNoYesYes
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Students benefiting from direct interventions to enhance learning - FemaleValue0.0050.0053.20
    Date
    Comment
  • Number of schools that publicly display development planValue0.00100.00100.00
    DateJune 1, 2017July 29, 2022June 30, 2022
    Comment
  • Large-scale primary/secondary learning assessments completedValueNoYesYes
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Number of schools that conduct teacher assessment based on Teacher Professional StandardsValue0.00100.00100.00
    DateJune 1, 2017July 29, 2022June 30, 2022
    Comment
  • School Improvement Fund Manual produced/revised for school based management activityValueNo ManualRevisedN/A
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Training plans for POE, DOE and school levels produced for school based management activityValueNo planRevisedN/A
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Number of submitted POE improvement plans based on the SIF manualValue0.0025.0025.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Number of submitted DOE improvement plans based on the SIF manualValue0.0099.0075.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Annual status report for SIF producedValueNoYesYes
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • MoEYS formally adopted a Teacher Upgrading Strategy as well as a corresponding implementation plan and its Operational ManualValueNo strategy no manualsRevisedInitial manual revised
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Number of enrolled teachers in TUPValue0.002348.002200.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • MOEYS formally adopted Leadership Upgrading Training ManualValueNo manualsRevisedManual revised
    DateJuly 3, 2017July 29, 2022June 30, 2020
    Comment
  • Number of school directors/deputy who graduate LUPValue0.00599.00310.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Number of school directors /deputy directors who are enrolled in LUPValue0.00636.00310.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Number of classrooms constructed in new locationsValue0.00150.00150.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Number of school rehabilitatedValue0.00100.00100.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment
  • Number of SSCs participating in decision making process of schools.Value0.00100.00100.00
    DateJuly 3, 2017July 29, 2022June 30, 2022
    Comment