Financier | Commitments |
---|---|
IDA Credit | 200.00 |
P159330
Active
Aymen Ali
Ministry of Finance
November 3, 2016
(as of board presentation)
May 4, 2017
February 15, 2018
US$ 200.00 million
National Road Fund Agency
2017
US$ 200.00 million
B
Not Applicable
December 31, 2025
Yes
BANK APPROVED
February 8, 2024
Financier | Commitments |
---|---|
IDA Credit | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 200.00 |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 200.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 23, 2020 | IDA-60390 | Loan Disb | 5,500,000.00 |
Dec 31, 2019 | IDA-60390 | Int Charges | 233,500.52 |
Dec 31, 2019 | IDA-60390 | Int Charges | 331,254.40 |
Jun 26, 2019 | IDA-60390 | Int Charges | 331,254.40 |
Jun 26, 2019 | IDA-60390 | Int Charges | 87,555.98 |
Nov 15, 2019 | IDA-60390 | Loan Disb | 5,000,000.00 |
May 30, 2019 | IDA-60390 | Int Charges | 142,137.45 |
May 15, 2018 | IDA-60390 | Int Charges | 249,800.86 |
May 15, 2018 | IDA-60390 | Int Charges | 39,654.98 |
Jun 30, 2021 | IDA-60390 | Loan Disb | 62,320.90 |
Dec 23, 2020 | IDA-60390 | Int Charges | 33,758.87 |
Dec 23, 2020 | IDA-60390 | Int Charges | 219,643.19 |
Dec 23, 2020 | IDA-60390 | Int Charges | 567,527.00 |
Nov 30, 2020 | IDA-60390 | Loan Disb | 5,172,204.50 |
Nov 15, 2018 | IDA-60390 | Int Charges | 1,918.61 |
Nov 15, 2018 | IDA-60390 | Int Charges | 235,482.10 |
Nov 15, 2018 | IDA-60390 | Int Charges | 296,429.56 |
Jun 11, 2018 | IDA-60390 | Loan Disb | 10,715,339.00 |
Apr 12, 2018 | IDA-60390 | Loan Disb | 492,080.25 |
Feb 15, 2018 | IDA-60390 | Loan Disb | 500,000.00 |
Feb 15, 2018 | IDA-60390 | Fee Charges | 500,000.00 |
May 16, 2023 | IDA-60390 | Int Charges | 108,588.53 |
May 16, 2023 | IDA-60390 | Int Charges | 34,780.18 |
Feb 15, 2018 | IDA-60390 | Loan Disb | 3,015,000.00 |
May 16, 2023 | IDA-60390 | Int Charges | 1,555,669.10 |
Nov 22, 2022 | IDA-60390 | Loan Cancel | 45,000,000.00 |
May 15, 2024 | IDA-60390 | Int Charges | 146,688.05 |
May 15, 2024 | IDA-60390 | Int Charges | 1,847,271.60 |
Jun 25, 2024 | IDA-60390 | Loan Disb | 6,266,524.50 |
Jan 18, 2024 | IDA-60390 | Loan Disb | 6,055,818.50 |
May 4, 2017 | IDA-60390 | Loan Commitment | 200,000,000.00 |
Sep 20, 2022 | IDA-60390 | Loan Disb | 5,357,853.50 |
Jan 28, 2022 | IDA-60390 | Loan Disb | 15,979,105.00 |
Dec 20, 2022 | IDA-60390 | Loan Disb | 8,147,418.50 |
Nov 25, 2022 | IDA-60390 | Int Charges | 177,887.10 |
Nov 25, 2022 | IDA-60390 | Int Charges | 1,289,500.50 |
Nov 22, 2023 | IDA-60390 | Int Charges | 209,316.19 |
Nov 22, 2023 | IDA-60390 | Int Charges | 1,720,577.20 |
Jun 26, 2023 | IDA-60390 | Loan Disb | 7,439,607.50 |
Nov 22, 2022 | IDA-60390 | Loan Cancel | -45,000,000.00 |
Dec 29, 2020 | IDA-60390 | Loan Disb | 53,290.33 |
Oct 15, 2020 | IDA-60390 | Loan Disb | 106,794.36 |
Jun 15, 2020 | IDA-60390 | Int Charges | 408,930.80 |
Jun 2, 2020 | IDA-60390 | Int Charges | 222,283.02 |
May 15, 2022 | IDA-60390 | Int Charges | 499.88 |
May 26, 2022 | IDA-60390 | Int Charges | 1,141,636.10 |
May 26, 2022 | IDA-60390 | Int Charges | 184,607.45 |
Nov 24, 2021 | IDA-60390 | Int Charges | 10,100.41 |
Nov 24, 2021 | IDA-60390 | Int Charges | 200,050.81 |
Nov 24, 2021 | IDA-60390 | Int Charges | 928,436.90 |
Sep 7, 2021 | IDA-60390 | Loan Disb | -62,270.90 |
Jun 21, 2021 | IDA-60390 | Int Charges | 377.87 |
Jun 21, 2021 | IDA-60390 | Int Charges | 209,877.14 |
Jun 21, 2021 | IDA-60390 | Int Charges | 678,075.50 |
May 7, 2021 | IDA-60390 | Loan Disb | 10,685,937.00 |
Jun 2, 2020 | IDA-60390 | Int Charges | 36,814.74 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2025-04-23 |
Financial Management | Moderately Satisfactory | 2025-04-23 |
Monitoring and Evaluation | Satisfactory | 2025-04-23 |
Procurement | Satisfactory | 2025-04-23 |
Project Management | Satisfactory | 2025-04-23 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2025-04-23 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of rural population with access to an all-season road | Value | 18.70 | 18.70 | 25.00 |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Number of rural people with access to an all-season road | Value | 1147000.00 | 1147000.00 | 1587000.00 |
Date | February 28, 2017 | April 27, 2018 | December 31, 2025 | |
Comment |
Increased proportion of Primary Feeder Roads in the country, that is in good and fair condition | Value | 0.00 | 7.28 | 30.00 |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Improved institutional oversight capacity in the roads sector, assessed by the development and application of an RDA performance framework | Value | No | No | Yes |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Employment created through the implementation of NCC’s labor-based policy | Value | 0.00 | 0.00 | 25000.00 |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Number of beneficiaries benefiting from emergency response and recovery activities, if the CERC is triggered | Value | 0.00 | 0.00 | 0.00 |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Proportion of PFRs in the project provinces, that is in good and fair condition | Value | 18.00 | 18.00 | 63.00 |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 100374.00 | 464128.00 |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Total length of rural roads improved through OPRC approach under the project | Value | 0.00 | 1665.32 | 4300.00 |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 228955.00 |
Date | February 28, 2017 | April 27, 2018 | December 31, 2025 | |
Comment |
Existence of government funded road maintenance contracts for continued upkeep of roads after Bank supported OPRC contracts end | Value | No | No | Yes |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Proportion of women employed in the road maintenance aspects of the road contracts | Value | 0.00 | 10.08 | 20.00 |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Completion and implementation of a rural roads maintenance strategy by RDA and MLGH | Value | No | Yes | Yes |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Development and implementation of a citizen engagement tool for social and environmental safeguards and labor influx | Value | No | Yes | Yes |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Share of the road fund revenues allocated by NRFA towards road maintenance | Value | 26.00 | 34.40 | 35.00 |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Proportion of complaints addressed and resolved through Grievance Redress Mechanism | Value | 0.00 | 83.00 | 75.00 |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |
Performance of road safety audit by RTSA on all OPRC packages | Value | 0.00 | 10.00 | 15.00 |
Date | February 28, 2017 | September 15, 2023 | December 31, 2025 | |
Comment |