The development objectives of the Eqra Project for Afghanistan are to increase equitable access to primary and secondary education, particularly for girls, in selected lagging provinces, and to improve learning conditions in Afghanistan. The project comprises of four components. The first component, equitable access to basic education aims to increase access to basic education, especially for girls in selected lagging provinces. It consists of following...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objectives (PDO) are “to increase equitable access to primary and secondary education, particularly for girls, in selected lagging provinces, and to improve learning conditions in Afghanistan”.

Key Details

Project Details

  • P159378

  • Active

  • Tsuyoshi Fukao , Matiullah Noori

  • Islamc Republic of Afghanistan

  • Afghanistan

  • July 16, 2018

  • (as of board presentation)

    September 28, 2018

  • January 3, 2019

  • US$ 273.00 million

  • Ministry of Rural Rehabilitation and Development,Ministry of Education

  • South Asia

  • 2019

  • US$ 273.00 million

  • B

  • Not Applicable

  • June 30, 2025

  • Yes

  • BANK APPROVED

  • September 18, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
EFA-FTI Education Program Development Fund 98.00
Afghanistan Resilience Trust Fund 75.00
IDA Grant 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount 173.00
Total Project Cost** 273.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 28, 2018 IDA-D3810 Loan Commitment 100,000,000.00
Jun 21, 2021 IDA-D3810 Loan Disb 129,248.34
Dec 3, 2020 IDA-D3810 Loan Disb 130,176.57
May 8, 2020 IDA-D3810 Loan Disb 1,177,614.90
Mar 19, 2019 IDA-D3810 Loan Disb 38,000,000.00
Jun 25, 2020 IDA-D3810 Loan Cancel 24,504,836.00
Aug 24, 2020 IDA-D3810 Loan Disb 128,209.21
Mar 20, 2019 IDA-D3810 Loan Disb 395,520.00
Jun 24, 2020 IDA-D3810 Loan Disb 1,967,270.20

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2023-06-16
Financial Management Moderately Satisfactory 2023-06-16
Monitoring and Evaluation Satisfactory 2023-06-16
Overall Implementation Progress (IP) Moderately Satisfactory 2023-06-16
Project Management Moderately Satisfactory 2023-06-16
Procurement Moderately Satisfactory 2023-06-16

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-14-2023
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-28-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualityModestN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Students attending school regularly in selected provincesValue4,318,47350184294,993,337
    DateDecember 31, 2016December 29, 2023December 31, 2023
    Comment
  • Out of school children in selected provincesValue2,289,88010898801,095,329
    DateDecember 31, 2016December 29, 2023December 31, 2023
    Comment
  • Teachers meeting subject specific qualificationsValue52%7272%
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • Students attending school regularly in selected provinces, femaleValue1,616,79919189191,907,405
    DateDecember 31, 2016December 29, 2023December 31, 2023
    Comment
  • out of school children in selected provinces, femaleValue1,387,717643029646,244
    DateDecember 31, 2016December 29, 2023December 31, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Schools constructed or expanded with classrooms, boundary walls, water points, and gender segregated latrinesValue02646Cumulative 2,398 (1,768 school buildings and 630 m
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • Students benefiting from direct interventions to enhance learningValue6447000.007247000.007247000.00
    DateDecember 31, 2016December 29, 2023December 29, 2023
    Comment
  • Annual results based reports implemented between MOE, PEDs and DEDsValueNo annual results reporting between MOE, PEDS and 100%NA
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • NESP III Operational plan on management and budgeting cycle developed and results reported (Text, Custom, DLI)ValueNew O&M budget allocation formula not establishedBy February 2021, progress on results toward 2018,NA
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • Students benefiting from direct interventions to enhance learning - FemaleValue2462000.000.000.00
    DateMarch 22, 2015
    Comment
  • School Grants implementedValue02298NA
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • Existing textbooks distributed and teaching and learning materials for the new curriculum developed for all gradesValueOld national curriculum framework in effect45000000NA
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • Integrated personnel database for education staff establishedValueNo integrated personnel databaseOrganizational mapping of all education Tashkeel sNA
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • Teaching quality rating based on classroom observationsValueBaseline to be collected in 2019Teaching quality rating, based on TEACH classroom Teaching quality rating, based on TEACH classroom
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • Provincial workshops conducted with DEDs, school shura representatiaves to identify constraints to educationValue060NA
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • Grades 1 to 3 teachers and head masters trained in Early Grade ReadingValue0.0020000.0020000.00
    DateMarch 1, 2021December 29, 2023December 31, 2023
    Comment
  • Improved EMIS data collection and quality assurance procedures implementedValueNo monthly phone survey data collection proceduresAll 2019–2022 CBE information reported to the MoE NA
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • Evaluation of Subject Teacher TrainingValueNo data collection conductedCompletion of base line and end line data collectiCompletion of end line data collection of teacher
    DateMarch 1, 2021December 29, 2023December 31, 2023
    Comment
  • Development and implementation of a teacher policy for prioritization in the hiring and allocation of teachers based on needValueNo policy in place for prioritization in the hirinA teacher policy comprising step-by-step procedureNA
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • Complaints addressed through grievance redressal mechanismValue0.0070.0070.00
    DateJune 1, 2018December 29, 2023December 31, 2023
    Comment
  • Implementation of GBV action planValueImplementation of GBV action plan (Text)The relevant MoE staff, teachers, principals and sProtocols and systems to report and respond to GBV
    DateMarch 1, 2021December 29, 2023December 31, 2023