Mark your calendar for October 13–18 as leaders, experts, and voices from around the world come together for critical conversations on the global economy and development. From live discussions to special events, there’s something for everyone to follow online. Sign up now to receive updates and be the first to know what’s happening throughout the week.

Skip to Main Navigation

Vietnam - Additional Financing for Medium Cities Development Project

Development Objective

The development objective of the project is to increase access to improved urban infrastructure services in selected medium-sized cities in Vietnam.

Key Details

Project Details

  • P159426

  • Closed

  • Cuong Dang , Kremena Ionkova

  • State Bank of Vietnam

  • Viet Nam

  • January 20, 2017

  • (as of board presentation)

    June 9, 2017

  • N/A

  • US$ 64.65 million

  • Project Management Unit (PMU) in Vinh,Project Management Unit (PMU) in Lao Cai,Project Management Unit (PMU) in Phu Ly

  • East Asia and Pacific

  • 2017

  • US$ 53.00 million

  • A

  • Not Applicable

  • June 30, 2022

  • Yes

  • BANK APPROVED

  • P116398

  • August 15, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 15.06
IDA Credit 53.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 53.00
IBRD + IDA Commitment 53.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 64.65

Summary Status of World Bank Financing (US$ Millions) as of September 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of September 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people in urban areas provided with access to Improved Water Sources under the projectValue0.006000.0040000.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Number of people in urban areas provided with access to Improved Sanitation under the projectValue0.0074710.00223200.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Reduction in vehicle operating time on new roadsValue0.0015.0030.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Implementation of a comprehensive and sustainable urban asset management plan with an approved annual budget for adequate O&MValue0.000.003.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • School students provided with access to newly built or improved classroomsValue0.001655.003440.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Shared femaleValue0.000.0050.00
    DateNovember 17, 2011May 29, 2012December 31, 2020
    Comment
  • Shared female studentsValue0.000.0050.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Shared femaleValue0.000.0050.00
    DateNovember 17, 2011May 29, 2012December 31, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of water supply pipeline laidValue0.0020.0089.50
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Additional treated water supply capacity made availableValue0.000.006000.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Number of schools with completed sanitation facilitiesValue0.0054.0054.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Length of drainage channel constructed or rehabilitated (including interceptors)Value0.004.609.80
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Additional wastewater treatment capacity made availableValue0.000.005800.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Length of new or upgraded local roadValue0.0037.40116.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Length of waste water pipeline laidValue0.0031.70100.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Roads constructed, non-ruralValue0.0044.30145.20
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Direct project beneficiariesValue0.0069918.00300220.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Female beneficiariesValue0.0050.0050.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Classrooms built or rehabilitatedValue0.0079.00130.00
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Length of primary roads and bridges constructed or improvedValue0.006.9029.20
    DateNovember 17, 2011October 31, 2016December 31, 2020
    Comment
  • Degree of citizen engagement - Beneficiaries involved in consultation of planning/ implementation/ evaluation of project.Value0.000.00300220.00
    DateNovember 17, 2011December 31, 2020
    Comment
  • Shared female beneficiaries involved in consultation processValue0.000.0050.00
    DateNovember 17, 2011December 31, 2020
    Comment