Financier | Commitments |
---|---|
IDA Credit | 100.00 |
Borrowing Agency | 5.00 |
P159712
Active
Dmytro Glazkov
Ministry of Economic Affairs
March 15, 2017
(as of board presentation)
June 14, 2018
January 9, 2019
US$ 105.00 million
Energy Department - Government of Sindh
2018
US$ 100.00 million
B
April 26, 2024
July 31, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 100.00 |
Borrowing Agency | 5.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 100.00 |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 105.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 15, 2020 | IDA-62580 | Int Charges | 205.37 |
Oct 15, 2020 | IDA-62580 | Int Charges | 6.70 |
Oct 15, 2020 | IDA-62580 | Int Charges | 6.70 |
Oct 15, 2020 | IDA-62580 | Int Charges | 4,435.15 |
Oct 15, 2020 | IDA-62580 | Int Charges | 4,435.15 |
Oct 15, 2020 | IDA-62580 | Int Charges | 5,726.75 |
Oct 9, 2020 | IDA-62580 | Loan Disb | 5,000,000.00 |
Feb 12, 2021 | IDA-62580 | Loan Disb | 25,821.54 |
Nov 18, 2020 | IDA-62580 | Loan Disb | 5,000,000.00 |
Jun 14, 2018 | IDA-62580 | Loan Commitment | 100,000,000.00 |
Mar 8, 2024 | IDA-62580 | Loan Disb | 1,640.10 |
Apr 15, 2024 | IDA-62580 | Int Charges | 140,354.19 |
Apr 15, 2024 | IDA-62580 | Loan Repay | 1,482,403.90 |
Apr 15, 2024 | IDA-62580 | Int Charges | 87,264.37 |
Apr 15, 2024 | IDA-62580 | Int Charges | 87,264.37 |
Feb 26, 2024 | IDA-62580 | Loan Disb | 5,000,000.00 |
Jun 21, 2024 | IDA-62580 | Loan Disb | 5,000,000.00 |
Oct 15, 2023 | IDA-62580 | Int Charges | 76,929.69 |
Oct 15, 2023 | IDA-62580 | Int Charges | 76,929.69 |
Jun 7, 2023 | IDA-62580 | Loan Disb | 500,000.00 |
Nov 6, 2023 | IDA-62580 | Loan Disb | 3,000,000.00 |
Apr 15, 2024 | IDA-62580 | Loan Repay | 29,315.44 |
Apr 19, 2024 | IDA-62580 | Loan Disb | 26,143.52 |
Feb 23, 2024 | IDA-62580 | Loan Disb | 26,124.45 |
Apr 15, 2023 | IDA-62580 | Int Charges | 70,163.47 |
Apr 15, 2023 | IDA-62580 | Int Charges | 70,163.47 |
May 30, 2023 | IDA-62580 | Loan Disb | 24,388.97 |
Jul 28, 2023 | IDA-62580 | Loan Disb | 37,385.48 |
Oct 15, 2023 | IDA-62580 | Int Charges | 2,574.57 |
Oct 15, 2023 | IDA-62580 | Loan Repay | 1,504,312.10 |
Oct 15, 2023 | IDA-62580 | Int Charges | 128,216.12 |
Dec 28, 2022 | IDA-62580 | Loan Disb | 18,919.67 |
Oct 18, 2022 | IDA-62580 | Loan Disb | 7,571.03 |
Nov 9, 2022 | IDA-62580 | Loan Disb | 5,000,000.00 |
Oct 15, 2022 | IDA-62580 | Int Charges | 3,868.23 |
Oct 15, 2022 | IDA-62580 | Int Charges | 3,868.23 |
Oct 15, 2022 | IDA-62580 | Int Charges | 50,684.53 |
Oct 15, 2022 | IDA-62580 | Int Charges | 50,684.53 |
Mar 30, 2023 | IDA-62580 | Loan Disb | 24,388.98 |
Nov 10, 2022 | IDA-62580 | Loan Disb | 18,919.66 |
Mar 10, 2023 | IDA-62580 | Loan Disb | 48,778.00 |
Apr 15, 2023 | IDA-62580 | Int Charges | 122,613.21 |
Apr 15, 2023 | IDA-62580 | Int Charges | 5,001.85 |
Apr 15, 2023 | IDA-62580 | Int Charges | 5,001.85 |
Jul 7, 2022 | IDA-62580 | Loan Disb | 19,225.00 |
Apr 15, 2022 | IDA-62580 | Int Charges | 57,973.14 |
Apr 15, 2022 | IDA-62580 | Int Charges | 57,973.14 |
Apr 15, 2022 | IDA-62580 | Int Charges | 97,169.80 |
Feb 28, 2022 | IDA-62580 | Loan Disb | 19,225.01 |
Oct 15, 2022 | IDA-62580 | Int Charges | 90,921.21 |
May 26, 2021 | IDA-62580 | Loan Disb | 35,723.68 |
Jun 3, 2021 | IDA-62580 | Loan Disb | 1,500,000.00 |
Apr 15, 2021 | IDA-62580 | Int Charges | 1,696.61 |
Apr 15, 2021 | IDA-62580 | Int Charges | 38,179.18 |
Apr 15, 2021 | IDA-62580 | Int Charges | 38,179.18 |
Apr 15, 2021 | IDA-62580 | Int Charges | 63,631.96 |
Apr 14, 2021 | IDA-62580 | Loan Disb | 52,835.94 |
Oct 1, 2021 | IDA-62580 | Loan Disb | 12,949.48 |
Oct 15, 2021 | IDA-62580 | Int Charges | 877.36 |
Oct 15, 2021 | IDA-62580 | Int Charges | 877.36 |
Oct 15, 2021 | IDA-62580 | Int Charges | 44,801.92 |
Oct 15, 2021 | IDA-62580 | Int Charges | 44,801.92 |
Oct 15, 2021 | IDA-62580 | Int Charges | 76,132.11 |
Oct 13, 2021 | IDA-62580 | Loan Disb | 3,500,000.00 |
Apr 15, 2022 | IDA-62580 | Int Charges | 328.71 |
Apr 15, 2022 | IDA-62580 | Int Charges | 328.71 |
Oct 9, 2019 | IDA-62580 | Loan Disb | 985,126.60 |
Apr 15, 2020 | IDA-62580 | Int Charges | 3,696.73 |
Apr 15, 2020 | IDA-62580 | Int Charges | 3,696.73 |
Apr 15, 2020 | IDA-62580 | Int Charges | 6,161.20 |
Apr 15, 2020 | IDA-62580 | Int Charges | 123.23 |
Apr 15, 2020 | IDA-62580 | Int Charges | 123.23 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Moderately Satisfactory | 2025-01-08 |
Project Management | Satisfactory | 2025-01-08 |
Monitoring and Evaluation | Satisfactory | 2025-01-08 |
Overall Implementation Progress (IP) | Satisfactory | 2025-01-08 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-01-08 |
Procurement | Moderately Satisfactory | 2025-01-08 |
Financial Management | Moderately Satisfactory | 2025-01-08 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with new or improved electricity service | Value | 0.00 | 1610.00 | 1200000.00 |
Date | May 14, 2018 | March 28, 2024 | December 29, 2023 | |
Comment |
Generation capacity of energy constructed or rehabilitated | Value | 0.00 | 20.00 | 420.00 |
Date | May 14, 2018 | March 28, 2024 | December 31, 2024 | |
Comment |
People provided with access to electricity under the project by household connections (grid or off-grid). | Value | 0.00 | 1610.00 | 1200000.00 |
Date | May 14, 2018 | March 28, 2024 | December 29, 2023 | |
Comment |
Renewable energy generation capacity (other than hydropower) constructed under the project | Value | 0.00 | 20.00 | 420.00 |
Date | May 14, 2018 | March 28, 2024 | December 31, 2024 | |
Comment |
Utility-scale solar power generation capacity constructed under the project | Value | 0.00 | 0.00 | 400.00 |
Date | May 14, 2018 | March 28, 2024 | December 31, 2024 | |
Comment |
Distributed solar power generation capacity constructed under the project | Value | 0.00 | 20.00 | 20.00 |
Date | May 14, 2018 | March 28, 2024 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Consumer Advocate added to Project Steering Committee | Value | No | Yes | Yes |
Date | May 14, 2018 | April 29, 2022 | December 31, 2019 | |
Comment |
Private capital mobilized | Value | 0.00 | 0.00 | 273500000.00 |
Date | May 14, 2018 | March 28, 2024 | December 29, 2023 | |
Comment |
Number of priority healthcare facilities to receive solar installations under COVID-19 emergency response | Value | 0.00 | 34.00 | 35.00 |
Date | April 1, 2020 | March 28, 2024 | October 29, 2021 | |
Comment |
Social Audit conducted at mid-term and results incorporated into project | Value | No | No | Yes |
Date | May 14, 2018 | March 28, 2024 | December 31, 2020 | |
Comment |
Female and/or disabled staff within the PMU | Value | 0.00 | 19.00 | 15.00 |
Date | May 14, 2018 | October 6, 2023 | December 29, 2023 | |
Comment |
Training event for women and/or disabled people held | Value | No | Yes | Yes |
Date | May 14, 2018 | March 24, 2023 | December 31, 2020 | |
Comment |
Completion of competitive bidding process for awarding the first 50 MW sub-project | Value | No | No | Yes |
Date | May 14, 2018 | March 28, 2024 | December 29, 2023 | |
Comment |
Identification of at least 1 MW of distributed solar PV and competitive bidding completed | Value | No | Yes | Yes |
Date | May 14, 2018 | November 26, 2021 | December 31, 2019 | |
Comment |
Female-headed households provided with solar home systems | Value | 0.00 | 82.00 | 4000.00 |
Date | May 14, 2018 | April 29, 2022 | December 29, 2023 | |