Financier | Commitments |
---|---|
Borrower/Recipient | 1680.10 |
IDA Credit | 153.00 |
P159737
Closed
Hardwick Tchale , Nghi Nguyen
SOCIALIST REPUBLIC OF VIETNAM
March 30, 2017
(as of board presentation)
June 28, 2017
May 15, 2019
US$ 1833.10 million
Ministry of Agriculture and Rural Development
2017
US$ 153.00 million
N/A
June 26, 2024
December 31, 2021
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 1680.10 |
IDA Credit | 153.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 153.00 |
IBRD + IDA Commitment | 153.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 1833.10 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 1, 2021 | IDA-61130 | Int Charges | 264.80 |
Nov 1, 2021 | IDA-61130 | Int Charges | 264.80 |
Nov 1, 2021 | IDA-61130 | Int Charges | 288,817.47 |
Apr 3, 2020 | IDA-61130 | Loan Disb | 29,198,164.00 |
Nov 13, 2020 | IDA-61130 | Int Charges | 17,802.77 |
Nov 13, 2020 | IDA-61130 | Int Charges | 17,802.77 |
Nov 13, 2020 | IDA-61130 | Int Charges | 29,671.28 |
Nov 13, 2020 | IDA-61130 | Int Charges | 114,446.32 |
Nov 13, 2020 | IDA-61130 | Int Charges | 114,446.32 |
May 1, 2024 | IDA-61130 | Int Charges | 238,537.67 |
Jun 28, 2017 | IDA-61130 | Loan Commitment | 153,000,000.00 |
Nov 13, 2020 | IDA-61130 | Int Charges | 190,743.90 |
May 1, 2024 | IDA-61130 | Int Charges | 238,537.67 |
May 1, 2024 | IDA-61130 | Loan Repay | 48,053.95 |
May 1, 2024 | IDA-61130 | Loan Repay | 2,281,726.00 |
May 1, 2024 | IDA-61130 | Int Charges | 397,562.80 |
Nov 1, 2023 | IDA-61130 | Int Charges | 410,352.88 |
Nov 1, 2023 | IDA-61130 | Int Charges | 30,714.88 |
Nov 1, 2023 | IDA-61130 | Loan Repay | 2,319,768.00 |
Nov 1, 2023 | IDA-61130 | Int Charges | 246,211.70 |
Nov 1, 2023 | IDA-61130 | Int Charges | 246,211.70 |
May 1, 2023 | IDA-61130 | Int Charges | 262,421.28 |
May 1, 2023 | IDA-61130 | Int Charges | 262,421.28 |
May 1, 2023 | IDA-61130 | Loan Repay | 52,836.08 |
May 1, 2023 | IDA-61130 | Loan Repay | 2,335,279.00 |
May 1, 2023 | IDA-61130 | Int Charges | 405,749.03 |
Nov 1, 2022 | IDA-61130 | Int Charges | 263,446.75 |
Nov 1, 2022 | IDA-61130 | Int Charges | 263,446.75 |
Nov 1, 2022 | IDA-61130 | Int Charges | 439,078.00 |
Nov 1, 2022 | IDA-61130 | Loan Repay | 27,560.92 |
Nov 1, 2022 | IDA-61130 | Loan Repay | 3,463,238.20 |
Jun 30, 2022 | IDA-61130 | Loan Cancel | 36,691,872.00 |
May 1, 2022 | IDA-61130 | Int Charges | 6,786.42 |
May 1, 2022 | IDA-61130 | Int Charges | 268,665.66 |
May 1, 2022 | IDA-61130 | Int Charges | 268,665.66 |
May 1, 2022 | IDA-61130 | Int Charges | 459,086.88 |
Dec 30, 2021 | IDA-61130 | Loan Cancel | 40,903,016.00 |
May 1, 2022 | IDA-61130 | Int Charges | 6,786.42 |
Feb 8, 2021 | IDA-61130 | Loan Disb | 47,589,040.00 |
May 1, 2021 | IDA-61130 | Int Charges | 330,089.12 |
May 1, 2021 | IDA-61130 | Int Charges | 924.00 |
May 1, 2021 | IDA-61130 | Int Charges | 924.00 |
May 1, 2021 | IDA-61130 | Int Charges | 197,129.45 |
May 1, 2021 | IDA-61130 | Int Charges | 197,129.45 |
Nov 1, 2021 | IDA-61130 | Int Charges | 288,817.47 |
Nov 1, 2021 | IDA-61130 | Int Charges | 481,803.88 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2021-12-23 |
Monitoring and Evaluation | Satisfactory | 2021-12-23 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2021-12-23 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 09-27-2022 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-28-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of ethnic minorities and women satisfied with access to, and quality of community assets or services for increasing agricultural production and livelihoods. | Value | 40.00 | 20.00 | 20.00 |
Date | August 31, 2018 | December 31, 2021 | December 31, 2021 | |
Comment |
Share of households with additional diversified income sources | Value | 60.00 | 20.00 | 20.00 |
Date | June 28, 2017 | December 31, 2021 | December 31, 2021 | |
Comment |
Number of participating provinces with an NTP-SEDP integrated planning process | Value | 0.00 | 18.00 | 0.00 |
Date | June 28, 2017 | December 31, 2021 | December 31, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of officers at the provincial, district, commune and village-level trainied in the use of the enhanced operations manual | Value | 0.00 | 50000.00 | 0.00 |
Date | August 31, 2016 | December 31, 2021 | ||
Comment |
Issuance of Policy and Guidance instruments for the NRD and SPR-P135 | Value | 0.00 | 2.00 | 0.00 |
Date | June 30, 2016 | March 28, 2019 | ||
Comment |
Percentage of infrastructure investment sub-projects implemented in compliance with the enhanced operations manual | Value | 0.00 | 90.00 | 0.00 |
Date | August 31, 2018 | December 31, 2021 | ||
Comment |
Number of monitoring reports submitted to the NTP steering committee with updated information on end of year implementation status and reporting of Program impacts at completion | Value | 0.00 | 6.00 | 0.00 |
Date | August 31, 2016 | December 31, 2021 | ||
Comment |
Number of targeted Program provinces with plans prepared in a participatory manner (bottom-up) with community involvement with effective consultations of ethnic minorities and women | Value | 0.00 | 18.00 | 0.00 |
Date | June 30, 2016 | December 31, 2021 | ||
Comment |
Number of monitoring and evaluation (M&E) frameworks developed for NTP-NRD and SPR-P135 | Value | 0.00 | 2.00 | 0.00 |
Date | August 31, 2016 | December 31, 2021 | ||
Comment |
Issuance of ed standardized procedures for scaling up climate-resilient livelihood and enterprise support established for both the NTP-NRD and SPR-P135 informed by value chain analysis | Value | None | Enhanced Operations manual drafted and finalized | |
Date | August 31, 2016 | March 28, 2019 | ||
Comment |
Number of participating provinces with an operational NRD-MIS web-based platform, including semi-annual reports with physical outputs and financial information from TABMIS | Value | 0.00 | 18.00 | 0.00 |
Date | August 31, 2016 | December 31, 2021 | ||
Comment |
Percentage of livelihood support subprojects implemented in compliance with the enhanced operations manual | Value | 0.00 | 90.00 | 0.00 |
Date | August 31, 2016 | December 31, 2021 | ||
Comment |
Number of publicly accessible websites publishing semi-annual reports on physical progress and financial information on NRD and SPR-P135 | Value | 0.00 | 2.00 | 0.00 |
Date | August 31, 2016 | December 31, 2021 | ||
Comment |
Baseline and end-line tracking survey for NRD and SPR-P135 | Value | 0.00 | 2.00 | 0.00 |
Date | August 31, 2016 | December 31, 2021 | ||
Comment |
Issuance of Policy and Guidance instruments for the NTP-NRD and SPR-P135 that include PforR agreed planning, technical and implementation improvements/reforms (Text, Custom) | Value | None | 2 Decisions issued for implementation of NTP-NRD a | |
Date | June 30, 2016 | March 28, 2019 | ||
Comment |
Issuance of enhanced operations manual for socio-economic infrastructure for both the NTP-NRD and SPR-135 | Value | None | Enhanced Operations manuals being drafted and fina | |
Date | August 31, 2016 | March 28, 2019 | ||
Comment |
Percentage of spending linked to value-chain based and climate-resilient livelihood investments (separatedly for NRD and SPR-P135) | Value | 0.00 | 30.00 | 0.00 |
Date | August 31, 2016 | December 31, 2021 | ||
Comment |