Financier | Commitments |
---|---|
IDA Credit | 40.00 |
P160801
Closed
Ousmane Deme , Fabienne Mroczka
Republic of Congo
November 21, 2016
(as of board presentation)
May 4, 2017
July 17, 2018
US$ 40.00 million
Ministry of Economy, Planning, Statistics and Regional Integration
2017
US$ 40.00 million
C
Not Applicable
December 31, 2023
TBD
BANK APPROVED
June 28, 2024
Financier | Commitments |
---|---|
IDA Credit | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 40.00 |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 40.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 14, 2023 | IDA-60230 | Loan Disb | 195,967.25 |
Dec 20, 2023 | IDA-60230 | Loan Disb | 361,747.70 |
Oct 16, 2023 | IDA-60230 | Loan Disb | 173,241.62 |
Oct 20, 2023 | IDA-60230 | Loan Disb | 145,044.40 |
Nov 15, 2023 | IDA-60230 | Loan Disb | 296,465.44 |
Nov 15, 2023 | IDA-60230 | Loan Disb | 465,485.50 |
Aug 28, 2024 | IDA-60230 | Int Charges | 685.90 |
Aug 28, 2024 | IDA-60230 | Int Charges | 685.90 |
Aug 28, 2024 | IDA-60230 | Int Charges | 1,143.17 |
Aug 28, 2024 | IDA-60230 | Int Charges | 139,431.84 |
Aug 28, 2024 | IDA-60230 | Int Charges | 139,431.84 |
Aug 28, 2024 | IDA-60230 | Int Charges | 213,441.23 |
Aug 28, 2024 | IDA-60230 | Loan Repay | 658,460.90 |
Aug 28, 2024 | IDA-60230 | Int Charges | 3,730.47 |
Nov 29, 2023 | IDA-60230 | Loan Disb | 331,565.03 |
Nov 29, 2023 | IDA-60230 | Loan Disb | 507,093.70 |
Oct 18, 2023 | IDA-60230 | Loan Disb | 152,294.56 |
Dec 13, 2023 | IDA-60230 | Loan Disb | 188,720.00 |
Dec 8, 2023 | IDA-60230 | Loan Disb | 155,643.98 |
Dec 18, 2023 | IDA-60230 | Loan Disb | 187,766.48 |
Dec 13, 2023 | IDA-60230 | Loan Disb | 409,395.84 |
Dec 11, 2023 | IDA-60230 | Loan Disb | 99,766.23 |
Dec 27, 2023 | IDA-60230 | Loan Disb | 509,308.70 |
Nov 13, 2023 | IDA-60230 | Loan Disb | 962,669.40 |
Nov 13, 2023 | IDA-60230 | Loan Disb | 517,031.72 |
Mar 23, 2023 | IDA-60230 | Loan Repay | 643,260.44 |
Mar 13, 2023 | IDA-60230 | Loan Disb | 1,085,558.40 |
Feb 15, 2023 | IDA-60230 | Loan Disb | 291,870.34 |
May 12, 2023 | IDA-60230 | Loan Disb | 652,170.50 |
Jul 31, 2023 | IDA-60230 | Loan Disb | 199,784.23 |
Jul 31, 2023 | IDA-60230 | Loan Disb | 123,884.82 |
Jun 9, 2023 | IDA-60230 | Loan Disb | 22,071.22 |
Mar 21, 2024 | IDA-60230 | Int Charges | 392.57 |
Mar 21, 2024 | IDA-60230 | Int Charges | 392.57 |
Oct 24, 2019 | IDA-60230 | Loan Disb | 61,924.54 |
Feb 27, 2020 | IDA-60230 | Loan Disb | 58,585.51 |
Jan 22, 2020 | IDA-60230 | Loan Disb | 702,286.70 |
Dec 5, 2019 | IDA-60230 | Loan Disb | 254,070.36 |
Mar 27, 2020 | IDA-60230 | Loan Disb | 16,522.50 |
Mar 27, 2020 | IDA-60230 | Loan Disb | 17,183.39 |
Nov 5, 2019 | IDA-60230 | Loan Disb | 34,440.00 |
Dec 5, 2019 | IDA-60230 | Loan Disb | 39,177.78 |
Jan 21, 2020 | IDA-60230 | Loan Disb | 29,150.00 |
Aug 14, 2018 | IDA-60230 | Loan Disb | 2,281,502.20 |
Aug 2, 2018 | IDA-60230 | Loan Disb | 1,796,443.00 |
Dec 4, 2018 | IDA-60230 | Loan Disb | 78,041.92 |
Jan 24, 2019 | IDA-60230 | Loan Disb | 263,161.84 |
Dec 20, 2018 | IDA-60230 | Loan Disb | 320,284.78 |
Dec 26, 2018 | IDA-60230 | Loan Disb | 99,723.27 |
May 14, 2019 | IDA-60230 | Loan Disb | 347,607.06 |
Mar 4, 2019 | IDA-60230 | Loan Disb | 148,813.39 |
Jul 11, 2019 | IDA-60230 | Loan Disb | 47,174.88 |
Apr 18, 2019 | IDA-60230 | Loan Disb | 445,168.10 |
Mar 12, 2019 | IDA-60230 | Int Charges | 15,057.78 |
Mar 12, 2019 | IDA-60230 | Int Charges | 15,057.78 |
Mar 12, 2019 | IDA-60230 | Int Charges | 23,683.25 |
Jun 28, 2019 | IDA-60230 | Loan Disb | 259,413.66 |
Mar 15, 2019 | IDA-60230 | Loan Disb | 251,847.30 |
Dec 28, 2020 | IDA-60230 | Loan Disb | 347,828.22 |
Mar 9, 2021 | IDA-60230 | Loan Disb | 195,915.56 |
May 11, 2021 | IDA-60230 | Loan Disb | 136,861.80 |
May 29, 2020 | IDA-60230 | Loan Disb | 15,200.01 |
Jun 10, 2020 | IDA-60230 | Loan Disb | 78,011.63 |
May 28, 2020 | IDA-60230 | Loan Disb | 49,696.61 |
Jun 8, 2020 | IDA-60230 | Loan Disb | 19,293.00 |
Jun 24, 2020 | IDA-60230 | Loan Disb | 156,556.62 |
Sep 29, 2020 | IDA-60230 | Loan Disb | 350,919.56 |
Aug 11, 2020 | IDA-60230 | Loan Disb | 127,358.63 |
Oct 13, 2020 | IDA-60230 | Loan Disb | 57,553.23 |
Jul 10, 2020 | IDA-60230 | Loan Disb | 15,546.02 |
Nov 13, 2020 | IDA-60230 | Loan Disb | 291,790.88 |
Sep 8, 2020 | IDA-60230 | Int Charges | 38,224.24 |
Mar 18, 2020 | IDA-60230 | Loan Disb | 22,750.00 |
Dec 12, 2019 | IDA-60230 | Loan Disb | 30,287.00 |
Mar 12, 2020 | IDA-60230 | Loan Disb | 23,787.75 |
Jan 6, 2020 | IDA-60230 | Loan Disb | 23,331.22 |
Feb 12, 2020 | IDA-60230 | Int Charges | 27,679.56 |
Apr 14, 2022 | IDA-60230 | Loan Disb | 736,763.00 |
Feb 22, 2022 | IDA-60230 | Loan Disb | 224,409.05 |
Dec 14, 2021 | IDA-60230 | Loan Disb | 110,957.66 |
May 16, 2022 | IDA-60230 | Loan Disb | 292,174.78 |
Jun 21, 2022 | IDA-60230 | Loan Disb | 202,677.25 |
Apr 25, 2022 | IDA-60230 | Loan Disb | 421,134.20 |
Jul 26, 2021 | IDA-60230 | Loan Disb | 106,932.98 |
Jun 23, 2021 | IDA-60230 | Loan Disb | 1,712,554.40 |
Apr 12, 2021 | IDA-60230 | Loan Disb | 359,319.20 |
Jun 10, 2021 | IDA-60230 | Loan Disb | 500,424.60 |
Jun 24, 2021 | IDA-60230 | Loan Disb | 519,820.28 |
Sep 21, 2021 | IDA-60230 | Loan Disb | 210,306.12 |
Nov 4, 2021 | IDA-60230 | Loan Disb | 298,087.40 |
Oct 19, 2021 | IDA-60230 | Loan Disb | 227,541.90 |
Sep 21, 2020 | IDA-60230 | Loan Disb | 430,524.88 |
Sep 16, 2020 | IDA-60230 | Loan Disb | 158,463.81 |
Sep 8, 2020 | IDA-60230 | Int Charges | 60,106.03 |
Sep 8, 2020 | IDA-60230 | Int Charges | 2,336.48 |
Sep 8, 2020 | IDA-60230 | Int Charges | 38,224.24 |
Feb 18, 2021 | IDA-60230 | Loan Disb | 260,915.77 |
Mar 4, 2021 | IDA-60230 | Int Charges | 3,662.47 |
Mar 4, 2021 | IDA-60230 | Int Charges | 45,649.12 |
Mar 4, 2021 | IDA-60230 | Int Charges | 73,489.95 |
Aug 21, 2020 | IDA-60230 | Loan Disb | 44,550.00 |
Mar 4, 2021 | IDA-60230 | Int Charges | 45,649.12 |
Jan 13, 2021 | IDA-60230 | Loan Disb | 212,349.25 |
Dec 9, 2020 | IDA-60230 | Loan Disb | 402,321.25 |
Aug 31, 2023 | IDA-60230 | Int Charges | 182,177.88 |
Aug 31, 2023 | IDA-60230 | Loan Repay | 649,542.70 |
Aug 31, 2023 | IDA-60230 | Int Charges | 687.70 |
Aug 31, 2023 | IDA-60230 | Int Charges | 1,146.14 |
Aug 31, 2023 | IDA-60230 | Int Charges | 110,524.33 |
Aug 31, 2023 | IDA-60230 | Int Charges | 110,524.33 |
Aug 31, 2023 | IDA-60230 | Int Charges | 687.70 |
Aug 31, 2023 | IDA-60230 | Int Charges | 20,846.78 |
Aug 3, 2023 | IDA-60230 | Loan Disb | 245,092.60 |
Sep 27, 2023 | IDA-60230 | Loan Disb | 154,754.40 |
Sep 27, 2023 | IDA-60230 | Loan Disb | 129,850.62 |
Sep 27, 2023 | IDA-60230 | Loan Disb | 322,278.22 |
Jun 12, 2023 | IDA-60230 | Loan Disb | 727,778.06 |
Aug 30, 2022 | IDA-60230 | Loan Disb | 437,354.44 |
Jan 8, 2020 | IDA-60230 | Loan Disb | 25,879.41 |
Feb 21, 2020 | IDA-60230 | Loan Disb | 38,120.79 |
Jan 8, 2020 | IDA-60230 | Loan Disb | 22,500.00 |
Feb 12, 2020 | IDA-60230 | Int Charges | 27,679.56 |
Feb 12, 2020 | IDA-60230 | Int Charges | 43,864.69 |
Mar 16, 2020 | IDA-60230 | Loan Disb | 304,888.25 |
Dec 23, 2019 | IDA-60230 | Loan Disb | 23,790.00 |
Feb 12, 2020 | IDA-60230 | Int Charges | 700.70 |
Feb 27, 2020 | IDA-60230 | Loan Disb | -23,047.05 |
Feb 20, 2020 | IDA-60230 | Loan Disb | 133,193.60 |
Feb 5, 2020 | IDA-60230 | Loan Disb | 24,468.85 |
Apr 2, 2020 | IDA-60230 | Loan Disb | 120,163.20 |
Feb 7, 2020 | IDA-60230 | Loan Disb | 23,101.05 |
Dec 19, 2019 | IDA-60230 | Loan Disb | 30,680.38 |
Feb 6, 2020 | IDA-60230 | Loan Disb | 50,324.24 |
Dec 17, 2019 | IDA-60230 | Loan Disb | 170,822.20 |
Jan 3, 2020 | IDA-60230 | Loan Disb | 68,283.75 |
Dec 17, 2019 | IDA-60230 | Loan Disb | 50,958.90 |
Jan 3, 2020 | IDA-60230 | Loan Disb | 22,649.43 |
Jan 30, 2020 | IDA-60230 | Loan Disb | 20,208.99 |
Dec 19, 2019 | IDA-60230 | Loan Disb | 23,800.00 |
Feb 5, 2020 | IDA-60230 | Loan Disb | 22,750.00 |
Dec 16, 2019 | IDA-60230 | Loan Disb | 41,800.00 |
Apr 30, 2020 | IDA-60230 | Loan Disb | 167,613.64 |
May 13, 2020 | IDA-60230 | Loan Disb | 71,613.33 |
Apr 22, 2020 | IDA-60230 | Loan Disb | 20,940.16 |
May 5, 2020 | IDA-60230 | Loan Disb | 26,032.88 |
May 5, 2020 | IDA-60230 | Loan Disb | 24,742.06 |
Jun 20, 2019 | IDA-60230 | Loan Disb | 229,803.98 |
Aug 16, 2019 | IDA-60230 | Loan Disb | 256,109.77 |
Oct 2, 2019 | IDA-60230 | Loan Disb | 225,947.70 |
Sep 10, 2019 | IDA-60230 | Int Charges | 1,393.86 |
Oct 4, 2021 | IDA-60230 | Loan Disb | 1,245,601.60 |
Sep 1, 2021 | IDA-60230 | Int Charges | 54,635.49 |
Sep 1, 2021 | IDA-60230 | Int Charges | 54,635.49 |
Sep 1, 2021 | IDA-60230 | Int Charges | 87,140.57 |
Sep 1, 2021 | IDA-60230 | Int Charges | 2,569.22 |
Sep 14, 2021 | IDA-60230 | Loan Disb | 138,314.70 |
Apr 14, 2022 | IDA-60230 | Loan Disb | 494,627.03 |
Dec 28, 2021 | IDA-60230 | Loan Disb | 293,797.62 |
Dec 28, 2021 | IDA-60230 | Loan Disb | 238,857.52 |
Dec 21, 2022 | IDA-60230 | Loan Disb | 666,409.06 |
Oct 14, 2022 | IDA-60230 | Loan Disb | 235,928.81 |
Jan 3, 2023 | IDA-60230 | Loan Disb | 541,836.80 |
Nov 23, 2022 | IDA-60230 | Loan Disb | 441,962.30 |
Sep 13, 2022 | IDA-60230 | Loan Disb | 571,133.00 |
Feb 1, 2023 | IDA-60230 | Loan Repay | 14,994.08 |
Jan 20, 2023 | IDA-60230 | Loan Disb | 888,407.60 |
Apr 28, 2023 | IDA-60230 | Loan Disb | 1,057,321.10 |
Mar 23, 2023 | IDA-60230 | Int Charges | 96,836.57 |
Mar 23, 2023 | IDA-60230 | Int Charges | 96,836.57 |
Mar 23, 2023 | IDA-60230 | Int Charges | 140,269.25 |
Apr 25, 2022 | IDA-60230 | Loan Disb | 724,501.56 |
Apr 25, 2022 | IDA-60230 | Loan Disb | 486,395.34 |
Apr 13, 2022 | IDA-60230 | Loan Disb | 462,728.72 |
Apr 18, 2022 | IDA-60230 | Loan Disb | 316,232.44 |
Jul 19, 2022 | IDA-60230 | Loan Disb | 549,228.90 |
Aug 1, 2022 | IDA-60230 | Int Charges | 132,663.40 |
Aug 22, 2022 | IDA-60230 | Loan Disb | 423,702.97 |
Aug 22, 2022 | IDA-60230 | Loan Disb | 676,199.25 |
Jan 26, 2022 | IDA-60230 | Loan Disb | 372,119.62 |
Aug 1, 2022 | IDA-60230 | Loan Repay | 647,007.90 |
Aug 1, 2022 | IDA-60230 | Int Charges | 79,598.03 |
Aug 1, 2022 | IDA-60230 | Int Charges | 79,598.03 |
Aug 1, 2022 | IDA-60230 | Int Charges | 714.27 |
Feb 28, 2022 | IDA-60230 | Int Charges | 3,840.43 |
Feb 28, 2022 | IDA-60230 | Int Charges | 68,190.58 |
Feb 28, 2022 | IDA-60230 | Int Charges | 68,190.58 |
Feb 28, 2022 | IDA-60230 | Int Charges | 112,898.91 |
Mar 11, 2024 | IDA-60230 | Loan Disb | 187,766.48 |
May 4, 2017 | IDA-60230 | Loan Commitment | 40,000,000.00 |
May 17, 2024 | IDA-60230 | Loan Disb | -348.59 |
Feb 12, 2024 | IDA-60230 | Loan Disb | -187,708.48 |
Mar 21, 2024 | IDA-60230 | Int Charges | 654.27 |
Mar 21, 2024 | IDA-60230 | Int Charges | 125,782.45 |
Mar 21, 2024 | IDA-60230 | Int Charges | 125,782.45 |
Mar 21, 2024 | IDA-60230 | Int Charges | 205,956.27 |
Mar 21, 2024 | IDA-60230 | Int Charges | 2,030.03 |
Mar 21, 2024 | IDA-60230 | Loan Repay | 649,762.50 |
Sep 10, 2019 | IDA-60230 | Int Charges | 34,091.79 |
Sep 10, 2019 | IDA-60230 | Int Charges | 20,875.23 |
Sep 10, 2019 | IDA-60230 | Int Charges | 20,875.23 |
Aug 6, 2019 | IDA-60230 | Loan Disb | 50,574.77 |
Oct 23, 2019 | IDA-60230 | Loan Disb | 243,977.31 |
Sep 16, 2019 | IDA-60230 | Loan Disb | 61,505.81 |
Oct 25, 2019 | IDA-60230 | Loan Disb | 20,074.00 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-04-25 |
Financial Management | Moderately Satisfactory | 2024-04-25 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-04-25 |
Project Management | Moderately Satisfactory | 2024-04-25 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-04-25 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-04-25 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2024 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 11-26-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Modest | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PDO 3: Active civilian civil servants at central and deconcentrated levels registered in the HRMIS | Value | 0.00 | 60.00 | 60.00 |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
PDO 4: Number of citizens reached through workshops and awareness raising efforts on budget transparency in priority sectors (health, and education) by CSOs | Value | 0.00 | 5000.00 | 5000.00 |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
PDO 1: Development of an integrated, streamlined and secure tax management system (process) | Value | No effective and integrated tax management system | 50 % of registered large taxpayers filing and payi | 50 % of registered large taxpayers filing and payi |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
PDO 2: Share of budget allocated to new investment projects, which have been selected based on the PIM evaluation process, in priority NDP sectors | Value | 0.00 | 30.00 | 30.00 |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Ministries with strategic plans that are aligned with medium-term budgets | Value | 0.00 | 8.00 | 8.00 |
Date | December 31, 2016 | December 31, 2023 | December 31, 2023 | |
Comment |
Implementation of a digitalized Human Resource Management (HRM) system (SIGRHE) (process) | Value | No digital HRM system in place | SIGRHE civil servant registry is interfaced with t | SIGRHE civil servant registry is interfaced with t |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
CCDB capacity and institutional framework are strengthened (process) | Value | CCDB lacking the capacity and regulatory framework | Amended CCDB legal and regulatory framework is dra | Amended CCDB legal and regulatory framework is dra |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
Number of civil servants, parliament and CSOs members that are trained on auditing (including ISSAI/INTOSAI) | Value | 0.00 | 120.00 | 120.00 |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
Strategic revenue mobilization roadmap adoption and implementation (process) | Value | No strategic revenue management or tax administrat | TADAT self assessment conducted Improvement in 2 K | TADAT self assessment conducted Improvement in 2 K |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
Percentage of women trained | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Improved integrity of the taxpayer registry (process) | Value | No centralized taxpayer registry | At least 50 percent of the large taxpayers estimat | At least 50 percent of the large taxpayers estimat |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
Budget execution monitoring reports published by CSOs on education and health sectors (number) | Value | 0.00 | 3.00 | 3.00 |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
Ministries using the new selection procedure for investment projects (number) | Value | 0.00 | 3.00 | 3.00 |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
Implementation of EITI work program (process) | Value | EITI reports not published in timely fashion | Timely publication of EITI report and adoption of | Timely publication of EITI report and adoption of |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |
Civil society training and workshops conducted by the EITI Secretariat (Transparency in the EI, Mining sector diagnosis, Beneficiary ownership) | Value | 0.00 | 3.00 | 3.00 |
Date | October 29, 2021 | December 31, 2023 | December 31, 2023 | |
Comment |