Financier | Commitments |
---|---|
IDA Credit | 13.40 |
P160964
Closed
Maria Mogollon , Kobina Daniel
Ministry of Finance
December 29, 2016
(as of board presentation)
March 24, 2017
N/A
US$ 14.50 million
Ministry of Trade & Industry
2017
US$ 13.40 million
B
Not Applicable
June 30, 2022
Yes
BANK APPROVED
February 27, 2020
Financier | Commitments |
---|---|
IDA Credit | 13.40 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 13.40 |
IBRD + IDA Commitment | 13.40 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 14.50 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of non-textile investment projects facilitated over the 5-year project duration. | Value | 0.00 | 3.00 | 6.00 |
Date | December 31, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Jobs in the horticulture and handicraft sectors | Value | 1160.00 | 1160.00 | 1315.00 |
Date | December 31, 2016 | December 31, 2016 | June 30, 2022 | |
Comment |
Increase in domestic enterprises registered and operational in non-textile sectors | Value | 11402.00 | 54.00 | 60.00 |
Date | September 4, 2013 | June 30, 2016 | December 31, 2018 | |
Comment |
Implemented reforms supporting private sector development | Value | 0.00 | 2.00 | 5.00 |
Date | December 31, 2013 | December 31, 2016 | December 31, 2021 | |
Comment |
Client satisfaction with selected government-to-business services | Value | 0.00 | 0.00 | 0.00 |
Date | June 30, 2022 | |||
Comment |
Direct project beneficiaries | Value | 0.00 | 110189.00 | 220000.00 |
Date | September 4, 2013 | December 31, 2016 | June 30, 2022 | |
Comment | Decline is due to an improvement in methodology; project beneficiaries from the credit bureau now reflects the number of peoplecovered, rather than number of loans/accounts |
Female beneficiaries | Value | 0.00 | 24.00 | 22.00 |
Date | September 4, 2013 | December 31, 2016 | June 30, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 119809.00 | 120000.00 |
Date | September 4, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Days required to obtain a construction permit from the Maseru City Council | Value | 106.00 | 106.00 | 30.00 |
Date | September 4, 2013 | December 31, 2016 | December 31, 2021 | |
Comment |
Adult population covered by the Credit Bureau | Value | 0.00 | 7.10 | 13.00 |
Date | September 4, 2013 | October 26, 2016 | December 31, 2021 | |
Comment |
Registered lodging operations under the star grading system | Value | 7.00 | 14.00 | 40.00 |
Date | September 4, 2013 | June 30, 2016 | June 30, 2022 | |
Comment |
Tourism information center established and operational | Value | No | No | Yes |
Date | September 4, 2013 | December 31, 2016 | June 30, 2022 | |
Comment |
Revenue generated by commercial horticulture farms (maloti) | Value | 38606.00 | 79264.00 | 1948748.00 |
Date | April 30, 2014 | June 30, 2016 | December 31, 2021 | |
Comment | Decrease in revenue due to the recent drought. |
Percentage increase in sales of LEAP supported firms | Value | 0.00 | 17.00 | 10.00 |
Date | September 4, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Female beneficiaries | Value | 0.00 | 21.00 | 22.00 |
Date | September 4, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Agencies connected to the Trade Automation System | Value | 0.00 | 0.00 | 4.00 |
Date | December 31, 2013 | December 31, 2016 | June 30, 2022 | |
Comment |
Amount of funds disbursed to businesses through LEAP | Value | 56422.00 | 745230.00 | 663242.00 |
Date | December 31, 2013 | December 31, 2016 | June 30, 2022 | |
Comment | Represents support provided by the GoL in the window between PSCED-I closing (June 30, 2013) and PSCED-II effectiveness (January 9,2014) |