Alliance for Education Quality Project

Abstract*

The development objective of the Alliance for Education Quality Project for Nicaragua is to improve: (a) teacher practices for participating teachers in preschool, primary, and secondary education nationwide; and (b) physical learning conditions in targeted schools. The project comprises of three components. The first component, improving teacher practices for participating teachers in preschool, primary, and secondary education nationwide, seeks...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to improve (a) teacher practices for participating teachers in preschool, primary and secondary education nationwide, and (b) physical learning conditions in targeted schools.

Key Details

Project Details

  • P161029

  • Closed

  • Marcelo Becerra

  • Republic of Nicaragua

  • Nicaragua

  • December 14, 2016

  • (as of board presentation)

    April 13, 2017

  • July 17, 2017

  • US$ 55.00 million

  • B

  • October 30, 2023

  • April 30, 2023

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 55.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 55.00
IBRD + IDA Commitment 55.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 55.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 15, 2021 IDA-60150 Loan Disb 2,984,776.00
Apr 15, 2021 IDA-60150 Int Charges 20,397.84
Apr 15, 2021 IDA-60150 Int Charges 250,041.38
Apr 15, 2021 IDA-60150 Int Charges 250,041.38
Apr 15, 2021 IDA-60150 Int Charges 234,732.72
Oct 15, 2021 IDA-60150 Int Charges 304,346.40
Oct 15, 2021 IDA-60150 Int Charges 304,346.40
Oct 15, 2021 IDA-60150 Int Charges 285,712.97
Feb 7, 2020 IDA-60150 Loan Disb 7,220,444.00
Apr 15, 2020 IDA-60150 Int Charges 3,562.51
Apr 15, 2020 IDA-60150 Int Charges 112,926.61
Apr 15, 2020 IDA-60150 Int Charges 112,926.61
Apr 15, 2020 IDA-60150 Int Charges 106,012.72
Jul 20, 2020 IDA-60150 Loan Disb 1,630,462.10
Oct 15, 2020 IDA-60150 Int Charges 167,541.11
Oct 15, 2020 IDA-60150 Int Charges 167,541.11
Oct 15, 2020 IDA-60150 Int Charges 136,885.64
Sep 11, 2020 IDA-60150 Loan Disb 7,578,149.50
Jun 26, 2019 IDA-60150 Loan Disb 1,484,031.10
Apr 15, 2019 IDA-60150 Int Charges 45,073.92
Apr 15, 2019 IDA-60150 Int Charges 51,261.67
Apr 15, 2019 IDA-60150 Int Charges 51,261.67
Mar 5, 2019 IDA-60150 Loan Disb 962,929.25
Aug 30, 2019 IDA-60150 Loan Disb 1,000,000.00
Oct 15, 2019 IDA-60150 Int Charges 3,049.27
Oct 15, 2019 IDA-60150 Int Charges 71,077.04
Oct 15, 2019 IDA-60150 Int Charges 71,077.04
Oct 15, 2019 IDA-60150 Int Charges 63,162.86
Dec 11, 2019 IDA-60150 Loan Disb 2,367,183.80
Apr 15, 2018 IDA-60150 Int Charges 22,033.69
Apr 15, 2018 IDA-60150 Int Charges 22,033.69
Jun 14, 2018 IDA-60150 Loan Disb 973,408.70
Dec 11, 2018 IDA-60150 Loan Disb 209,220.90
Dec 12, 2018 IDA-60150 Loan Disb 333,121.53
Feb 8, 2019 IDA-60150 Loan Disb 1,000,000.00
Oct 15, 2018 IDA-60150 Int Charges 41,875.49
Oct 15, 2018 IDA-60150 Int Charges 41,875.49
Oct 15, 2018 IDA-60150 Int Charges 39,311.69
Apr 13, 2017 IDA-60150 Loan Commitment 55,000,000.00
Oct 15, 2023 IDA-60150 Int Charges 383,923.75
Sep 8, 2023 IDA-60150 Loan Cancel 209,065.94
Apr 15, 2024 IDA-60150 Loan Repay 903,194.25
Apr 15, 2024 IDA-60150 Int Charges 376,032.84
Apr 15, 2024 IDA-60150 Int Charges 376,032.84
Apr 15, 2024 IDA-60150 Int Charges 353,010.44
Apr 15, 2024 IDA-60150 Int Charges -107.43
Apr 15, 2024 IDA-60150 Int Charges 107.43
Apr 15, 2024 IDA-60150 Loan Repay 612.38
Sep 8, 2023 IDA-60150 Loan Disb -209,065.94
Oct 15, 2023 IDA-60150 Int Charges 360,418.20
Oct 15, 2023 IDA-60150 Int Charges 712.50
Oct 15, 2023 IDA-60150 Loan Repay 907,500.00
Oct 15, 2023 IDA-60150 Int Charges 383,923.75
Oct 15, 2022 IDA-60150 Loan Repay 907,500.00
Oct 15, 2022 IDA-60150 Int Charges 377,828.62
Oct 15, 2022 IDA-60150 Int Charges 377,828.62
Oct 15, 2022 IDA-60150 Int Charges 354,696.22
Dec 7, 2022 IDA-60150 Loan Disb 500,000.00
Apr 15, 2023 IDA-60150 Int Charges 386,540.56
Apr 15, 2023 IDA-60150 Int Charges 386,540.56
Mar 27, 2023 IDA-60150 Loan Disb 500,000.00
Apr 15, 2023 IDA-60150 Loan Repay 907,500.00
Apr 15, 2023 IDA-60150 Int Charges 362,162.34
Dec 2, 2021 IDA-60150 Loan Disb 7,379,285.00
Apr 15, 2022 IDA-60150 Int Charges 330,200.00
Jun 27, 2022 IDA-60150 Loan Disb 4,218,114.50
Apr 15, 2022 IDA-60150 Loan Repay 907,500.00
Apr 15, 2022 IDA-60150 Int Charges 351,734.78
Apr 15, 2022 IDA-60150 Int Charges 351,734.78
Dec 22, 2020 IDA-60150 Loan Disb 2,000,000.00
Feb 5, 2021 IDA-60150 Loan Disb 7,615,873.00
Apr 15, 2018 IDA-60150 Int Charges 20,684.70
Dec 28, 2017 IDA-60150 Loan Disb 3,043,000.00
Dec 28, 2017 IDA-60150 Loan Disb 1,400,000.00
Dec 28, 2017 IDA-60150 Loan Disb 600,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2023-04-30
Monitoring and Evaluation Satisfactory 2023-04-30
Overall Implementation Progress (IP) Satisfactory 2023-04-30
Progress towards achievement of PDO Satisfactory 2023-04-30
Procurement Satisfactory 2023-04-30
Financial Management Satisfactory 2023-04-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 10-30-2023
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-03-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • PDOI1. Number of participating primary and secondary education teachers with improved teaching practices.Value0.003141.002735.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • PDOI2. Percentage of preschool teachers with desired teaching practices.Value54.0098.7060.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • PDOI3. Percentage of Project-supported schools meeting minimal physical quality standards.Value0.00100.0080.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • Sub-PDOI1a. Number of participating primary school teachers with improved teaching practicesValue0.000.00469.00
    DateDecember 1, 2016March 19, 2018
    Comment
  • Sub-PDOI1b. Number of participating secondary school teachers with improved teaching practices.Value0.000.0078.00
    DateDecember 1, 2016March 19, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • IRI9. Number of in-service preschool and primary school teachers that received textbooks, teacher's guides and other educational supplies (including equipment).Value0.0032483.0020000.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI10. Learning outcome results in student or child development assessment analyzed and disseminated nationwide.ValueYes (TERCE report)ERCE, National, and Early Childhood Development asBaseline for Preschool Education (ERCE socializati
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI11. Teacher training and teacher mentoring programs whose design or implementation have been adjusted according to student and child development assessments, and teacher mentoring results.ValueNot startedReport/ summary on how assessments and results werReport/ summary on how assessments and results wer
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI12. Study to assess the effectiveness of the TMP for primary school teachersValueNot startedFinal Report completed and satisfactory to the BanBaseline report
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI13. Number of teachers that provide qualitative feedback on quality of classroom observation/mentoring during the mentoring sessions.Value0.003699.00625.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI 14. Number of mentoring visits carried out by education personnel as part of the In-Service Training Program for Preschool TeachersValue0.00443.000.00
    DateDecember 11, 2020August 9, 2023
    Comment
  • IRI 15. Percentage of primary and secondary teachers belonging to indigenous and Afro-descendant groups that receive mentoringValue0.0011.005.00
    DateDecember 11, 2020August 9, 2023July 31, 2021
    Comment
  • IRI 16. Number of school principals trained under the adjusted In-Service Training ProgramValue0.001627.000.00
    DateDecember 11, 2020August 9, 2023
    Comment
  • Sub-IRI 16a. Percentage of trained school principals under the adjusted In-Service Training Program who are womenValue0.0060.000.00
    DateDecember 11, 2020August 9, 2023
    Comment
  • Students benefiting from direct interventions to enhance learningValue0.001113627.00440000.00
    DateDecember 11, 2020August 9, 2023July 31, 2021
    Comment
  • Students benefiting from direct interventions to enhance learning - FemaleValue0.000.000.00
    Date
    Comment
  • IRI22. Development and implementation of the first phase of the School Infrastructure Planning System (SIGIE)ValueNot startedFirst phase of automatization of SIGIE is completeWorkplan, Software Acceptance Requirements and Cri
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI17. Percentage of targeted schools included in a National Program aimed at involving the community in school maintenance.Value0.00100.0080.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI1. Number of in-service preschool teachers certified in the Preschool Teacher Training ProgramValue0.009498.005500.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI 23. Percentage of communications received through the Grievance Redress Mechanism (GRM) resolved according to the agreed procedureValue0.00100.0090.00
    DateJuly 31, 2017August 9, 2023July 31, 2021
    Comment
  • IRI18. Update of Standards and Design Criteria for School FacilitiesValueNoYesNo
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • Sub-IRI1a. Percentage of female in-service preschool teachers certified in the Preschool Teacher Training Program (Percentage)Value0.0098.001.00
    DateJanuary 6, 2021August 9, 2023July 31, 2021
    Comment
  • IRI 19. Percentage of Project-supported schools located in indigenous territoriesValue0.0019.000.00
    DateDecember 11, 2020August 9, 2023
    Comment
  • IRI2. Number of education personnel trained in teacher mentoring.Value0.00540.000.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI 20. Number of Project-supported schools with improvements to Water, Sanitation, and Hygiene systems to meet minimum conditions to enhance learningValue0.0060.0060.00
    DateDecember 11, 2020August 9, 2023December 22, 2022
    Comment
  • IRI3. Number of in-service basic education teachers who received at least three mentoring visits.Value0.003997.002500.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI 21. Number of preschool classrooms rehabilitated and equipped under the Project.Value0.0023.0023.00
    DateDecember 11, 2020August 9, 2023December 22, 2022
    Comment
  • IRI4. Number of in-service primary school teachers with gender-inclusive teaching practices.Value0.001511.00375.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI5. Percentage of in-service basic education teachers trained in two 'Strategies for improving teacher practices' EPI workshops.Value0.0088.0080.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI6. Number of in-service primary school teachers certified in the Teacher Training Program.Value0.0023936.0014500.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI7. Number of mentoring visits carried out by pedagogical counselors as part of the Primary Teacher Training Program.Value0.008321.002520.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment
  • IRI8. Number of in-service preschool and primary school teachers that received workbooks, planning charts and fungible materials.Value0.0031483.0020000.00
    DateDecember 1, 2016August 9, 2023July 31, 2021
    Comment