Tina River Hydropower Development Project

Development Objective

The project development objective (PDO) is to increase the share of renewable energy through hydropower in Solomon Islands.

Key Details

Project Details

  • P161319

  • Active

  • Renee Berthome , Nicolas Sans

  • Solomon Islands

  • Solomon Islands

  • January 27, 2017

  • (as of board presentation)

    June 20, 2017

  • March 9, 2016

  • US$ 240.48 million

  • Tina Hydropower Limited,Solomon Islands Electricity Authority,Solomon Islands Ministry of Mines, Energy and Rural Electrification

  • East Asia and Pacific

  • 2017

  • US$ 208.93 million

  • A

  • May 9, 2024

  • December 15, 2025

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Australia-Pacific Islands Partnership Trust Fund 12.70
Green Climate Fund 86.00
IDA Credit 23.38
ABU DHABI: Abu Dhabi Fund for Arab Economic Development 15.00
KOREA, Rep of: Economic Development Cooperation Fund 31.60
Borrower/Recipient 22.15
IDA Grant 10.26
Private Commercial Sources (identified) 10.80
Asian Development Bank 30.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 33.63
IBRD + IDA Commitment 33.63
Lending Instrument
Grant Amount 175.30
Total Project Cost** 240.48

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 11, 2024 IDA-60860 Loan Disb 4,997,612.50
Nov 25, 2019 TF-B1492 Loan Commitment 35,000,000.00
Aug 15, 2024 IDA-60860 Loan Disb 7,799.92
Aug 15, 2024 IDA-60860 Int Charges 7,799.92
Sep 25, 2023 IDA-D2020 Loan Disb 73,544.93
Aug 10, 2023 IDA-D2020 Loan Disb 120,306.19
May 30, 2023 IDA-D2020 Loan Disb 137,029.38
Jul 24, 2024 IDA-D2020 Loan Disb 116,342.66
Dec 4, 2023 IDA-D2020 Loan Disb 91,871.29
May 28, 2024 IDA-D2020 Loan Disb 82,088.24
Aug 21, 2024 IDA-D2020 Loan Disb 158,195.38
Mar 16, 2022 IDA-D2020 Loan Disb 144,453.90
Nov 23, 2021 IDA-D2020 Loan Disb 155,215.73
Oct 15, 2021 IDA-D2020 Loan Disb 86,823.98
Aug 16, 2021 IDA-D2020 Loan Disb 1,710,353.40
May 11, 2022 IDA-D2020 Loan Disb 147,569.36
Sep 1, 2022 IDA-D2020 Loan Disb 84,818.98
Nov 10, 2022 IDA-D2020 Loan Disb 172,260.20
Jan 19, 2023 IDA-D2020 Loan Disb 76,136.67
Mar 7, 2023 IDA-D2020 Loan Disb 47,837.66
Jan 10, 2024 IDA-D2020 Loan Disb 166,103.12
May 22, 2020 IDA-D2020 Loan Disb 91,951.39
Sep 24, 2020 IDA-D2020 Loan Disb 165,000.30
Aug 25, 2020 IDA-D2020 Loan Disb 20,379.75
Sep 10, 2020 IDA-D2020 Loan Disb 1,073,321.20
Nov 30, 2020 IDA-D2020 Loan Disb 2,504,747.20
Nov 30, 2020 IDA-D2020 Loan Disb 50,384.33
Jan 13, 2021 IDA-D2020 Loan Disb 189,052.45
Jun 17, 2021 IDA-D2020 Loan Disb 85,948.31
Sep 16, 2019 IDA-D2020 Loan Disb 70,775.81
Aug 23, 2019 IDA-D2020 Loan Disb 75,913.61
Dec 20, 2019 IDA-D2020 Loan Disb 2,066,578.00
Jan 24, 2020 IDA-D2020 Loan Disb 52,294.36
Mar 16, 2020 IDA-D2020 Loan Disb 170,556.08
Mar 7, 2019 IDA-D2020 Loan Disb 200,000.00
Jun 20, 2017 IDA-60860 Loan Commitment 23,375,000.00
Jun 20, 2017 IDA-D2020 Loan Commitment 10,255,000.00
Nov 25, 2019 TF-B1491 Loan Commitment 35,000,000.00
Jun 27, 2024 IDA-60860 Loan Disb 668,614.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2024-12-18
Overall Safeguards Rating Moderately Unsatisfactory 2024-12-18
Procurement Moderately Satisfactory 2024-12-18
Progress towards achievement of PDO Moderately Satisfactory 2024-12-18
Project Management Moderately Satisfactory 2024-12-18
Financial Management Moderately Satisfactory 2024-12-18
Monitoring and Evaluation Moderately Satisfactory 2024-12-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Electricity generated by the Project (Gigawatt-hour (GWh), Custom)Value0.000.0078.35
    DateJune 30, 2017March 29, 2024December 15, 2025
    Comment
  • Hydropower generation capacity constructed under the project (Megawatt, Corporate Breakdown)Value0.000.0015.00
    DateJune 30, 2017March 29, 2024December 15, 2025
    Comment
  • Share of hydropower in the generation mix (Percentage, Custom)Value0.000.0068.00
    DateJune 30, 2017March 29, 2024December 15, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Net greenhouse gas (GHG) reduction (tCO2-eq per year) (Tones/year, Custom)Value0.000.0049500.00
    DateJune 30, 2017March 29, 2024December 15, 2025
    Comment
  • Roads constructed, Rural (Kilometers, Custom)Value0.000.0018.70
    DateJune 30, 2017March 29, 2024December 31, 2020
    Comment
  • Transmission lines constructed or rehabilitated under the project (Kilometers, Custom)Value0.000.0023.00
    DateJune 30, 2017March 29, 2024October 31, 2023
    Comment
  • Increase in project-affected community household consumption before and after hydropower facility commissioning (Percentage, Custom)Value0.000.0020.00
    DateJune 30, 2017March 29, 2024December 15, 2025
    Comment
  • Private Capital Mobilized (Amount(USD), CustomValue0.009962520.0010800000.00
    DateJune 30, 2017March 29, 2024December 15, 2025
    Comment
  • Quarterly meetings of the Gender Action Plan Steering Committee taking place in a year (Number, Custom)Value0.0016.0026.00
    DateJune 30, 2017March 29, 2024December 15, 2025
    Comment
  • Fuel savings (million liters per year) (Liters (Million), Custom)Value0.000.0018.00
    DateJune 30, 2017March 29, 2024December 15, 2025
    Comment
  • Women who are satisfied with the way in which their individual Tribal Cooperative account funds, and those of their children, are spent (Percentage, Custom)Value0.000.0075.00
    DateJune 30, 2017March 29, 2024December 15, 2025
    Comment
  • Completion of semi-annual, independent social and environmental monitoring reports (Number, Custom)Value0.008.0012.00
    DateJune 30, 2017March 29, 2024December 15, 2025
    Comment
  • Preparation of Protected Area Management Plan and Budget by upper catchment communities (Yes/No, Custom)ValueNoNoYes
    DateJune 30, 2017March 29, 2024December 19, 2022
    Comment
  • Completion of Dam Safety Advisory Panel annual reviews (Number, Custom)Value0.003.006.00
    DateJune 30, 2017March 29, 2024December 15, 2025
    Comment