| Financier | Commitments | 
|---|---|
| IDA Credit | 9.50 | 
| IDA Grant | 4.60 | 
P161454
Closed
Dung Hoang , Pierre Graftieaux
Ministry of Finance and Economic Management
November 8, 2016
(as of board presentation)
January 10, 2017
N/A
US$ 14.10 million
N/A
2017
US$ 14.10 million
N/A
Not Applicable
December 31, 2019
TBD
BANK APPROVED
July 15, 2021
| Financier | Commitments | 
|---|---|
| IDA Credit | 9.50 | 
| IDA Grant | 4.60 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | N/A | 
| IDA Commitment | 14.10 | 
| IBRD + IDA Commitment | 14.10 | 
| Lending Instrument | |
|---|---|
| Grant Amount | N/A | 
| Total Project Cost** | 14.10 | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Regulatory certification of safety and security at Bauerfield (VLI) maintained | Value | VLI certified | VLI Certified | Re-validation of certification of VLI in accordanc | 
| Date | March 5, 2015 | August 31, 2016 | June 30, 2019 | |
| Comment | 
| Modernization of air traffic management achieved | Value | No VSAT or ADS-B | ADS-B ground stations procured and due to arrive e | VSAT or ADS-B operational | 
| Date | March 5, 2015 | August 31, 2016 | June 30, 2018 | |
| Comment | 
| Regional safety and security levy for departing international passengers implemented | Value | No levy | No levy. Legislation for implementation of levy cu | AU$5 collected from each departing international p | 
| Date | March 5, 2015 | August 31, 2016 | June 30, 2016 | |
| Comment | 
| State requirements for safety measured by Universal Safety Oversight Audit Programme (USOAP) reaches global ICAO average | Value | 47.51 | 47.51 | 41.38 | 
| Date | March 5, 2015 | August 31, 2016 | June 30, 2019 | |
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Navigation and safety aids in line with implementation schedule | Value | 0.00 | 0.00 | 100.00 | 
| Date | March 5, 2015 | August 31, 2016 | June 30, 2017 | |
| Comment | 
| Repairs to Bauerfieled, Whitegrass and Pekoa Airport pavements in line with implementation schedule | Value | 0.00 | 0.00 | 100.00 | 
| Date | March 5, 2015 | June 30, 2018 | ||
| Comment | 
| Fire Standards at VLI Achieved | Value | Category 6 | Category 6 | Category 8 | 
| Date | March 5, 2015 | August 31, 2016 | June 30, 2018 | |
| Comment | 
| Airport Master Plan and Aviation Sector Strategy in line with implementation schedule | Value | 0.00 | 0.00 | 100.00 | 
| Date | March 5, 2015 | August 31, 2016 | June 30, 2018 | |
| Comment | 
| Successful implementation of agreed training plan | Value | No Training Plan | No training plan | Training Plan completed | 
| Date | March 5, 2015 | August 31, 2016 | December 31, 2017 | |
| Comment | 
| Grievance registered related to delivery of project benefits by gender that are actually addressed | Value | 0.00 | 0.00 | 100.00 | 
| Date | March 5, 2015 | August 31, 2016 | December 31, 2017 | |
| Comment | 
| Grievances responded and/or resolved within the stipulated services standards for response times | Value | 0.00 | 0.00 | 75.00 | 
| Date | March 5, 2015 | August 31, 2016 | December 31, 2017 | |
| Comment | 
| Project-supported organization(s) publishing periodic reports on GRM and how issues were resolved | Value | No | No | Yes | 
| Date | March 5, 2015 | August 31, 2016 | December 31, 2017 | |
| Comment |