Financier | Commitments |
---|---|
IDA Credit | 18.00 |
IDA Grant | 7.00 |
P161630
Closed
Pierre Boulenger , Christopher Trimble
Ministry of Economic and Regional Integration
April 9, 2017
(as of board presentation)
May 30, 2017
N/A
US$ 25.00 million
PHIMP
2017
US$ 25.00 million
B
December 15, 2023
June 30, 2024
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 18.00 |
IDA Grant | 7.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 25.00 |
IBRD + IDA Commitment | 25.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 25.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Non-revenue water | Value | 47.10 | 58.00 | 40.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment |
Network transmission and distribution losses | Value | 46.60 | 36.90 | 30.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment |
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 0.00 | 134100.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment | [= (8) x 8 + (10) x 300] â One household is composed of 8 persons (2009 census) and one public standpost provides water to 300people. | Target in the original Project was 76,800 |
Annual electricity generated | Value | 22.94 | 22.94 | 35.00 |
Date | March 26, 2014 | April 21, 2017 | June 30, 2018 | |
Comment |
Number of people benefiting from enhanced water services under the project | Value | 0.00 | 42000.00 | 80000.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 42000.00 | 342100.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment | [= (1) + (3)] Note: (2) is excluded to avoid double counting, as existing water customers are also electricity customers.[ = 51%] â based on 2009 census | Target in the original Project was 284,800 |
Number of people benefitting from enhanced electricity services under the project | Value | 0.00 | 0.00 | 208000.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment |
Female beneficiaries | Value | 51.00 | 0.00 | 51.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of water service connections equipped with meters | Value | 70.40 | 33.80 | 90.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment |
Percentage of electricity connections equipped with pre-payment meters | Value | 59.50 | 42.40 | 95.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment |
Services Contract executed and implemented | Value | No | No | Yes |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment |
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 0.00 | 12600.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment | Target in the original Project was 6600 |
Piped household water connections that are benefiting from rehabilitation works undertaken by the project | Value | 0.00 | 0.00 | 10000.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 0.00 | 111.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment | Target in the original Project was 80 |
Distribution lines constructed or rehabilitated under the project | Value | 0.00 | 0.00 | 85.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment | [= MT network + BT network] | Target in the original Project was 12 |
Operating time of ABC generators | Value | 9176.00 | 9176.00 | 14000.00 |
Date | March 26, 2014 | April 21, 2017 | June 30, 2018 | |
Comment |
Prepayment meters installed under the project | Value | 0.00 | 2758.00 | 21030.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment | Target in the original Project was 11,030 |
Distribution lines rehabilitated under the project | Value | 0.00 | 0.00 | 0.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment | Target in the original Project was 12 |
Citizen engagement: percentage of complaints to the call center that are satisfactorily addressed | Value | 0.00 | 0.00 | 80.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment |
Collection rate of electricity and water bills (private customers) | Value | 0.00 | 53.00 | 80.00 |
Date | March 26, 2014 | April 21, 2017 | December 31, 2021 | |
Comment |