Financier | Commitments |
---|---|
IDA Grant | 20.00 |
P162245
Closed
Michael Thibert , Nash Eyison, Steven Clarke
Ministry of Economy, Planning, and International Cooperation
November 3, 2017
(as of board presentation)
January 17, 2018
May 24, 2018
US$ 20.00 million
Ministry of Development of Energy and Water Resources (MDEWR),Société des Eaux de Centrafrique (SODECA),Energie Centrafricaine (ENERCA)
2018
US$ 20.00 million
B
Not Applicable
June 30, 2023
Yes
BANK APPROVED
December 11, 2023
Financier | Commitments |
---|---|
IDA Grant | 20.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 20.00 |
IBRD + IDA Commitment | 20.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 20.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 22, 2023 | IDA-D2690 | Loan Disb | 55,360.77 |
Sep 22, 2023 | IDA-D2690 | Loan Disb | 4,286.31 |
Jun 30, 2023 | IDA-D2690 | Loan Disb | 155,234.50 |
Jun 30, 2023 | IDA-D2690 | Loan Disb | 32,584.39 |
Jun 30, 2023 | IDA-D2690 | Loan Disb | 164,093.31 |
Jun 30, 2023 | IDA-D2690 | Loan Disb | 240,063.75 |
Nov 1, 2023 | IDA-D2690 | Loan Disb | -574.15 |
Nov 1, 2023 | IDA-D2690 | Loan Disb | 6,401.63 |
Oct 12, 2023 | IDA-D2690 | Loan Disb | 35,350.35 |
Nov 1, 2023 | IDA-D2690 | Loan Cancel | 2,023,194.00 |
Nov 1, 2023 | IDA-D2690 | Loan Disb | -0.45 |
Oct 23, 2023 | IDA-D2690 | Loan Disb | 230,073.25 |
Oct 23, 2023 | IDA-D2690 | Loan Disb | 279,123.12 |
Oct 26, 2023 | IDA-D2690 | Loan Disb | 52,636.32 |
Sep 27, 2023 | IDA-D2690 | Loan Disb | -52,644.86 |
Jan 26, 2022 | IDA-D2690 | Loan Disb | 172,358.25 |
Sep 1, 2022 | IDA-D2690 | Loan Disb | 58,581.15 |
Jan 3, 2022 | IDA-D2690 | Loan Disb | 87,615.92 |
Jan 3, 2022 | IDA-D2690 | Loan Disb | 3,835.14 |
Jan 27, 2022 | IDA-D2690 | Loan Disb | 53,915.05 |
Nov 23, 2022 | IDA-D2690 | Loan Disb | 141,275.27 |
Dec 30, 2022 | IDA-D2690 | Loan Disb | 248,915.03 |
Nov 21, 2022 | IDA-D2690 | Loan Disb | 250,499.92 |
Nov 28, 2022 | IDA-D2690 | Loan Disb | 34,575.53 |
Oct 18, 2022 | IDA-D2690 | Loan Disb | 462,141.12 |
Nov 17, 2022 | IDA-D2690 | Loan Disb | 474,915.62 |
Dec 16, 2022 | IDA-D2690 | Loan Disb | 242,312.94 |
Oct 24, 2022 | IDA-D2690 | Loan Disb | 673,628.80 |
Apr 17, 2023 | IDA-D2690 | Loan Disb | 4,521.17 |
Apr 13, 2023 | IDA-D2690 | Loan Disb | 143,050.23 |
Aug 10, 2023 | IDA-D2690 | Loan Disb | 251,902.97 |
Jun 21, 2023 | IDA-D2690 | Loan Disb | 160,552.38 |
Jun 21, 2023 | IDA-D2690 | Loan Disb | 505,315.44 |
Aug 30, 2023 | IDA-D2690 | Loan Disb | 151,783.92 |
Sep 20, 2023 | IDA-D2690 | Loan Disb | 53,643.90 |
Aug 30, 2023 | IDA-D2690 | Loan Disb | 54,402.10 |
Apr 1, 2021 | IDA-D2690 | Loan Disb | 254,980.00 |
May 28, 2021 | IDA-D2690 | Loan Disb | 14,961.72 |
Jun 3, 2021 | IDA-D2690 | Loan Disb | 450,306.70 |
May 28, 2021 | IDA-D2690 | Loan Disb | 11,346.99 |
May 28, 2021 | IDA-D2690 | Loan Disb | 35,843.27 |
Jul 20, 2021 | IDA-D2690 | Loan Disb | 1,837.57 |
Jul 20, 2021 | IDA-D2690 | Loan Disb | 114,404.62 |
Sep 27, 2021 | IDA-D2690 | Loan Disb | 67,056.65 |
Sep 16, 2021 | IDA-D2690 | Loan Disb | 34,561.75 |
Sep 16, 2021 | IDA-D2690 | Loan Disb | 379,916.16 |
Apr 28, 2022 | IDA-D2690 | Loan Disb | 241,676.90 |
Apr 28, 2022 | IDA-D2690 | Loan Disb | 241,676.80 |
Apr 12, 2022 | IDA-D2690 | Loan Disb | 83,059.17 |
Apr 12, 2022 | IDA-D2690 | Loan Disb | 125,771.04 |
May 31, 2022 | IDA-D2690 | Loan Disb | 67,369.67 |
May 31, 2022 | IDA-D2690 | Loan Disb | 41,845.50 |
May 6, 2022 | IDA-D2690 | Loan Disb | 254,974.62 |
Jul 12, 2022 | IDA-D2690 | Loan Disb | 365,999.50 |
Jul 21, 2022 | IDA-D2690 | Loan Disb | 278,475.22 |
Jun 22, 2022 | IDA-D2690 | Loan Disb | 69,048.04 |
May 10, 2022 | IDA-D2690 | Loan Disb | 330,635.12 |
May 24, 2018 | IDA-D2690 | Loan Disb | 562,640.70 |
Nov 20, 2018 | IDA-D2690 | Loan Disb | 625,108.56 |
Nov 16, 2018 | IDA-D2690 | Loan Disb | 326,702.16 |
Nov 16, 2018 | IDA-D2690 | Loan Disb | 6,991.87 |
Mar 7, 2019 | IDA-D2690 | Loan Disb | 119,475.01 |
Jun 14, 2019 | IDA-D2690 | Loan Disb | 146,535.94 |
Oct 28, 2019 | IDA-D2690 | Loan Disb | 90,632.02 |
Dec 27, 2019 | IDA-D2690 | Loan Disb | 499,054.25 |
Feb 28, 2020 | IDA-D2690 | Loan Disb | 278,496.20 |
Feb 18, 2020 | IDA-D2690 | Loan Disb | 193,828.17 |
Feb 20, 2020 | IDA-D2690 | Loan Disb | 144,079.95 |
Apr 30, 2020 | IDA-D2690 | Loan Disb | 854,547.25 |
Apr 1, 2020 | IDA-D2690 | Loan Disb | 439,413.38 |
Jun 19, 2020 | IDA-D2690 | Loan Disb | 239,806.81 |
Aug 27, 2020 | IDA-D2690 | Loan Disb | 208,458.44 |
Nov 4, 2020 | IDA-D2690 | Loan Disb | 162,329.98 |
Oct 22, 2020 | IDA-D2690 | Loan Disb | 350,727.47 |
Feb 18, 2021 | IDA-D2690 | Loan Disb | 171,457.55 |
Dec 3, 2020 | IDA-D2690 | Loan Disb | 88,535.50 |
Dec 9, 2020 | IDA-D2690 | Loan Disb | 417,791.78 |
Nov 25, 2020 | IDA-D2690 | Loan Disb | 391,956.25 |
Dec 3, 2020 | IDA-D2690 | Loan Disb | 558,474.94 |
Jun 11, 2021 | IDA-D2690 | Loan Disb | 527,226.94 |
Jan 17, 2018 | IDA-D2690 | Loan Commitment | 20,000,000.00 |
Aug 30, 2023 | IDA-D2690 | Loan Disb | 20,201.02 |
Aug 30, 2023 | IDA-D2690 | Loan Disb | 166,241.45 |
Aug 30, 2023 | IDA-D2690 | Loan Disb | 28,403.56 |
Aug 30, 2023 | IDA-D2690 | Loan Disb | 30,895.24 |
Aug 24, 2023 | IDA-D2690 | Loan Disb | 249,895.77 |
Aug 24, 2023 | IDA-D2690 | Loan Disb | 293,694.94 |
Jun 22, 2023 | IDA-D2690 | Loan Disb | 198,315.48 |
Sep 22, 2023 | IDA-D2690 | Loan Disb | 6,966.59 |
Sep 22, 2023 | IDA-D2690 | Loan Disb | 90,565.54 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Moderately Satisfactory | 2023-06-29 |
Progress towards achievement of PDO | Moderately Satisfactory | 2023-06-29 |
Procurement | Moderately Satisfactory | 2023-06-29 |
Project Management | Moderately Satisfactory | 2023-06-29 |
Financial Management | Moderately Satisfactory | 2023-06-29 |
Monitoring and Evaluation | Moderately Satisfactory | 2023-06-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-11-2023 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-03-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Modest | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with access to improved water sources | Value | 0.00 | 22525.00 | 32000.00 |
Date | January 17, 2018 | August 31, 2023 | June 23, 2022 | |
Comment |
People provided with new or improved electricity service | Value | 0.00 | 25000.00 | 0.00 |
Date | January 17, 2018 | June 30, 2023 | ||
Comment |
People provided with access to improved water sources - Female (RMS requirement) | Value | 0.00 | 12725.00 | 0.00 |
Date | ||||
Comment |
People provided with new or improved electricity service - Female | Value | 0.00 | 19750.00 | 0.00 |
Date | ||||
Comment |
Water production capacity constructed or rehabilitated | Value | 0.00 | 1945.00 | 1800.00 |
Date | January 17, 2018 | August 31, 2023 | June 23, 2022 | |
Comment |
Non-Revenue Water in the project area | Value | 72.00 | 50.00 | 0.00 |
Date | January 17, 2018 | June 30, 2023 | ||
Comment |
Generation capacity of energy constructed or rehabilitated | Value | 0.00 | 2.80 | 0.00 |
Date | January 17, 2018 | June 30, 2023 | ||
Comment |
Energy Bill Collection Ratio | Value | 60.00 | 76.00 | 0.00 |
Date | January 17, 2018 | June 30, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 2625.00 | 2600.00 |
Date | January 17, 2018 | August 31, 2023 | June 23, 2022 | |
Comment |
Prepaid and smart electricity meters installed | Value | 0.00 | 5500.00 | 0.00 |
Date | January 17, 2018 | June 30, 2023 | ||
Comment |
SODECA - Independent Audit and Validated Financial Statements Available | Value | No | Yes | |
Date | January 17, 2018 | June 30, 2023 | ||
Comment |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 47.00 | 100.00 |
Date | January 17, 2018 | June 30, 2023 | June 23, 2022 | |
Comment |
Turbine alternators of Boali 1 hydropower plant refurbished | Value | 0.00 | 4.00 | 0.00 |
Date | January 17, 2018 | June 30, 2023 | ||
Comment |
ENERCA - Independent Audit and Validated Financial Statements Available | Value | No | Yes | |
Date | January 17, 2018 | June 30, 2023 | ||
Comment |
Water quality tests at rehabilitated utility water storage that meet required standards | Value | 0.00 | 0.00 | 0.00 |
Date | January 17, 2018 | June 30, 2023 | ||
Comment |
Least-cost development plan and tariff study available | Value | No | Yes | |
Date | January 17, 2018 | June 30, 2023 | ||
Comment |