Financier | Commitments |
---|---|
Global Financing Facility | 16.00 |
P162477
Closed
Rianna Mohammed-Roberts , Shunsuke Mabuchi
Republic of Liberia
December 21, 2016
(as of board presentation)
February 23, 2017
N/A
US$ 16.00 million
Ministry of Health,MOH Project Implementation Unit
2017
US$ 16.00 million
B
March 27, 2024
November 30, 2021
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Global Financing Facility | 16.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 16.00 |
Total Project Cost** | 16.00 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2021-06-03 |
Monitoring and Evaluation | Moderately Satisfactory | 2021-06-03 |
Progress towards achievement of PDO | Satisfactory | 2021-06-03 |
Financial Management | Moderately Satisfactory | 2021-06-03 |
Procurement | Moderately Satisfactory | 2021-06-03 |
Overall Implementation Progress (IP) | Satisfactory | 2021-06-03 |