Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Borrower/Recipient | 88.60 |
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) | 50.00 |
P162623
Active
Guangming Yan
People's Republic of China
December 18, 2017
(as of board presentation)
May 28, 2019
August 28, 2020
US$ 238.60 million
Foreign Debt Management Office, Shaanxi Provincial Development and Reform Commission
2019
US$ 150.00 million
B
Not Applicable
December 31, 2025
Yes
BANK APPROVED
July 12, 2023
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Borrower/Recipient | 88.60 |
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | 50.00 |
Total Project Cost** | 238.60 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 1, 2021 | IBRD-89640 | Int Charges | 125,932.04 |
Jun 25, 2024 | IBRD-89640 | Loan Disb | 1,954,472.40 |
Feb 28, 2024 | IBRD-89640 | Loan Disb | 7,038,617.00 |
Sep 1, 2021 | IBRD-89640 | Int Charges | 13,790.59 |
May 28, 2019 | IBRD-89640 | Loan Commitment | 100,000,000.00 |
May 4, 2021 | IBRD-89640 | Loan Disb | 8,408,050.00 |
Mar 1, 2022 | IBRD-89640 | Int Charges | 111,511.09 |
Mar 1, 2022 | IBRD-89640 | Int Charges | 24,208.69 |
Dec 15, 2021 | IBRD-89640 | Loan Disb | 4,339,173.50 |
Jul 1, 2022 | IBRD-89640 | Loan Disb | 4,968,622.00 |
Mar 1, 2023 | IBRD-89640 | Int Charges | 2,154.17 |
May 5, 2023 | IBRD-89640 | Loan Disb | 7,006,282.00 |
Jan 20, 2023 | IBRD-89640 | Loan Disb | 3,359,079.00 |
Sep 1, 2022 | IBRD-89640 | Int Charges | 90,552.00 |
Sep 1, 2022 | IBRD-89640 | Int Charges | 39,603.40 |
Oct 21, 2022 | IBRD-89640 | Loan Disb | 5,291,654.00 |
Nov 28, 2023 | IBRD-89640 | Loan Disb | 7,451,752.50 |
Sep 1, 2023 | IBRD-89640 | Int Charges | 994.82 |
Sep 1, 2023 | IBRD-89640 | Int Charges | 7,719.72 |
Sep 1, 2023 | IBRD-89640 | Int Charges | 67,454.46 |
Sep 1, 2023 | IBRD-89640 | Int Charges | 924,723.56 |
Aug 28, 2023 | IBRD-89640 | Loan Disb | 6,389,624.00 |
Feb 27, 2023 | IBRD-89640 | Loan Disb | 5,170,450.50 |
Mar 1, 2023 | IBRD-89640 | Int Charges | 2,126.66 |
Mar 1, 2023 | IBRD-89640 | Int Charges | 82,468.69 |
Mar 1, 2023 | IBRD-89640 | Int Charges | 301,458.00 |
Mar 1, 2024 | IBRD-89640 | Int Charges | 175.17 |
Mar 1, 2024 | IBRD-89640 | Int Charges | 2,815.69 |
Mar 1, 2024 | IBRD-89640 | Int Charges | 49,102.96 |
Mar 1, 2024 | IBRD-89640 | Int Charges | 1,369,076.50 |
Jan 9, 2024 | IBRD-89640 | Loan Disb | 4,974,839.50 |
Oct 23, 2020 | IBRD-89640 | Fee Charges | 263,914.20 |
Mar 1, 2021 | IBRD-89640 | Int Charges | 131,208.02 |
Mar 1, 2021 | IBRD-89640 | Int Charges | 132,792.52 |
Apr 14, 2022 | IBRD-89640 | Loan Disb | 7,070,848.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-04-24 |
Monitoring and Evaluation | Satisfactory | 2025-04-24 |
Overall Implementation Progress (IP) | Satisfactory | 2025-04-24 |
Procurement | Satisfactory | 2025-04-24 |
Financial Management | Satisfactory | 2025-04-24 |
Project Management | Satisfactory | 2025-04-24 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Formal regional collaboration platform by Shaanxi Provincial Government operationalized (Percentage, milestones based on the numberof output level indicators achieved) | Value | 0.00 | 50.00 | 100.00 |
Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
Comment |
People provided with access to improved basic urban services and public amenities within ~500m* radius | Value | 0.00 | 112000.00 | 214000.00 |
Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
Comment |
of which are women | Value | 0.00 | 0.00 | 49.00 |
Date | ||||
Comment |
Population mitigated against flood risk | Value | 0.00 | 185000.00 | 423000.00 |
Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
Comment |
of which are women | Value | 0.00 | 0.00 | 49.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Formal decision announcement signed | Value | No | Yes | Yes |
Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
Comment |
Area of emergency facilities built | Value | 0.00 | 19.00 | 27.30 |
Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
Comment |
Area of old neighborhoods rehabilitated | Value | 0.00 | 185.00 | 356.00 |
Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
Comment |
Regional Flood Risk Management System in operation | Value | No | No | Yes |
Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
Comment |
Length of new evacuation routes constructed | Value | 0.00 | 6.80 | 10.80 |
Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
Comment |
Length of pedestrian and bike lanes newly built or rehabilitated | Value | 0.00 | 80.23 | 91.10 |
Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
Comment |
Regional Water Pollution Monitoring System in operation | Value | No | No | Yes |
Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
Comment |
Length of newly built and upgraded storm and drainage pipelines improved | Value | 0.00 | 62.48 | 89.70 |
Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
Comment |