Financier | Commitments |
---|---|
IDA Grant | 50.00 |
P163467
Closed
Marie Sacadura , Stanislas Honkuy
N/A
March 14, 2018
(as of board presentation)
April 10, 2018
N/A
US$ 50.00 million
N/A
2018
US$ 50.00 million
B
Not Applicable
June 30, 2024
Yes
BANK APPROVED
May 30, 2024
Financier | Commitments |
---|---|
IDA Grant | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 50.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of beneficiaries trained in entrepreneurship | Value | 0.00 | 1201.00 | 2000.00 |
Date | April 30, 2013 | May 19, 2017 | May 31, 2019 | |
Comment |
Youth graduating in the TVET institutions supported by the project in priority sectors (%) of which in the agriculture sector (%) | Value | 0.00 | 0.00 | 65.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target increased to reflect the AF focus in the agriculture sector and the end target date adjusted to reflect revised projectclosing date. |
Direct project beneficiaries | Value | 0.00 | 7736.00 | 31600.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target increased to reflect the additional direct beneficiaries under the AF and the end target date adjusted to reflectrevised project closing date. |
Out of school youth who completed dual apprenticeship programs (of which in the agriculture sector) (%) | Value | 0.00 | 80.00 | 80.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target date adjusted to reflect revised project closing date. |
Short-term vocationally trained youth who are employed or self-employed (overall and by sector) | Value | 0.00 | 50.00 | 50.00 |
Date | April 30, 2013 | June 15, 2016 | November 30, 2022 | |
Comment | End target reduced to 50% as it was reviewed as over ambitious and the end target date adjusted to reflect revised project closingdate. |
Percentage of females | Value | 0.00 | 26.00 | 30.00 |
Date | April 30, 2013 | June 15, 2016 | May 31, 2019 | |
Comment |
Percentage of graduating females | Value | 0.00 | 0.00 | 30.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment |
Female beneficiaries | Value | 0.00 | 43.00 | 50.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment |
Percentage of females | Value | 0.00 | 30.00 | 40.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment |
Percentage of youth who completed dual apprenticeship programs in the agriculture sector | Value | 0.00 | 0.00 | 70.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment |
Youth graduating in the TVET institutions supported by the project in the agriculture sector | Value | 0.00 | 0.00 | 65.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment |
Number of beneficiaries trained in entrepreneurship | Value | 0.00 | 1201.00 | 5000.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target date adjusted to reflect revised project closing date. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Trainers trained in the 4 priority sectors as a result of project intervention | Value | 0.00 | 41.00 | 70.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target increased to reflect activity scale up and end target date adjusted to reflect revised project closing date. |
Youth enrolled in the TVET institutions supported by the project in priority sectors (of which in the agriculture sector) (%) | Value | 0.00 | 0.00 | 8300.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target increased to reflect scale up and end target date adjusted to reflect revised project closing date. |
Labor Market Observatory data collection | Value | No | No | Yes |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target date adjusted to reflect revised project closing date. |
Out of school youth enrolled in dual apprenticeship programs as a result of project intervention (of which in the agriculture sector) (%) (of which females) (%) | Value | 0.00 | 3068.00 | 9000.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target increased to reflect activity scale up and end target date adjusted to reflect revised project closing date. |
Out of school youth completing on-demand technical training as a result of project intervention | Value | 0.00 | 326.00 | 1500.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target date adjusted to reflect revised project closing date. |
Tertiary and secondary technical graduates connected with potential employers as a result of project intervention | Value | 0.00 | 2946.00 | 6500.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target increased to reflect activity scale up and end target date adjusted to reflect revised project closing date. |
Beneficiary surveys completed to support on-going training improvement | Value | No | Yes | Yes |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target date adjusted to reflect revised project closing date. |
Number of trainers in entrepreneurship programs trained as a result of project intervention | Value | 0.00 | 90.00 | 90.00 |
Date | April 30, 2013 | May 19, 2017 | May 31, 2019 | |
Comment | This indicator has already reached its target. |
Percentage female | Value | 0.00 | 0.00 | 30.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment |
Percentage female | Value | 0.00 | 23.00 | 40.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment | End target date adjusted to reflect revised project closing date. |
Youth enrolled in the TVET institutions supported by the project in the agriculture sector | Value | 0.00 | 0.00 | 60.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment |
Out of school youth enrolled in the dual apprenticeship programs in the agriculture sector | Value | 0.00 | 0.00 | 50.00 |
Date | April 30, 2013 | May 19, 2017 | November 30, 2022 | |
Comment |
Trained youth unemployed for more than two years requalified as a result of project intervention | Value | 0.00 | 0.00 | 800.00 |
Date | November 30, 2017 | November 30, 2022 | ||
Comment | End target date added to reflect revised project closing date. |
Number of prizewinner youth in the business plan competition (of which females) | Value | 0.00 | 0.00 | 300.00 |
Date | November 30, 2022 | |||
Comment | New target added to reflect new activity introduced in the AF |
Percentage of females | Value | 0.00 | 0.00 | 40.00 |
Date | November 30, 2022 | |||
Comment |