Dushanbe Water Supply and Wastewater Project

Abstract*

The objectives of the Dushanbe Water Supply and Wastewater Project for Tajikistan are: (a) to improve reliability of water supply and wastewater services in selected areas in Dushanbe City; and (b) to improve the operational performance of the Dushanbe Water Utility. There are three components to the project, the first component being institutional strengthening, capacity building of DVK and water meters provision. The component will finance the next...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objectives are: (a) to improve reliability of water supply and wastewater services in selected areas in Dushanbe City; and (b) to improve the operational performance of the Dushanbe Water Utility.

Key Details

Project Details

  • P163734

  • Active

  • Aleix Serrat Capdevila , Farzona Mukhitdinova

  • Ministry of Finance, Republic of Tajikistan

  • Tajikistan

  • October 9, 2018

  • (as of board presentation)

    June 5, 2019

  • April 10, 2020

  • US$ 32.00 million

  • State Unitary Entity "Obu Korezi Dushanbe"

  • Europe and Central Asia

  • 2019

  • US$ 30.00 million

  • B

  • December 2, 2023

  • July 31, 2025

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Municipalities of Borrowing Country 2.00
IDA Grant 30.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 30.00
IBRD + IDA Commitment 30.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 32.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 12, 2023 IDA-D4780 Loan Disb 770,552.90
Jun 5, 2019 IDA-D4780 Loan Commitment 30,000,000.00
Nov 1, 2023 IDA-D4780 Loan Disb 1,348,437.20
Oct 18, 2023 IDA-D4780 Loan Disb 1,860,771.60
May 22, 2024 IDA-D4780 Loan Disb 1,807,958.00
Aug 30, 2024 IDA-D4780 Loan Disb 1,339,392.60
Jul 27, 2020 IDA-D4780 Loan Disb 1,500,000.00
Jun 21, 2021 IDA-D4780 Loan Disb 502,081.75
Sep 30, 2021 IDA-D4780 Loan Disb 236,165.55
Nov 4, 2021 IDA-D4780 Loan Disb 803,968.60
Jun 21, 2022 IDA-D4780 Loan Disb 746,096.44
May 26, 2022 IDA-D4780 Loan Disb 473,299.62
May 26, 2022 IDA-D4780 Loan Disb 131,985.06
May 26, 2022 IDA-D4780 Loan Disb 724,730.50
Dec 19, 2022 IDA-D4780 Loan Disb 968,428.70
Dec 20, 2021 IDA-D4780 Loan Disb 862,876.80
May 12, 2023 IDA-D4780 Loan Disb 685,968.44
Feb 1, 2023 IDA-D4780 Loan Disb 808,731.20
Oct 24, 2022 IDA-D4780 Loan Disb 272,986.12
Oct 24, 2022 IDA-D4780 Loan Disb 1,206,811.60
Sep 7, 2023 IDA-D4780 Loan Disb 1,179,591.50
Jun 14, 2023 IDA-D4780 Loan Disb 583,824.90
Aug 1, 2023 IDA-D4780 Loan Disb 1,222,650.60
Sep 18, 2023 IDA-D4780 Loan Disb 3,300,000.00
Jan 29, 2024 IDA-D4780 Loan Disb 2,176,763.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-12-08
Procurement Moderately Satisfactory 2024-12-08
Financial Management Moderately Satisfactory 2024-12-08
Monitoring and Evaluation Moderately Satisfactory 2024-12-08
Project Management Moderately Satisfactory 2024-12-08
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-08

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People benefitting from enhanced water supply services in Sino districtValue0.00124860.00150000.00
    DateFebruary 28, 2019October 2, 2023December 20, 2024
    Comment
  • Improved Operating Cost Coverage RatioValue0.590.70The end-target of 0.75 has been adopted.
    DateFebruary 28, 2019October 2, 2023December 20, 2024
    Comment
  • People benefitting from new wastewater services in Sino districtValue014,29341,000
    DateFebruary 28, 2019October 2, 2023December 28, 2024
    Comment
  • Increased metering coverage of DVK's customers in Sino districtValue32.0072.0074.00
    DateFebruary 28, 2019June 11, 2023December 20, 2024
    Comment
  • Sewer pipe breaks expressed in breaks/km/year reduced in Sino districtValue3.401.791.50
    DateFebruary 28, 2019October 2, 2023December 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Wastewater Master Plan developed and endorsed by the DVK (with the inventory of sewarage network and its hydraulic modelling completed)ValueData on the current status of sewerage network in A contract has been signed with Wapcos Limited INDWastewater Master Plan for Dushanbe developed and
    DateFebruary 28, 2019October 2, 2023December 20, 2024
    Comment
  • Water supply pipelines in Sino district rehabilitated/replacedValue0.0062.4462.00
    DateFebruary 1, 2019October 2, 2023December 20, 2024
    Comment
  • Grievances responded and/or resolved within the stipulated service standards for response timesValue90.0094.8095.00
    DateFebruary 28, 2019October 2, 2023December 20, 2024
    Comment
  • Integrated Urban Water Resilience Plan developed and endorsed by Dushanbe CityValueNoNoYes
    DateFebruary 28, 2019October 2, 2023December 20, 2024
    Comment
  • Water storage capacity in Sino district increasedValue42000.0042000.0054000.00
    DateFebruary 28, 2019October 2, 2023December 20, 2024
    Comment
  • Staff of the SUE DVK trained on operation, financial management, communicationValue0.00337.00500.00
    DateFebruary 1, 2019October 2, 2023December 20, 2024
    Comment
  • Booster pumps rehabilitated and energy efficiency and climate-smart systems equipment installedValue0.0036.0021.00
    DateFebruary 28, 2019June 11, 2023December 20, 2024
    Comment
  • Sewage pipelines in Sino district rehabilitated/replacedValue0.0015.9025.00
    DateFebruary 28, 2019October 2, 2023December 20, 2024
    Comment
  • of which female staff of the SUE DVK trainedValue0.000.000.00
    Date
    Comment
  • Inventory and verification of the accounts receivable completedValueNoYesYes
    DateFebruary 28, 2019June 11, 2023December 20, 2024
    Comment
  • Reduced energy consumption of the operated water supply system (as a result of PSs rehabilitation) in Sino districtValue3690.001886.532770.00
    DateFebruary 28, 2019October 2, 2023December 20, 2024
    Comment
  • Call Center services improved and performance assessment implemented on quarterly basisValueNoNoYes
    DateFebruary 28, 2019October 2, 2023December 20, 2024
    Comment
  • Number of trainees/interns accepted for internship in the SUE DVK per yearValue70.00115.0090.00
    DateFebruary 28, 2019October 2, 2023December 20, 2024
    Comment
  • Female trainees accepted for internship program in the SUE DVKValue3.0023.0010.00
    DateFebruary 28, 2019October 2, 2023February 28, 2025
    Comment
  • Share of customers in Sino district reporting satisfaction with improved water or wastewater servicesValue0.0075.0080.00
    DateFebruary 28, 2019October 2, 2023December 20, 2024
    Comment