| Financier | Commitments | 
|---|---|
| Multi-donor Umbrella Facility for Capacity Development | 25.12 | 
| Forced Displacement Trust Fund | 12.00 | 
| Borrower/Recipient | 44.09 | 
| IDA Credit | 180.27 | 
P163829
Closed
Senidu Fanuel
Ministry of Finance
September 14, 2017
(as of board presentation)
June 26, 2018
April 22, 2019
US$ 333.60 million
Ethiopian Investment Commission
2018
US$ 217.39 million
B
Not Applicable
August 31, 2025
BANK APPROVED
June 12, 2024
| Financier | Commitments | 
|---|---|
| Multi-donor Umbrella Facility for Capacity Development | 25.12 | 
| Forced Displacement Trust Fund | 12.00 | 
| Borrower/Recipient | 44.09 | 
| IDA Credit | 180.27 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | N/A | 
| IDA Commitment | 180.27 | 
| IBRD + IDA Commitment | 180.27 | 
| Lending Instrument | |
|---|---|
| Grant Amount | 37.12 | 
| Total Project Cost** | 333.60 | 
| Period | Financier | Transaction Type | Amount (US$) | 
|---|---|---|---|
| Jun 26, 2018 | IDA-62920 | Loan Commitment | 83,330,000.00 | 
| Apr 15, 2020 | IDA-62920 | Int Charges | 22,522.99 | 
| Oct 30, 2023 | IDA-62920 | Int Charges | 1,017.62 | 
| Oct 30, 2023 | IDA-62920 | Int Charges | 1,017.62 | 
| Oct 30, 2023 | IDA-62920 | Int Charges | 151,432.10 | 
| Oct 30, 2023 | IDA-62920 | Int Charges | 151,432.10 | 
| Apr 15, 2024 | IDA-62920 | Int Charges | 2,400.01 | 
| Apr 15, 2024 | IDA-62920 | Int Charges | 2,400.01 | 
| Apr 15, 2024 | IDA-62920 | Int Charges | 149,571.22 | 
| Apr 15, 2024 | IDA-62920 | Int Charges | 149,571.22 | 
| Apr 28, 2023 | IDA-62920 | Int Charges | 137,364.84 | 
| Apr 28, 2023 | IDA-62920 | Int Charges | 137,364.84 | 
| Apr 15, 2023 | IDA-62920 | Int Charges | 4,367.83 | 
| Apr 15, 2023 | IDA-62920 | Int Charges | 4,367.83 | 
| Apr 15, 2022 | IDA-62920 | Int Charges | 830.50 | 
| Apr 15, 2022 | IDA-62920 | Int Charges | 830.50 | 
| Apr 15, 2022 | IDA-62920 | Int Charges | 135,150.20 | 
| Apr 15, 2022 | IDA-62920 | Int Charges | 135,150.20 | 
| Oct 15, 2022 | IDA-62920 | Int Charges | 3,427.38 | 
| Oct 15, 2022 | IDA-62920 | Int Charges | 3,427.38 | 
| Oct 15, 2022 | IDA-62920 | Int Charges | 123,606.71 | 
| Oct 15, 2022 | IDA-62920 | Int Charges | 123,606.71 | 
| Feb 2, 2023 | IDA-62920 | Loan Disb | 5,766,006.00 | 
| Oct 20, 2020 | IDA-62920 | Int Charges | 8,216.42 | 
| Oct 20, 2020 | IDA-62920 | Int Charges | 8,216.42 | 
| Oct 20, 2020 | IDA-62920 | Int Charges | 90,280.47 | 
| Oct 20, 2020 | IDA-62920 | Int Charges | 90,280.47 | 
| Oct 20, 2020 | IDA-62920 | Loan Disb | 373,789.70 | 
| Oct 20, 2020 | IDA-62920 | Loan Disb | 280,342.25 | 
| Oct 20, 2020 | IDA-62920 | Loan Disb | 280,342.25 | 
| Apr 16, 2021 | IDA-62920 | Int Charges | 436.84 | 
| Apr 16, 2021 | IDA-62920 | Int Charges | 436.84 | 
| Apr 16, 2021 | IDA-62920 | Int Charges | 95,062.53 | 
| Apr 16, 2021 | IDA-62920 | Int Charges | 95,062.53 | 
| Apr 23, 2021 | IDA-62920 | Loan Disb | 12,620,417.00 | 
| Oct 15, 2021 | IDA-62920 | Int Charges | 714.55 | 
| Oct 15, 2021 | IDA-62920 | Int Charges | 714.55 | 
| Oct 15, 2021 | IDA-62920 | Int Charges | 137,723.11 | 
| Oct 15, 2021 | IDA-62920 | Int Charges | 137,723.11 | 
| Jun 13, 2019 | IDA-D3460 | Loan Disb | 8,582,722.00 | 
| Apr 22, 2019 | IDA-D3460 | Loan Disb | 886,093.70 | 
| Dec 31, 2019 | IDA-D3460 | Loan Disb | 24,691,812.00 | 
| Oct 13, 2020 | IDA-D3460 | Loan Disb | 527,671.94 | 
| Oct 13, 2020 | IDA-D3460 | Loan Disb | 396,107.60 | 
| Oct 13, 2020 | IDA-D3460 | Loan Disb | 396,107.60 | 
| Oct 13, 2020 | IDA-D3460 | Loan Disb | 563,392.30 | 
| Apr 5, 2021 | IDA-D3460 | Loan Disb | 18,194,428.00 | 
| Feb 27, 2023 | IDA-D3460 | Loan Disb | 7,963,178.00 | 
| Jun 25, 2024 | IDA-D3460 | Loan Disb | 2,096,377.50 | 
| Jun 13, 2019 | IDA-62920 | Loan Disb | 6,090,964.00 | 
| Mar 23, 2020 | IDA-62920 | Loan Disb | 17,072,488.00 | 
| Oct 15, 2019 | IDA-62920 | Int Charges | 15,329.33 | 
| Oct 15, 2019 | IDA-62920 | Int Charges | 15,329.33 | 
| Apr 15, 2020 | IDA-62920 | Int Charges | 40.93 | 
| Apr 15, 2020 | IDA-62920 | Int Charges | 40.93 | 
| Apr 15, 2020 | IDA-62920 | Int Charges | 22,522.99 | 
| Jun 26, 2018 | IDA-D3460 | Loan Commitment | 118,670,000.00 | 
| Name | Review | Date | 
|---|---|---|
| Progress towards achievement of PDO | Satisfactory | 2025-08-27 | 
| Monitoring and Evaluation | Satisfactory | 2025-08-27 | 
| Overall Implementation Progress (IP) | Satisfactory | 2025-08-27 | 
| Monitoring and Evaluation | Satisfactory | 2025-08-27 | 
| Monitoring and Evaluation | Satisfactory | 2025-08-27 | 
| Overall Implementation Progress (IP) | Satisfactory | 2025-08-27 | 
| Overall Implementation Progress (IP) | Satisfactory | 2025-08-27 | 
| Progress towards achievement of PDO | Satisfactory | 2025-08-27 | 
| Progress towards achievement of PDO | Satisfactory | 2025-08-27 | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Percentage of refugee hosting communities with functional ARRA facilitation and support branches | Value | 0.00 | 50.00 | 80.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Number of Refugees with access to Economic Opportunities | Value | 0.00 | 17054.00 | 30000.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Number of Ethiopians with access to economic opportunities | Value | 0.00 | 24607.00 | 30000.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Disclosure of Better work Synthesis compliance reports and MoLSA synthesis inspection reports | Value | No | Yes | Yes | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| A formal domestic MoU is signed between FEAAC and the Office of AG to formalize cooperation on Fraud and corruption | Value | No | Yes | Yes | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Environmental standards and guidelines for IPs developed | Value | 0.00 | 1.00 | 1.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Percentage of refugee hosting communities with functional GRM in place | Value | 0.00 | 50.00 | 80.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Share of factory workers reporting satisfaction with thier workplace condition in the existing IPs | Value | 0.00 | 0.00 | 50.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Promulgation of the new refugees proclamation by the Parliament | Value | No | Yes | Yes | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Private sector investment catalyzed (signed MoUs) in IPs supported by the Program | Value | 3.00 | 38.00 | 31.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Number of project beneficieries reached by jobs focused WBG interventions | Value | 0.00 | 41661.00 | 60000.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| MoLSA, EIC, ARRA and IPDC establish a system for recording, reporting and information sharing for handling maladministration, procurement and corruption complaints | Value | No | Yes | Yes | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Ethiopian Investment Board decision made on feasibility study of private sector led participation in BL I, HIP, MIP and KIP | Value | 0.00 | 1.00 | 5.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Number of Business Licenses issued for refugees | Value | 0.00 | 0.00 | 500.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Number of targeted investment facilitations by EIC | Value | 250.00 | 7193.00 | 1750.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Directives amended to permit establishment of foreign exchange accounts and to permit higher debt-equity ratio for foreign investors | Value | No | Yes | Yes | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| An Investment Promotion strategy adopted by EIC | Value | No | Yes | Yes | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment | 
| Number of new leads for Business to Business matches between local suppliers and international purchasers in competitive export sectors | Value | 5.00 | 31.00 | 50.00 | 
| Date | July 31, 2017 | February 29, 2024 | December 31, 2024 | |
| Comment |