| Financier | Commitments | 
|---|---|
| IDA Credit | 45.70 | 
P163846
Closed
Yitbarek Mammo
N/A
June 6, 2017
(as of board presentation)
June 28, 2017
N/A
US$ 45.70 million
N/A
2017
US$ 45.70 million
B
Not Applicable
June 30, 2020
TBD
BANK APPROVED
October 18, 2023
| Financier | Commitments | 
|---|---|
| IDA Credit | 45.70 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | N/A | 
| IDA Commitment | 45.70 | 
| IBRD + IDA Commitment | 45.70 | 
| Lending Instrument | |
|---|---|
| Grant Amount | N/A | 
| Total Project Cost** | 45.70 | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Number of people in rural areas provided with access to Improved Water Sources under the project | Value | 0.00 | 755000.00 | 800000.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Reliability of water supply services under the project area | Value | 0.00 | 16.00 | 16.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Communities in project area declared free of open defecation (number) | Value | 0.00 | 50.00 | 550.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Water systems in project areas with ratio of revenues over O&M costs (including depreciation) >=1.0(percent) | Value | 1.00 | 0.90 | 0.90 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Percentage of installed water supply system functional | Value | 0.00 | 100.00 | 100.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| People provided with access to "improved sanitation facilities” under the proj. | Value | 0.00 | 343905.00 | 600000.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Direct project beneficiaries | Value | 0.00 | 755000.00 | 800000.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| People provided with access to ?improved sanitation facilities?- rural | Value | 0.00 | 343905.00 | 600000.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Female beneficiaries | Value | 0.00 | 52.00 | 52.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| New water systems for small towns operational (number) | Value | 0.00 | 57.00 | 60.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| New mechanized boreholes operational | Value | 0.00 | 58.00 | 60.00 | 
| Date | June 22, 2010 | June 13, 2016 | December 31, 2019 | |
| Comment | 
| New water systems based on boreholes fitted with hand pumps operational | Value | 0.00 | 998.00 | 1200.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| New community water systems fed from GWCL | Value | 0.00 | 0.00 | 5.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Former GWCL systems transferred to communities rehabilitated | Value | 0.00 | 6.00 | 15.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Orphan boreholes rehabilitated | Value | 0.00 | 400.00 | 300.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| New Institutional toilet facilities constructed and operational | Value | 0.00 | 437.00 | 400.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Communities sensitized about hygiene practices and eradication of open free defecation | Value | 0.00 | 1489.00 | 600.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Subproject implementation in accordance with timetable in procurement plan (percent for each participating DA) | Value | 0.00 | 0.80 | 0.95 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Acceptable implementation (including safeguards) quarterly reports delivered on time (percent for each participating DA) | Value | 0.00 | 0.80 | 1.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Timely submittal of clean (unqualified) FM audit reports (percent for each participating DA) | Value | 0.00 | 0.70 | 1.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| District Assemblies operating DiMES | Value | 0.00 | 64.00 | 94.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Key institutions (CWSA, MOFEP, MWRWH, MLGRD) trained in the use Sector Information Systems | Value | 0.00 | 4.00 | 4.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
| Comment | 
| Improved latrines constructed under the project | Value | 0.00 | 22927.00 | 40000.00 | 
| Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |