| Financier | Commitments | 
|---|---|
| IDA Grant | 38.49 | 
P163922
Closed
Anita Shrestha , Toufiq Ahmed, Sean David Michaels
Micronesia, Federated States of
February 12, 2018
(as of board presentation)
May 9, 2019
August 14, 2019
US$ 38.49 million
Department of Justice,Department of Environment, Climate Change and Emergency Management,Department of Transportation, Communication & Infrastructure
2019
US$ 38.49 million
B
Not Applicable
August 1, 2024
Yes
Bank Approved
April 29, 2024
| Financier | Commitments | 
|---|---|
| IDA Grant | 38.49 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | N/A | 
| IDA Commitment | 38.49 | 
| IBRD + IDA Commitment | 38.49 | 
| Lending Instrument | |
|---|---|
| Grant Amount | N/A | 
| Total Project Cost** | 38.49 | 
| Period | Financier | Transaction Type | Amount (US$) | 
|---|---|---|---|
| Apr 30, 2020 | IDA-D4500 | Loan Disb | 701,993.90 | 
| Dec 9, 2019 | IDA-D4500 | Loan Disb | 3,000,000.00 | 
| Aug 25, 2020 | IDA-D4500 | Loan Disb | 157,964.61 | 
| Jul 23, 2024 | IDA-D4500 | Loan Cancel | 1,504,436.60 | 
| Jul 23, 2024 | IDA-D6450 | Loan Cancel | 2,518,469.00 | 
| Apr 25, 2024 | IDA-D4500 | Loan Disb | 349,714.16 | 
| Feb 28, 2024 | IDA-D4500 | Loan Cancel | 24,999,920.00 | 
| Jun 5, 2020 | IDA-D6450 | Loan Commitment | 2,500,000.00 | 
| May 9, 2019 | IDA-D4500 | Loan Commitment | 38,490,000.00 | 
| Dec 4, 2023 | IDA-D4500 | Loan Disb | 338,510.28 | 
| Sep 8, 2023 | IDA-D4500 | Loan Disb | 366,793.62 | 
| Jun 12, 2023 | IDA-D4500 | Loan Disb | 214,666.48 | 
| Feb 27, 2023 | IDA-D4500 | Loan Disb | 232,668.56 | 
| Aug 12, 2022 | IDA-D4500 | Loan Disb | 117,855.89 | 
| Feb 7, 2022 | IDA-D4500 | Loan Disb | 379,081.56 | 
| Oct 26, 2022 | IDA-D4500 | Loan Disb | 186,172.78 | 
| May 23, 2022 | IDA-D4500 | Loan Disb | 421,760.10 | 
| Jun 4, 2021 | IDA-D4500 | Loan Disb | 163,181.95 | 
| Oct 18, 2021 | IDA-D4500 | Loan Disb | 221,647.78 | 
| Oct 18, 2021 | IDA-D4500 | Loan Disb | 269,855.38 | 
| Jun 4, 2021 | IDA-D4500 | Loan Disb | 187,304.60 | 
| Jul 30, 2020 | IDA-D4500 | Loan Disb | 178,128.62 | 
| Jun 25, 2020 | IDA-D4500 | Loan Disb | 2,500,000.00 | 
| Apr 28, 2020 | IDA-D4500 | Loan Disb | 74,834.07 | 
| May 5, 2020 | IDA-D4500 | Loan Disb | 150,266.75 | 
| Nov 25, 2020 | IDA-D4500 | Loan Disb | 237,845.72 | 
| Name | Review | Date | 
|---|---|---|
| Monitoring and Evaluation | Unsatisfactory | 2024-04-18 | 
| Financial Management | Moderately Unsatisfactory | 2024-04-18 | 
| Progress towards achievement of PDO | Unsatisfactory | 2024-04-18 | 
| Project Management | Unsatisfactory | 2024-04-18 | 
| Procurement | Unsatisfactory | 2024-04-18 | 
| Overall Implementation Progress (IP) | Unsatisfactory | 2024-04-18 | 
| INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-01-2025 | 
|---|---|
| Outcomes | |
| Risk to Development Outcome | |
| Bank Performance | |
| Borrower Performance | |
| Government Performance | |
| Implementing Agency | 
| INDICATOR | ICR REVIEW: 07-07-2025 | PROJECT PERFORMANCE ASSESSMENT REPORT: | 
|---|---|---|
| Outcome Rating | Highly Unsatisfactory | N/a | 
| Risk To Development Outcome | N/a | |
| Bank Performance | Moderately Unsatisfactory | N/a | 
| Borrower Performance | N/a | |
| Government Performance | N/a | |
| Implementing Agency | N/a | |
| Icr Quality | Substantial | N/a | 
| M&e Quality | Modest | N/a | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Reduction in cargo vessel turnaround times at project port(s) | Value | 1620.00 | 1620.00 | 1600.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| Project ports rehabilitated with at least one climate resilience measure | Value | 0.00 | 0.00 | 2.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| Ports with sectoral and contingency planning tools that address natural disasters and climate change | Value | 0.00 | 0.00 | 4.00 | 
| Date | February 25, 2024 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| Project ports fully compliant with ISPS requirements | Value | 0.00 | 0.00 | 4.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| Increase in container yard productivity at project port(s) | Value | 0.00 | 0.00 | 10.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Grievances registered related to delivery of project benefits that are addressed | Value | 0.00 | 0.00 | 100.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| Area of cargo yard hardened at Pohnpei and Chuuk Ports | Value | 0.00 | 0.00 | 11379.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| ISPS recommendations implemented against identified shortcomings | Value | 0.00 | 0.00 | 50.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| Adoption of a CERC manual given the risk of natural disaster | Value | No | Yes | Yes | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| Number of project ports with drainage measures implemented | Value | 0.00 | 0.00 | 2.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| Project ports with safety solutions implemented | Value | 0.00 | 0.00 | 3.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| CERC-related procurement packages completed on time as per the procurement plan | Value | 0.00 | 100.00 | 100.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| Energy efficiency recommendations implemented | Value | 0.00 | 0.00 | 2.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| People with enhanced access to transportation services | Value | 0.00 | 0.00 | 0.00 | 
| Date | February 25, 2019 | March 6, 2024 | ||
| Comment | 
| FSMIP implementation of SOP on trafficking referral service | Value | No | No | Yes | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| Women employed by FSMIP on Sea Ports | Value | 0.00 | 0.00 | 15.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| Percentage of contractor staff trained on GBV & Codes of Conduct | Value | 0.00 | 0.00 | 100.00 | 
| Date | February 25, 2019 | March 6, 2024 | August 1, 2023 | |
| Comment | 
| People with enhanced access to transportation services – IWT/ Ferries | Value | 0.00 | 0.00 | 0.00 | 
| Date | February 25, 2019 | March 6, 2024 | ||
| Comment |