Second DPL to reform the Indonesian maritime logistics sector

Abstract*

The development objective of Second Logistics Reform Development Policy Loan Project for Indonesia is to reduce the costs and improve the reliability of the logistics chain in Indonesia. It comprises of three pillars with the following PDOs: 1) Pillar A: Enhancing ports’ performance; 2) Pillar B: Improving logistics services; and 3) Pillar C: Strengthening trade processing. This second operation in the DPL series builds on the first operation to support...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Project Development Objective (Note: will be disclosed in the MOS)To reduce the costs and improve the reliability of the logistics chain in Indonesia by enabling reforms to make trade processing more efficient and transparent, to improve the business environment for logistics service providers and to increase the efficiency of ports operations.Board Schedule Comments

Key Details

Project Details

  • P163973

  • Closed

  • Massimiliano Cali

  • Ministry of Finance

  • Indonesia

  • January 31, 2018

  • (as of board presentation)

    June 28, 2018

  • July 9, 2018

  • US$ 300.00 million

  • Coordinating Ministry of Economic Affairs

  • East Asia and Pacific

  • 2018

  • US$ 300.00 million

  • N/A

  • Not Applicable

  • November 30, 2018

  • BANK APPROVED

  • P158140

  • August 20, 2020

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 300.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 300.00
IDA Commitment N/A
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 300.00

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 15, 2024 IBRD-88420 Int Charges 62,076.82
Jul 15, 2024 IBRD-88420 Int Charges 9,875,920.00
Jul 15, 2024 IBRD-88420 Loan Repay 9,990,000.00
Jan 15, 2024 IBRD-88420 Int Charges 10,311,517.00
Jan 15, 2024 IBRD-88420 Loan Repay 9,990,000.00
Jun 28, 2018 IBRD-88420 Loan Commitment 300,000,000.00
Jul 15, 2023 IBRD-88420 Int Charges 9,547,750.00
Jul 15, 2023 IBRD-88420 Loan Repay 9,990,000.00
Jan 15, 2023 IBRD-88420 Int Charges 6,532,000.00
Jul 15, 2022 IBRD-88420 Int Charges 2,413,333.20
Jan 15, 2022 IBRD-88420 Int Charges 2,070,000.00
Jul 15, 2021 IBRD-88420 Int Charges 2,187,083.20
Jan 15, 2021 IBRD-88420 Int Charges 2,361,333.20
Jan 15, 2020 IBRD-88420 Int Charges 5,228,666.50
Jul 15, 2019 IBRD-88420 Int Charges 6,123,833.50
Jan 15, 2019 IBRD-88420 Int Charges 5,332,000.00
Jul 26, 2018 IBRD-88420 Fee Charges 750,000.00
Jul 27, 2018 IBRD-88420 Loan Disb 300,000,000.00
Jul 15, 2020 IBRD-88420 Int Charges 4,656,166.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-09-2020
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceSubstantial
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-08-2020PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeModestN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • B3: Number of approved logistics bonded centers.Value0.0043.0030.00
    DateDecember 31, 2015July 3, 2017June 29, 2018
    Comment
  • C5: Share of shipments classified as red channel in Tanjung PriokValue6.004.784.00
    DateDecember 31, 2015February 28, 2017June 29, 2018
    Comment
  • C1: Pre-clearance time in Tanjung Priok PortValue3.601.892.00
    DateJune 30, 2015April 29, 2016June 29, 2018
    Comment
  • C3-1: Dwell time in Tanjung PriokValue5.503.344.00
    DateJune 30, 2015June 30, 2016June 29, 2018
    Comment
  • C3-2: Dwell time in Tanjung PerakValue6.305.544.00
    DateJune 30, 2015June 30, 2016June 29, 2018
    Comment
  • C2: Share of trade regulations included in the INTRValue90.000.00100.00
    DateDecember 31, 2015June 29, 2018
    Comment
  • A2: Number of approved applications for BOT sea-ports developmentValue0.003.002.00
    DateDecember 31, 2015June 1, 2017June 29, 2018
    Comment
  • A1: Number of Pelindos’ ports and terminals with internationally certified management systems (Quality Management Systems – ISO 9000 series)Value46.000.0060.00
    DateDecember 31, 2014June 29, 2018
    Comment
  • B1-1: New foreign licenses for freight forwardersValue1.000.005.00
    DateDecember 31, 2015June 29, 2018
    Comment
  • B1- 2: New foreign licenses for warehousing and cold storageValue7.000.0015.00
    DateDecember 31, 2015June 29, 2018
    Comment
  • B2-1: New shipping agents’ licenses (SUKK)Value0.007.005.00
    DateDecember 31, 2015March 27, 2017June 29, 2018
    Comment
  • B2-2: New foreign maritime cargo handling licensesValue1.000.003.00
    DateDecember 31, 2015June 29, 2018
    Comment
  • A3 - 1: Minimum and maximum ships’ waiting time in Tanjung Priok portValuemin. 1 hour – max. 24 hoursmin. 0.8 hours – max. 12 hours
    DateDecember 31, 2014June 29, 2018
    Comment
  • C4- Pre-clearance time for food and drugs in Tanjung PriokValuemin. 3 - max 6 daysmin. 2 – max. 4 days
    DateDecember 31, 2015December 29, 2017
    Comment