Financier | Commitments |
---|---|
IDA Credit | 40.00 |
P164242
Closed
Tahirou Kalam
Republic of Mali
January 12, 2018
(as of board presentation)
June 21, 2019
October 22, 2019
US$ 40.00 million
Ministere des Mines et du Pétrole
2019
US$ 40.00 million
B
Not Applicable
June 30, 2024
Yes
BANK APPROVED
June 22, 2024
Financier | Commitments |
---|---|
IDA Credit | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 40.00 |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 40.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 28, 2022 | IDA-64470 | Loan Disb | 158,515.06 |
Jul 28, 2022 | IDA-64470 | Loan Disb | 101,210.92 |
Jan 7, 2022 | IDA-64470 | Loan Disb | 134,109.12 |
Aug 21, 2024 | IDA-64470 | Loan Disb | 299,205.12 |
Feb 12, 2024 | IDA-64470 | Loan Disb | 448,489.10 |
May 24, 2024 | IDA-64470 | Loan Disb | 456,599.62 |
Feb 12, 2024 | IDA-64470 | Loan Cancel | 5,000,000.00 |
Dec 28, 2023 | IDA-64470 | Int Charges | 334.10 |
Dec 28, 2023 | IDA-64470 | Int Charges | 334.10 |
Dec 28, 2023 | IDA-64470 | Int Charges | 38,654.21 |
Dec 28, 2023 | IDA-64470 | Int Charges | 38,654.21 |
Dec 11, 2023 | IDA-64470 | Loan Disb | 337,439.30 |
Nov 13, 2023 | IDA-64470 | Loan Disb | 207,005.11 |
Jan 18, 2024 | IDA-64470 | Loan Disb | 177,834.90 |
Dec 21, 2023 | IDA-64470 | Loan Disb | 421,847.80 |
Oct 13, 2023 | IDA-64470 | Loan Disb | 466,743.56 |
Aug 8, 2023 | IDA-64470 | Loan Disb | 712,316.00 |
Jun 5, 2023 | IDA-64470 | Int Charges | 899.31 |
Jun 5, 2023 | IDA-64470 | Int Charges | 899.31 |
Jun 5, 2023 | IDA-64470 | Int Charges | 29,367.49 |
Jun 5, 2023 | IDA-64470 | Int Charges | 29,367.49 |
Jun 28, 2023 | IDA-64470 | Loan Disb | 360,824.94 |
Jun 8, 2023 | IDA-64470 | Loan Disb | 540,952.56 |
Apr 14, 2023 | IDA-64470 | Loan Cancel | 14,707,805.00 |
May 12, 2023 | IDA-64470 | Loan Disb | 284,313.78 |
Sep 8, 2023 | IDA-64470 | Loan Disb | 548,210.40 |
Dec 13, 2022 | IDA-64470 | Loan Disb | 229,289.30 |
Feb 14, 2023 | IDA-64470 | Loan Disb | 167,848.00 |
Apr 12, 2023 | IDA-64470 | Loan Disb | 217,699.62 |
Jan 23, 2023 | IDA-64470 | Loan Disb | 152,231.77 |
Mar 27, 2023 | IDA-64470 | Loan Disb | 97,386.03 |
Nov 17, 2022 | IDA-64470 | Int Charges | 39.73 |
Nov 17, 2022 | IDA-64470 | Int Charges | 39.73 |
Nov 17, 2022 | IDA-64470 | Int Charges | 21,802.70 |
Nov 17, 2022 | IDA-64470 | Int Charges | 21,802.70 |
Nov 17, 2022 | IDA-64470 | Loan Disb | 336,600.44 |
Sep 16, 2022 | IDA-64470 | Loan Disb | 543,197.44 |
Aug 3, 2022 | IDA-64470 | Loan Disb | 91,144.96 |
Aug 11, 2022 | IDA-64470 | Loan Disb | 93,901.37 |
Aug 29, 2022 | IDA-64470 | Loan Disb | 130,062.34 |
Dec 17, 2021 | IDA-64470 | Loan Disb | 197,022.60 |
Jul 28, 2022 | IDA-64470 | Loan Disb | 119,684.35 |
Apr 23, 2021 | IDA-64470 | Loan Disb | 149,521.10 |
May 25, 2021 | IDA-64470 | Int Charges | 13,561.84 |
May 25, 2021 | IDA-64470 | Int Charges | 13,561.84 |
Nov 16, 2021 | IDA-64470 | Int Charges | 15,085.40 |
Nov 16, 2021 | IDA-64470 | Loan Disb | 153,660.20 |
May 11, 2021 | IDA-64470 | Loan Disb | 270,866.22 |
Dec 18, 2020 | IDA-64470 | Loan Disb | 75,005.48 |
Feb 19, 2021 | IDA-64470 | Loan Disb | 212,790.66 |
Dec 14, 2020 | IDA-64470 | Loan Disb | 543,074.80 |
Nov 20, 2020 | IDA-64470 | Int Charges | 57.64 |
Nov 20, 2020 | IDA-64470 | Int Charges | 57.64 |
Nov 20, 2020 | IDA-64470 | Int Charges | 9,798.06 |
Nov 20, 2020 | IDA-64470 | Int Charges | 9,798.06 |
Jan 22, 2021 | IDA-64470 | Loan Disb | 238,142.08 |
Jun 25, 2020 | IDA-64470 | Loan Disb | 351,030.47 |
Aug 19, 2020 | IDA-64470 | Loan Disb | 109,115.40 |
Mar 4, 2020 | IDA-64470 | Loan Disb | 1,274,626.20 |
May 5, 2020 | IDA-64470 | Loan Disb | 252,533.95 |
May 19, 2020 | IDA-64470 | Loan Disb | 179,889.38 |
May 20, 2020 | IDA-64470 | Int Charges | 197.58 |
May 20, 2020 | IDA-64470 | Int Charges | 197.58 |
May 20, 2020 | IDA-64470 | Int Charges | 3,398.88 |
May 20, 2020 | IDA-64470 | Int Charges | 3,398.88 |
Oct 22, 2019 | IDA-64470 | Loan Disb | 419,426.90 |
Apr 2, 2024 | IDA-64470 | Loan Disb | 344,615.38 |
Jul 12, 2024 | IDA-64470 | Loan Disb | 645,604.90 |
Jun 21, 2019 | IDA-64470 | Loan Commitment | 40,000,000.00 |
Feb 26, 2024 | IDA-64470 | Loan Disb | 230,824.52 |
May 21, 2024 | IDA-64470 | Loan Disb | 147,018.98 |
Jun 13, 2024 | IDA-64470 | Loan Disb | 410,026.94 |
May 10, 2024 | IDA-64470 | Loan Disb | 508,185.84 |
Jun 27, 2024 | IDA-64470 | Loan Disb | 636,281.30 |
Mar 11, 2024 | IDA-64470 | Loan Disb | 345,751.25 |
Jul 25, 2024 | IDA-64470 | Loan Disb | 412,676.40 |
Jun 10, 2024 | IDA-64470 | Int Charges | 47,386.82 |
Jun 10, 2024 | IDA-64470 | Int Charges | 401.74 |
Jun 10, 2024 | IDA-64470 | Int Charges | 401.74 |
Jun 10, 2024 | IDA-64470 | Int Charges | 47,386.82 |
Jul 25, 2024 | IDA-64470 | Loan Disb | 273,880.06 |
Aug 29, 2024 | IDA-64470 | Loan Disb | 430,770.62 |
Feb 4, 2022 | IDA-64470 | Loan Disb | 702,008.60 |
Oct 11, 2022 | IDA-64470 | Loan Disb | 178,379.94 |
Jul 12, 2022 | IDA-64470 | Int Charges | 747.29 |
Jul 12, 2022 | IDA-64470 | Int Charges | 747.29 |
Jul 12, 2022 | IDA-64470 | Int Charges | 18,450.54 |
Jul 12, 2022 | IDA-64470 | Int Charges | 18,450.54 |
Oct 14, 2021 | IDA-64470 | Loan Disb | 116,561.68 |
Nov 16, 2021 | IDA-64470 | Int Charges | 85.72 |
Nov 16, 2021 | IDA-64470 | Int Charges | 85.72 |
Nov 16, 2021 | IDA-64470 | Int Charges | 15,085.40 |
Sep 20, 2021 | IDA-64470 | Loan Disb | 96,190.23 |
Sep 20, 2021 | IDA-64470 | Loan Disb | 142,742.97 |
Sep 20, 2021 | IDA-64470 | Loan Disb | 153,467.17 |
Sep 20, 2021 | IDA-64470 | Loan Disb | 273,048.38 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2024-06-28 |
Monitoring and Evaluation | Satisfactory | 2024-06-28 |
Procurement | Satisfactory | 2024-06-28 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-06-28 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2024-06-28 |
Project Management | Satisfactory | 2024-06-28 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Mining policy and regulatory framework attractiveness for sustainable investments (Fraser Institute Index) | Value | 50.40 | 38.04 | 60.00 |
Date | March 11, 2019 | June 22, 2024 | September 14, 2022 | |
Comment |
Satisfactory institutional effectiveness rating | Value | No | Yes | Yes |
Date | March 11, 2019 | June 22, 2024 | September 14, 2022 | |
Comment |
Resource Governance Index | Value | 53.00 | 63.00 | 75.00 |
Date | February 14, 2019 | June 22, 2024 | September 16, 2024 | |
Comment |
Proportion of women in mining supported by the project | Value | 0.00 | 32.00 | 30.00 |
Date | February 13, 2019 | June 22, 2024 | September 16, 2024 | |
Comment |
Number of artisanal mining cooperatives established and supported by the project | Value | 0.00 | 402.00 | 200.00 |
Date | March 11, 2019 | June 22, 2024 | June 30, 2022 | |
Comment |
Share of high-potential sheets covered by satellite imagery interpretation survey (Percentage) | Value | 25.00 | 30.00 | 40.00 |
Date | December 31, 2022 | June 24, 2024 | June 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of mining localities with completed strategic development plans that integrate mining EI revenues | Value | 0.00 | 11.00 | 6.00 |
Date | June 29, 2018 | June 22, 2024 | December 31, 2021 | |
Comment |
Number of registered and active ASM cooperatives, SMEs or associations as a result of the project formalization initiatives | Value | 100.00 | 402.00 | 400.00 |
Date | June 29, 2018 | June 22, 2024 | December 31, 2021 | |
Comment |
Establishment of an online platform for EI revenue data integration and monitoring at local and central levels | Value | No | Yes | Yes |
Date | June 12, 2019 | June 22, 2024 | December 31, 2023 | |
Comment |
Regulatory capacity (average processing time of mining title application) | Value | 180.00 | 113.00 | 30.00 |
Date | February 13, 2019 | June 22, 2024 | September 16, 2024 | |
Comment |
Representation of women in community-based management committees | Value | 10.00 | 30.00 | 30.00 |
Date | January 23, 2019 | June 22, 2024 | December 31, 2021 | |
Comment |
Number of women supported through associations to establish and operate value-added industries | Value | 0.00 | 6423.00 | 500.00 |
Date | June 12, 2019 | June 22, 2024 | December 31, 2021 | |
Comment |
Average number of annual health, safety, environmnetal and social compliance inspections for each active mining operation | Value | 1.00 | 10.00 | 4.00 |
Date | June 29, 2018 | June 22, 2024 | December 31, 2021 | |
Comment |
Annual publication of compliant EITI reports incorporating ASM revenue and disaggregated local revenue | Value | No | Yes | Yes |
Date | February 14, 2019 | June 22, 2024 | September 16, 2024 | |
Comment |
Number of mining companies signing on to multi-stakeholder initiatives for power and mining integration | Value | 0.00 | 2.00 | 3.00 |
Date | June 12, 2018 | June 22, 2024 | September 16, 2024 | |
Comment |
Establishment and operationalization of Inter-Ministerial Mine Coordination Unit | Value | No | Yes | Yes |
Date | June 29, 2018 | June 22, 2024 | September 16, 2024 | |
Comment |
Consultation and debates on the governance and transparency diligently documented and publicly disclosed | Value | 0.00 | 39.00 | 5.00 |
Date | May 28, 2019 | June 22, 2024 | June 28, 2024 | |
Comment |
Number of women supported to participate in alternative livelihood activities | Value | 0.00 | 3501.00 | 300.00 |
Date | June 12, 2018 | June 22, 2024 | September 16, 2024 | |
Comment |
Geological attractiveness for investment (available number of area maps surveyed at scale of 1:100 000 using satellite imagery for mining investment promotion) (Number) | Value | 80.00 | 81.00 | 110.00 |
Date | December 31, 2022 | June 22, 2024 | June 30, 2024 | |
Comment |
Feedback received from public consultations and debates have been incorporated in the upcoming Mali EITI report, as well as the mining sector beneficial ownership road map | Value | No | Yes | Yes |
Date | May 28, 2019 | September 22, 2023 | June 28, 2024 | |
Comment |