Financier | Commitments |
---|---|
IDA Grant | 40.00 |
P164543
Closed
Oceane Keou , Theophile Bougna Lonla
Republic of Guinea
February 8, 2018
(as of board presentation)
December 10, 2018
August 21, 2019
US$ 40.00 million
Ministere de l'Agriculture
2019
US$ 40.00 million
B
Not Applicable
June 28, 2024
No
BANK APPROVED
June 14, 2024
Financier | Commitments |
---|---|
IDA Grant | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 40.00 |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 40.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 18, 2023 | IDA-D4120 | Loan Disb | 118,359.41 |
Dec 14, 2022 | IDA-D4120 | Loan Disb | 109,812.85 |
Mar 30, 2023 | IDA-D4120 | Loan Disb | 296,181.60 |
Jul 9, 2024 | IDA-D4120 | Loan Disb | -117,000.00 |
May 7, 2024 | IDA-D4120 | Loan Disb | 946,825.70 |
Jun 5, 2024 | IDA-D4120 | Loan Disb | 680,621.30 |
Dec 29, 2023 | IDA-D4120 | Loan Disb | 134,174.73 |
Oct 11, 2023 | IDA-D4120 | Loan Disb | 1,138,718.40 |
Nov 16, 2023 | IDA-D4120 | Loan Disb | 672,718.80 |
Jun 27, 2023 | IDA-D4120 | Loan Disb | 107,382.06 |
Jun 13, 2023 | IDA-D4120 | Loan Disb | 225,194.67 |
Jun 13, 2023 | IDA-D4120 | Loan Disb | 292,492.16 |
Dec 8, 2023 | IDA-D4120 | Loan Disb | 263,185.70 |
Dec 10, 2018 | IDA-D4120 | Loan Commitment | 40,000,000.00 |
Jun 24, 2024 | IDA-D4120 | Loan Disb | 1,053,045.20 |
Apr 8, 2024 | IDA-D4120 | Loan Disb | 174,963.28 |
Feb 13, 2024 | IDA-D4120 | Loan Disb | 551,339.94 |
Mar 21, 2024 | IDA-D4120 | Loan Disb | 137,992.67 |
Nov 20, 2020 | IDA-D4120 | Loan Disb | 27,829.91 |
May 20, 2024 | IDA-D4120 | Loan Disb | 924,310.50 |
May 11, 2020 | IDA-D4120 | Loan Disb | 174,089.80 |
Jun 12, 2020 | IDA-D4120 | Loan Disb | 218,563.33 |
Aug 31, 2020 | IDA-D4120 | Loan Disb | 42,914.46 |
Aug 21, 2019 | IDA-D4120 | Loan Disb | 416,174.20 |
Feb 21, 2020 | IDA-D4120 | Loan Disb | 2,300,000.00 |
May 6, 2021 | IDA-D4120 | Loan Disb | 48,384.58 |
Jun 25, 2021 | IDA-D4120 | Loan Disb | 148,413.39 |
Aug 11, 2021 | IDA-D4120 | Loan Disb | 115,636.41 |
Jan 14, 2021 | IDA-D4120 | Loan Disb | 42,169.44 |
Dec 28, 2020 | IDA-D4120 | Loan Disb | 453,515.34 |
Apr 8, 2021 | IDA-D4120 | Loan Disb | 96,659.06 |
Jun 4, 2021 | IDA-D4120 | Loan Disb | 158,689.36 |
Oct 14, 2020 | IDA-D4120 | Loan Disb | 43,635.46 |
Feb 24, 2021 | IDA-D4120 | Loan Disb | 42,897.18 |
Apr 17, 2024 | IDA-D4120 | Loan Cancel | 21,830,660.00 |
Jul 29, 2020 | IDA-D4120 | Loan Disb | 61,241.78 |
Oct 27, 2022 | IDA-D4120 | Loan Disb | 1,658,721.40 |
Sep 13, 2023 | IDA-D4120 | Loan Disb | 571,347.10 |
Aug 24, 2023 | IDA-D4120 | Loan Disb | 1,733,250.60 |
Aug 9, 2023 | IDA-D4120 | Loan Disb | 128,030.53 |
Feb 27, 2023 | IDA-D4120 | Loan Disb | 378,602.78 |
Name | Review | Date |
---|---|---|
Project Management | Unsatisfactory | 2023-12-21 |
Progress towards achievement of PDO | Unsatisfactory | 2023-12-21 |
Procurement | Moderately Satisfactory | 2023-12-21 |
Overall Implementation Progress (IP) | Unsatisfactory | 2023-12-21 |
Financial Management | Moderately Unsatisfactory | 2023-12-21 |
Monitoring and Evaluation | Moderately Satisfactory | 2023-12-21 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-13-2025 |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-26-2025 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Unsatisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with an all season road | Value | 0.00 | 15281.00 | 0.00 |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
Number of markets reached by an improved road | Value | 0.00 | 1.00 | 0.00 |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
Number of accessible schools and health centers | Value | 0.00 | 9.00 | 0.00 |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
Proportion of project roads under communities routine maintenance | Value | 0.00 | 0.00 | 0.00 |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehablitated | Value | 0.00 | 43.00 | 0.00 |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
Number of person-days worked for routine maintenance | Value | 0.00 | 0.00 | 0.00 |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
Decree of creation of the Road Safety Observatory | Value | No | Yes | |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
Grievances addressed within the stipulated timeframe | Value | 0.00 | 100.00 | 0.00 |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
Percentage of villages covered by information and awareness sessions on violence against women | Value | 0.00 | 100.00 | 0.00 |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
Share of women employed in routine maintenance | Value | 0.00 | 0.00 | 0.00 |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
GBV risk monitoring | Value | No | Yes | |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
Roads rehabilitated - rural | Value | 0.00 | 26.00 | 0.00 |
Date | ||||
Comment |
Number of women represented in decision commitee of each community maintenance group | Value | 0.00 | 0.00 | 0.00 |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |
Roads rehabilitated - non-rural | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Share of civil works costs dedicated to small common facilities | Value | 0.00 | 13.00 | 0.00 |
Date | November 1, 2018 | December 8, 2023 | ||
Comment |