Skip to Main Navigation

Mozambique Land Administration Project (Terra Segura)

Abstract*

The objective of the Land Administration Project is to strengthen land tenure security in selected districts and improve the efficiency and accessibility of land administration services. There are four components to the project, the first component being institutional development and strengthening of the legal framework. The objective of this component is to improve the efficiency of existing land administration institutions and the standards or practices...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to a) strengthen land tenure security in selected districts and improve the efficiency and accessibility of land administration services, and b) provide immediate and effective response to the emergency in Northern Mozambique.

Key Details

Project Details

  • P164551

  • Closed

  • Camille Bourguignon-Roger

  • Ministry of Economy and Finance

  • Mozambique

  • September 16, 2018

  • (as of board presentation)

    December 4, 2018

  • October 2, 2019

  • US$ 100.00 million

  • National Fund for Social Development,Ministry of Land and Environment

  • Eastern and Southern Africa

  • 2019

  • US$ 100.00 million

  • B

  • March 7, 2024

  • March 29, 2024

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 100.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 6, 2023 IDA-D4010 Loan Disb 55,276.86
Jan 25, 2023 IDA-D4010 Loan Disb 208,495.52
Feb 15, 2023 IDA-D4010 Loan Disb 1,240,744.90
Feb 15, 2023 IDA-D4010 Loan Disb 424,429.78
Oct 4, 2022 IDA-D4010 Loan Disb 252,729.36
Nov 18, 2022 IDA-D4010 Loan Disb 226,805.38
Nov 18, 2022 IDA-D4010 Loan Disb 174,461.44
Oct 17, 2022 IDA-D4010 Loan Disb 428,821.56
Oct 17, 2022 IDA-D4010 Loan Disb 471,588.62
Nov 9, 2022 IDA-D4010 Loan Disb 1,503,821.20
Nov 9, 2022 IDA-D4010 Loan Disb 428,821.56
Sep 23, 2022 IDA-D4010 Loan Disb 116,644.77
Oct 20, 2022 IDA-D4010 Loan Disb 133,500.77
Sep 16, 2022 IDA-D4010 Loan Disb 151,986.00
Apr 8, 2022 IDA-D4010 Loan Disb -428,756.56
Aug 4, 2022 IDA-D4010 Loan Disb 92,128.10
Aug 25, 2022 IDA-D4010 Loan Disb 1,665,383.00
Feb 9, 2022 IDA-D4010 Loan Disb 2,775,000.00
Apr 6, 2022 IDA-D4010 Loan Disb 428,821.56
Apr 6, 2022 IDA-D4010 Loan Disb 695,423.30
Jun 9, 2022 IDA-D4010 Loan Disb 347,656.62
Apr 27, 2022 IDA-D4010 Loan Disb 230,320.31
May 13, 2022 IDA-D4010 Loan Disb 1,225,935.10
Mar 3, 2022 IDA-D4010 Loan Disb 1,019,633.70
Nov 22, 2021 IDA-D4010 Loan Disb 5,550,000.00
Apr 22, 2022 IDA-D4010 Loan Disb 471,588.62
May 31, 2022 IDA-D4010 Loan Disb 200,500.00
Sep 3, 2021 IDA-D4010 Loan Disb 4,251,909.50
Sep 24, 2021 IDA-D4010 Loan Disb 925,000.00
Nov 12, 2021 IDA-D4010 Loan Disb 735,770.75
Aug 7, 2020 IDA-D4010 Loan Disb -352,295.28
Nov 18, 2020 IDA-D4010 Loan Disb 357,749.38
Aug 26, 2020 IDA-D4010 Loan Disb 917,276.00
Aug 7, 2020 IDA-D4010 Loan Disb 352,295.28
Apr 1, 2020 IDA-D4010 Loan Disb 958,535.25
Jun 15, 2020 IDA-D4010 Loan Disb 463,617.50
Oct 2, 2019 IDA-D4010 Loan Disb 1,753,155.10
Jul 25, 2024 IDA-D4010 Loan Disb 212,653.12
Jul 25, 2024 IDA-D4010 Loan Disb 215,387.38
Mar 18, 2024 IDA-D4010 Loan Disb 187,831.27
Jul 25, 2024 IDA-D4010 Loan Disb 157,001.86
Mar 18, 2024 IDA-D4010 Loan Disb 554,213.70
Jul 25, 2024 IDA-D4010 Loan Disb 128,646.45
Apr 5, 2024 IDA-D4010 Loan Disb 347,326.94
Jul 5, 2024 IDA-D4010 Loan Disb 248,701.22
Feb 13, 2024 IDA-D4010 Loan Disb -193,482.00
Aug 9, 2024 IDA-D4010 Loan Disb 231,061.44
Aug 9, 2024 IDA-D4010 Loan Disb 179,183.61
Jul 8, 2024 IDA-D4010 Loan Disb 282,827.78
Jul 5, 2024 IDA-D4010 Loan Disb 208,436.36
Jul 5, 2024 IDA-D4010 Loan Disb 174,460.14
Jul 5, 2024 IDA-D4010 Loan Disb 374,040.34
Jul 23, 2024 IDA-D4010 Loan Disb 210,614.66
Nov 16, 2023 IDA-D4010 Loan Disb 78,599.99
Jan 5, 2024 IDA-D4010 Loan Disb 764,119.25
Nov 27, 2023 IDA-D4010 Loan Disb 316,693.50
Jan 18, 2024 IDA-D4010 Loan Disb 610,615.06
Jan 18, 2024 IDA-D4010 Loan Disb 195,056.31
Dec 12, 2023 IDA-D4010 Loan Disb 174,460.16
Dec 12, 2023 IDA-D4010 Loan Disb 187,020.17
Jan 18, 2024 IDA-D4010 Loan Disb 149,708.58
Nov 6, 2023 IDA-D4010 Loan Disb 2,427,588.50
Nov 27, 2023 IDA-D4010 Loan Disb 1,228,081.60
Nov 27, 2023 IDA-D4010 Loan Disb 149,708.60
Nov 27, 2023 IDA-D4010 Loan Disb 147,374.39
Jul 25, 2024 IDA-D4010 Loan Disb 317,501.50
Jul 25, 2024 IDA-D4010 Loan Disb 141,476.69
Jun 6, 2023 IDA-D4010 Loan Disb 77,538.42
Jun 30, 2023 IDA-D4010 Loan Disb 407,121.84
Jun 30, 2023 IDA-D4010 Loan Disb 411,302.03
Jun 30, 2023 IDA-D4010 Loan Disb 341,087.16
Jun 30, 2023 IDA-D4010 Loan Disb 385,367.25
Jun 30, 2023 IDA-D4010 Loan Disb 363,835.60
May 23, 2023 IDA-D4010 Loan Disb 424,430.10
Jul 19, 2023 IDA-D4010 Loan Disb 306,732.44
Jul 19, 2023 IDA-D4010 Loan Disb 237,520.12
May 23, 2023 IDA-D4010 Loan Disb 385,939.80
May 18, 2023 IDA-D4010 Loan Disb 20,742.08
May 18, 2023 IDA-D4010 Loan Disb 38,769.20
Dec 19, 2023 IDA-D4010 Loan Disb 147,374.39
Dec 29, 2023 IDA-D4010 Loan Disb 202,681.81
Dec 29, 2023 IDA-D4010 Loan Disb 207,447.38
Dec 18, 2023 IDA-D4010 Loan Disb 329,016.30
Jul 24, 2023 IDA-D4010 Loan Disb 257,999.98
Jul 24, 2023 IDA-D4010 Loan Disb 232,977.80
Jul 24, 2023 IDA-D4010 Loan Disb 200,095.00
Jul 24, 2023 IDA-D4010 Loan Disb 258,758.22
Jul 24, 2023 IDA-D4010 Loan Disb 233,113.20
Jul 24, 2023 IDA-D4010 Loan Disb 342,000.03
Jun 9, 2023 IDA-D4010 Loan Disb 56,859.24
Jul 24, 2023 IDA-D4010 Loan Disb 260,999.98
Jul 24, 2023 IDA-D4010 Loan Disb 349,200.12
Jun 20, 2023 IDA-D4010 Loan Disb 385,939.80
Jul 24, 2023 IDA-D4010 Loan Disb 341,958.22
Jul 24, 2023 IDA-D4010 Loan Disb 181,715.02
Aug 30, 2023 IDA-D4010 Loan Disb 55,276.85
Jul 20, 2023 IDA-D4010 Loan Disb 3,751,660.00
Jul 20, 2023 IDA-D4010 Loan Disb 305,625.16
Aug 2, 2023 IDA-D4010 Loan Disb 424,430.10
Aug 2, 2023 IDA-D4010 Loan Disb 385,939.80
Feb 15, 2023 IDA-D4010 Loan Disb 385,939.40
May 16, 2023 IDA-D4010 Loan Disb 385,939.40
May 16, 2023 IDA-D4010 Loan Disb 424,429.78
May 16, 2023 IDA-D4010 Loan Disb 155,076.83
May 16, 2023 IDA-D4010 Loan Disb 55,276.86
Feb 23, 2023 IDA-D4010 Loan Disb 33,369.92
May 16, 2023 IDA-D4010 Loan Disb 1,557,945.50
May 16, 2023 IDA-D4010 Loan Disb 50,662.01
May 16, 2023 IDA-D4010 Loan Disb 82,968.32
Jan 11, 2023 IDA-D4010 Loan Disb 100,125.58
Jun 20, 2023 IDA-D4010 Loan Disb 424,430.12
Sep 15, 2022 IDA-D4010 Loan Disb 99,449.99
Sep 15, 2022 IDA-D4010 Loan Disb 464,493.62
Jun 6, 2024 IDA-D4010 Loan Disb 120,212.97
Feb 6, 2024 IDA-D4010 Loan Disb 630,164.94
Jun 6, 2024 IDA-D4010 Loan Disb 266,622.90
Feb 6, 2024 IDA-D4010 Loan Disb 614,304.60
Apr 2, 2024 IDA-D4010 Loan Disb 147,374.39
Jun 6, 2024 IDA-D4010 Loan Disb 277,637.12
Apr 2, 2024 IDA-D4010 Loan Disb 149,708.60
Dec 4, 2018 IDA-D4010 Loan Commitment 100,000,000.00
Mar 1, 2024 IDA-D4010 Loan Disb 174,461.44
May 28, 2024 IDA-D4010 Loan Disb 108,907.55
May 28, 2024 IDA-D4010 Loan Disb 149,708.60
May 28, 2024 IDA-D4010 Loan Disb 333,189.12
May 28, 2024 IDA-D4010 Loan Disb 207,447.38
Jun 3, 2024 IDA-D4010 Loan Disb 116,123.40
Mar 6, 2024 IDA-D4010 Loan Disb 1,273,290.20
Jun 3, 2024 IDA-D4010 Loan Disb 350,269.38
Jun 3, 2024 IDA-D4010 Loan Disb 950,544.00
Jul 22, 2024 IDA-D4010 Loan Disb 174,460.14
Aug 1, 2024 IDA-D4010 Loan Disb 301,436.70
Mar 6, 2024 IDA-D4010 Loan Disb 184,256.19
Mar 6, 2024 IDA-D4010 Loan Disb 1,157,818.00
Jul 22, 2024 IDA-D4010 Loan Disb 187,020.17
Jul 30, 2024 IDA-D4010 Loan Disb 92,128.11
Jul 22, 2024 IDA-D4010 Loan Disb 249,891.84
Jul 22, 2024 IDA-D4010 Loan Disb 99,028.75
Feb 12, 2024 IDA-D4010 Loan Cancel 23,382,676.00
Apr 2, 2024 IDA-D4010 Loan Disb 147,374.39
Apr 2, 2024 IDA-D4010 Loan Disb 79,172.61
Feb 9, 2024 IDA-D4010 Loan Disb 261,692.17
Feb 2, 2024 IDA-D4010 Loan Disb 193,539.02
Mar 21, 2024 IDA-D4010 Loan Disb 227,365.02
Jun 18, 2024 IDA-D4010 Loan Disb 207,447.38
Aug 2, 2024 IDA-D4010 Loan Disb 918,099.94
Mar 1, 2024 IDA-D4010 Loan Disb 694,653.90
Jun 11, 2024 IDA-D4010 Loan Disb 409,721.34
Jun 11, 2024 IDA-D4010 Loan Disb 189,195.27
Mar 1, 2024 IDA-D4010 Loan Disb 1,065,985.20
Feb 20, 2024 IDA-D4010 Loan Disb 261,692.16
Feb 20, 2024 IDA-D4010 Loan Disb 174,460.14
Aug 2, 2024 IDA-D4010 Loan Disb 425,306.28
Aug 2, 2024 IDA-D4010 Loan Disb 215,387.38
Aug 2, 2024 IDA-D4010 Loan Disb 425,104.25
May 28, 2024 IDA-D4010 Loan Disb 208,600.03
Jun 11, 2024 IDA-D4010 Loan Disb 440,219.47
Jul 25, 2024 IDA-D4010 Loan Disb 212,552.12

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Satisfactory 2024-02-08
Project Management Satisfactory 2024-02-08
Monitoring and Evaluation Satisfactory 2024-02-08
Overall Implementation Progress (IP) Moderately Satisfactory 2024-02-08
Progress towards achievement of PDO Moderately Satisfactory 2024-02-08
Procurement Moderately Satisfactory 2024-02-08

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-21-2025PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Community delimitation certificates recorded in SiGIT in the name of the community, including an approved micro-zoning planValue0374 local communities have their land delimited an
    DateOctober 31, 2018September 15, 2023
    Comment
  • Satisfaction of DUAT beneficiaries with respect to land tenure regularization (LTR)Value-FNDS launched the first customer satisfaction surv
    DateOctober 31, 2018September 15, 2023
    Comment
  • Farmers reached with agricultural assets or servicesValue0.0030000.000.00
    DateDecember 14, 2020December 8, 2022
    Comment
  • Beneficiaries who received a DUAT recorded in SiGITValue0280,599 members of local communities have received
    DateOctober 31, 2018September 15, 2023
    Comment
  • Satisfaction of women who are DUAT beneficiaries with respect to land tenure regularization (LTR)Value-FNDS launched the first customer satisfaction surv
    DateOctober 31, 2018September 15, 2023
    Comment
  • Farmers reached with agricultural assets or services - FemaleValue0.000.000.00
    Date
    Comment
  • Women who received a DUAT recorded in SiGIT in their name or jointlyValue039% of the project beneficiaries who receive DUAT
    DateOctober 31, 2018September 15, 2023
    Comment
  • Reduction of cost to record a DUAT in SiGIT under a systematic regularization processValue50.0038.500.00
    DateOctober 31, 2018September 15, 2023
    Comment
  • SiGIT is deployed and operational on the centralized ICT infrastructure at the renovated DNDT Data CenterValue0%40% calculated as follows: SiGIT technical review
    DateDecember 28, 2018September 15, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • The final draft of land policy reform is submitted to the Council of MinistersValueThe 1995 land policy needs to be updated.The Council of Ministers approved the National Lan
    DateOctober 31, 2018September 15, 2023
    Comment
  • Household survey completedValue-The World Bank’s Gender Innovation Lab (GIL) compl
    DateOctober 31, 2018September 15, 2023
    Comment
  • DUATs regularized and recorded in SIGITValue0364,899 DUATs regularized and recorded in SIGIT.
    DateOctober 31, 2018September 15, 2023
    Comment
  • Final draft proposal and business plan for the creation of an autonomous Land Administration entity is submitted to the Council of MinistersValueNo proposal and business plan for the creation of The proposal for the establishment of the new Land
    DateOctober 31, 2018September 15, 2023
    Comment
  • Community awareness and communication campaign is implementedValue-Community awareness and communication campaign is
    DateOctober 31, 2018September 15, 2023
    Comment
  • End users who received training to use SiGITValue-86
    DateOctober 31, 2018September 15, 2023
    Comment
  • Quality Assurance and Quality Control procedures for land regularization are developed and implementedValueNo Quality Assurance and Quality Control procedureQuality Assurance and Quality Control procedures f
    DateOctober 31, 2018September 15, 2023
    Comment
  • Civil society actors and local government officials trained in legal and safeguard aspects related to land tenure regularization process (gender disaggregated)Value-483
    DateOctober 31, 2018September 15, 2023
    Comment
  • Women part of civil society actors and local government officials trained in legal and safeguard aspects related to land tenure regularization processValue-23% of the civil society actors and local governme
    DateOctober 31, 2018September 15, 2023
    Comment
  • Identified land conflicts addressed within the established conflict resolution mechanism at DINAT and Project levelValue-89% of the land conflicts identified are addressed
    DateOctober 31, 2018September 15, 2023
    Comment
  • Women participating in the consultation processValue-51% of the individuals participating in the consul
    DateOctober 31, 2018September 15, 2023
    Comment
  • Number of administrative territorial bounders up to the locality level, in the selected districts delimitedValue0.0067.000.00
    DateDecember 31, 2019September 15, 2023
    Comment