Financier | Commitments |
---|---|
IDA Credit | 25.00 |
P164584
Closed
Lorenzo Bertolini , Mampionona Amboarasoa
Union of the Comoros
February 9, 2018
(as of board presentation)
May 20, 2019
May 26, 2020
US$ 25.00 million
Ministry of Agriculture, Environment, Fisheries (MEAPE)
2019
US$ 25.00 million
B
Not Applicable
July 31, 2024
TBD
BANK APPROVED
April 2, 2024
Financier | Commitments |
---|---|
IDA Credit | 25.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 25.00 |
IBRD + IDA Commitment | 25.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 25.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 20, 2019 | IDA-64230 | Loan Commitment | 25,000,000.00 |
Aug 15, 2024 | IDA-64230 | Int Charges | 25,659.09 |
Aug 15, 2024 | IDA-64230 | Int Charges | 25,659.09 |
Aug 23, 2024 | IDA-64230 | Int Charges | 1,086.83 |
Aug 23, 2024 | IDA-64230 | Int Charges | 1,086.83 |
Aug 23, 2024 | IDA-64230 | Int Charges | 41,516.25 |
Aug 23, 2024 | IDA-64230 | Int Charges | 41,516.25 |
Aug 15, 2024 | IDA-64230 | Int Charges | 21,398.71 |
Aug 15, 2024 | IDA-64230 | Int Charges | 21,398.71 |
Feb 15, 2024 | IDA-64230 | Int Charges | 44,366.48 |
Feb 15, 2024 | IDA-64230 | Int Charges | 44,366.48 |
Feb 15, 2024 | IDA-64230 | Int Charges | 169.12 |
Feb 15, 2024 | IDA-64230 | Int Charges | 169.12 |
Feb 15, 2024 | IDA-64230 | Int Charges | 33,188.18 |
Feb 15, 2024 | IDA-64230 | Int Charges | 33,188.18 |
May 20, 2024 | IDA-64230 | Loan Disb | 544,301.90 |
Mar 18, 2024 | IDA-64230 | Loan Disb | 1,081,777.90 |
Apr 12, 2024 | IDA-64230 | Loan Disb | 378,672.60 |
Oct 2, 2023 | IDA-64230 | Loan Disb | 422,636.70 |
Nov 10, 2023 | IDA-64230 | Loan Disb | 472,440.72 |
Dec 20, 2023 | IDA-64230 | Loan Disb | 333,716.80 |
Jun 27, 2023 | IDA-64230 | Loan Disb | 449,539.38 |
Jun 27, 2023 | IDA-64230 | Loan Disb | 204,784.45 |
Jun 7, 2023 | IDA-64230 | Loan Disb | 704,469.80 |
Jun 23, 2023 | IDA-64230 | Loan Disb | 134,158.73 |
May 22, 2023 | IDA-64230 | Loan Disb | 2,655,935.00 |
Apr 14, 2021 | IDA-64230 | Loan Disb | 150,518.97 |
May 17, 2021 | IDA-64230 | Loan Disb | 113,881.36 |
Jul 26, 2021 | IDA-64230 | Loan Disb | 129,846.54 |
Jun 18, 2021 | IDA-64230 | Loan Disb | 63,886.36 |
Sep 18, 2020 | IDA-64230 | Loan Disb | 75,425.03 |
Mar 1, 2021 | IDA-64230 | Loan Disb | 43,767.95 |
Feb 15, 2021 | IDA-64230 | Int Charges | 784.14 |
Feb 15, 2021 | IDA-64230 | Int Charges | 784.14 |
Feb 15, 2021 | IDA-64230 | Int Charges | 2,678.71 |
Feb 15, 2021 | IDA-64230 | Int Charges | 2,678.71 |
Feb 8, 2021 | IDA-64230 | Loan Disb | 56,876.41 |
May 26, 2020 | IDA-64230 | Loan Disb | 451,337.38 |
Sep 29, 2020 | IDA-64230 | Loan Disb | 163,541.78 |
Nov 6, 2020 | IDA-64230 | Loan Disb | 94,416.94 |
Aug 18, 2022 | IDA-64230 | Int Charges | 31,387.51 |
Feb 16, 2022 | IDA-64230 | Int Charges | 240.25 |
Feb 16, 2022 | IDA-64230 | Int Charges | 240.25 |
Feb 16, 2022 | IDA-64230 | Int Charges | 11,935.72 |
Aug 29, 2022 | IDA-64230 | Loan Disb | 75,683.62 |
Dec 23, 2021 | IDA-64230 | Loan Disb | 133,936.55 |
Feb 18, 2022 | IDA-64230 | Loan Disb | 3,464,550.00 |
May 13, 2022 | IDA-64230 | Loan Disb | 359,648.62 |
Feb 16, 2022 | IDA-64230 | Int Charges | 11,935.72 |
Mar 4, 2022 | IDA-64230 | Loan Disb | 1,121,301.10 |
Jun 8, 2022 | IDA-64230 | Loan Disb | 893,889.94 |
Sep 17, 2021 | IDA-64230 | Loan Disb | 164,935.40 |
Aug 31, 2021 | IDA-64230 | Loan Disb | 43,410.43 |
Mar 16, 2022 | IDA-64230 | Loan Disb | 317,867.16 |
Jun 24, 2022 | IDA-64230 | Loan Disb | 569,705.90 |
Dec 14, 2021 | IDA-64230 | Loan Disb | 210,340.80 |
Apr 22, 2022 | IDA-64230 | Loan Disb | 540,601.90 |
Jun 27, 2022 | IDA-64230 | Loan Disb | 91,308.40 |
May 26, 2021 | IDA-64230 | Loan Disb | 1,492,656.00 |
Aug 15, 2021 | IDA-64230 | Int Charges | 6,494.05 |
Aug 15, 2021 | IDA-64230 | Int Charges | 6,494.05 |
Oct 27, 2021 | IDA-64230 | Loan Disb | 88,629.15 |
Aug 15, 2021 | IDA-64230 | Int Charges | 22.26 |
Aug 15, 2021 | IDA-64230 | Int Charges | 22.26 |
Mar 18, 2021 | IDA-64230 | Loan Disb | 78,585.62 |
Aug 15, 2023 | IDA-64230 | Int Charges | 752.98 |
Aug 15, 2023 | IDA-64230 | Int Charges | 752.98 |
Aug 15, 2023 | IDA-64230 | Int Charges | 61,305.58 |
Aug 15, 2023 | IDA-64230 | Int Charges | 61,305.58 |
Aug 21, 2023 | IDA-64230 | Loan Disb | 444,683.12 |
May 15, 2023 | IDA-64230 | Loan Disb | 878,944.25 |
Sep 11, 2023 | IDA-64230 | Loan Disb | 251,997.23 |
Sep 26, 2022 | IDA-64230 | Loan Disb | 107,862.25 |
Feb 6, 2023 | IDA-64230 | Loan Disb | 1,122,519.00 |
Apr 14, 2023 | IDA-64230 | Loan Disb | 1,244,808.40 |
Mar 22, 2023 | IDA-64230 | Loan Disb | 538,199.50 |
Mar 20, 2023 | IDA-64230 | Int Charges | 28,210.45 |
Mar 20, 2023 | IDA-64230 | Int Charges | 28,210.45 |
Feb 15, 2023 | IDA-64230 | Int Charges | 13,077.29 |
Feb 15, 2023 | IDA-64230 | Int Charges | 13,077.29 |
Feb 15, 2023 | IDA-64230 | Int Charges | 1,303.45 |
Feb 15, 2023 | IDA-64230 | Int Charges | 1,303.45 |
Dec 23, 2022 | IDA-64230 | Loan Disb | 219,326.16 |
Oct 14, 2022 | IDA-64230 | Loan Disb | 308,296.16 |
Nov 14, 2022 | IDA-64230 | Loan Disb | 252,307.55 |
Jan 9, 2023 | IDA-64230 | Loan Disb | 470,802.62 |
Aug 18, 2022 | IDA-64230 | Int Charges | 71.46 |
Aug 18, 2022 | IDA-64230 | Int Charges | 71.46 |
Aug 18, 2022 | IDA-64230 | Int Charges | 31,387.51 |
Feb 5, 2024 | IDA-64230 | Loan Disb | 323,108.25 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-06-25 |
Financial Management | Moderately Satisfactory | 2024-06-25 |
Project Management | Moderately Satisfactory | 2024-06-25 |
Overall Safeguards Rating | Moderately Satisfactory | 2024-06-25 |
Progress towards achievement of PDO | Satisfactory | 2024-06-25 |
Overall Implementation Progress (IP) | Satisfactory | 2024-06-25 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-06-25 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-31-2025 |
---|---|
Outcomes | Satisfactory |
Risk to Development Outcome | |
Bank Performance | Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 05-07-2025 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increased revenue among beneficiary start-ups, MSMEs and Value Chain actors | Value | 0.00 | 15.00 | 30.00 |
Date | March 1, 2019 | December 15, 2023 | June 30, 2024 | |
Comment |
Increase in volume of sold raw and processed agriculture products by project beneficiaries (% disaggregated by farmers and cooperatives for selected indicative crops and livestock products) | Value | 0.00 | 6.06 | 25.00 |
Date | March 1, 2019 | December 15, 2023 | June 30, 2024 | |
Comment |
Number of jobs created by beneficiary start-ups, MSMEs and Value Chain actors (# disaggregated by female and youth) | Value | 0.00 | 1508.00 | 1600.00 |
Date | March 1, 2019 | December 15, 2023 | May 31, 2024 | |
Comment |
Value of private finance catalyzed | Value | 0.00 | 4623548.00 | 2000000.00 |
Date | March 1, 2019 | December 15, 2023 | May 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Agriculture investment plan adopted by government (Y/N) | Value | No | Yes | Yes |
Date | March 1, 2019 | December 15, 2023 | June 30, 2024 | |
Comment |
Number of established firms/cooperatives that receive matching grants, with breakdown for women-owned companies | Value | 0.00 | 189.00 | 150.00 |
Date | March 1, 2019 | December 15, 2023 | June 30, 2024 | |
Comment |
Agriculture Data Unit Established and Operational | Value | No | Yes | Yes |
Date | March 1, 2019 | December 15, 2023 | May 30, 2024 | |
Comment |
Percentage of women-owned companies that received matching grants | Value | 0.00 | 0.00 | 10.00 |
Date | ||||
Comment |
Number of tourism investment promotion campaigns conducted | Value | 0.00 | 4.00 | 4.00 |
Date | March 1, 2019 | December 15, 2023 | May 30, 2024 | |
Comment |
Number of young entrepreneurs who receive cash grants or technical assistance | Value | 0.00 | 100.00 | 100.00 |
Date | March 1, 2019 | December 15, 2023 | June 30, 2024 | |
Comment |
Number of multi-service platforms for export crops and livestock established or upgraded | Value | 0.00 | 9.00 | 7.00 |
Date | March 1, 2019 | December 15, 2023 | June 30, 2024 | |
Comment |
Number of beneficiaries in the business development services capacity building program | Value | 0.00 | 250.00 | 100.00 |
Date | March 1, 2019 | December 15, 2023 | June 30, 2024 | |
Comment |
Number of Trained livestock and crop technicians | Value | 0.00 | 123.00 | 100.00 |
Date | March 1, 2019 | December 15, 2023 | May 30, 2024 | |
Comment |
Satisfaction rating by project beneficiaries administered through a survey questionnaire (%) (Citizen Engagement) | Value | 0.00 | 98.00 | 75.00 |
Date | March 1, 2019 | December 15, 2023 | May 30, 2024 | |
Comment |
Number of farmers benefitting from enhanced services and assets | Value | 0.00 | 1196.00 | 9000.00 |
Date | March 1, 2019 | December 15, 2023 | May 30, 2024 | |
Comment |
Percentage of complaints responded and/or resolved within the stipulated standard for response times. (Citizen engagement) | Value | 0.00 | 100.00 | 100.00 |
Date | March 1, 2019 | December 15, 2023 | May 30, 2024 | |
Comment |
Increase in yield per hectare, selected indicative crops (disaggregated by gender). | Value | 0.00 | 5.41 | 25.00 |
Date | March 1, 2019 | December 15, 2023 | June 30, 2024 | |
Comment |
Cooperatives established, registered, or received training (number, disaggregated) | Value | 0.00 | 43.00 | 30.00 |
Date | March 1, 2019 | December 15, 2023 | May 30, 2024 | |
Comment |
Increase in volume of chilled milk collected and transported to market (%) | Value | 0.00 | 8.00 | 25.00 |
Date | March 1, 2019 | December 15, 2023 | May 30, 2024 | |
Comment |
Operational cold-storage, dry storage and warehouse facilities (number, disaggregated) | Value | 0.00 | 8.00 | 10.00 |
Date | March 1, 2019 | December 15, 2023 | May 30, 2024 | |
Comment |
Feeder roads/agriculture paths and drainage rehabilitated (km) | Value | 0.00 | 17.31 | 30.00 |
Date | March 1, 2019 | December 15, 2023 | June 30, 2024 | |
Comment |