Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 126.89 |
Borrower/Recipient | 80.20 |
P165683
Active
Luis Alvestegui Justiniano , Paula Pedreira de Freitas de Oliveir
State Secretariat for Infrastructure, Water Resources and Environment
March 27, 2018
(as of board presentation)
February 28, 2019
January 19, 2021
US$ 207.09 million
AESA - State Water Resources Management Executive Agency,CAGEPA - State Water and Sanitation Company
2019
US$ 126.89 million
B
March 5, 2024
June 30, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 126.89 |
Borrower/Recipient | 80.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 126.89 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 126.89 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 207.09 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 24, 2021 | IBRD-89310 | Loan Disb | 1,893,258.10 |
Jan 19, 2021 | IBRD-89310 | Loan Disb | 317,215.00 |
Jan 19, 2021 | IBRD-89310 | Fee Charges | 317,215.00 |
Nov 15, 2022 | IBRD-89310 | Int Charges | 154,657.12 |
Nov 15, 2022 | IBRD-89310 | Int Charges | 73,092.09 |
May 15, 2022 | IBRD-89310 | Int Charges | 140,560.17 |
May 15, 2022 | IBRD-89310 | Int Charges | 14,003.33 |
May 15, 2022 | IBRD-89310 | Int Charges | 14,003.33 |
May 20, 2022 | IBRD-89310 | Loan Disb | 2,013,166.10 |
May 15, 2021 | IBRD-89310 | Int Charges | 1,287.91 |
May 15, 2023 | IBRD-89310 | Int Charges | 115,562.52 |
Feb 28, 2019 | IBRD-89310 | Loan Commitment | 126,886,000.00 |
May 15, 2021 | IBRD-89310 | Int Charges | 91,025.49 |
Jan 25, 2024 | IBRD-89310 | Loan Disb | 8,487,077.00 |
Nov 15, 2023 | IBRD-89310 | Int Charges | 137,698.66 |
Nov 15, 2023 | IBRD-89310 | Int Charges | 135,168.31 |
Nov 15, 2023 | IBRD-89310 | Int Charges | 2,530.34 |
Nov 15, 2023 | IBRD-89310 | Int Charges | 16,478.98 |
Nov 15, 2023 | IBRD-89310 | Int Charges | 2,530.34 |
Oct 31, 2023 | IBRD-89310 | Loan Disb | 3,995,844.20 |
May 15, 2023 | IBRD-89310 | Int Charges | 5,922.62 |
May 15, 2023 | IBRD-89310 | Int Charges | 152,067.70 |
Jun 17, 2024 | IBRD-89310 | Loan Disb | 9,278,504.00 |
May 15, 2024 | IBRD-89310 | Int Charges | 11,190.84 |
May 15, 2024 | IBRD-89310 | Int Charges | 141,192.10 |
May 15, 2024 | IBRD-89310 | Int Charges | 318,407.25 |
May 15, 2024 | IBRD-89310 | Int Charges | 410.54 |
May 15, 2024 | IBRD-89310 | Int Charges | 140,781.55 |
Nov 15, 2021 | IBRD-89310 | Int Charges | 157,242.05 |
Nov 15, 2021 | IBRD-89310 | Int Charges | 13,206.07 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-12-19 |
Project Management | Satisfactory | 2024-12-19 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-19 |
Financial Management | Moderately Satisfactory | 2024-12-19 |
Monitoring and Evaluation | Satisfactory | 2024-12-19 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-19 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of days with piped water in the benefitted cities of the Agreste and Borborema regions | Value | 98.00 | 98.00 | 328.00 |
Date | November 30, 2017 | October 6, 2023 | December 31, 2024 | |
Comment |
Non-Revenue Water reduced in the JPMR | Value | 0.00 | 4082662.00 | 17000000.00 |
Date | December 31, 2018 | October 6, 2023 | January 30, 2026 | |
Comment |
Annual operation water management plan for the Paraiba river issued | Value | No | Yes | Yes |
Date | December 31, 2018 | October 6, 2023 | December 31, 2021 | |
Comment |
Number of beneficiaries with reliable water services | Value | 0.00 | 0.00 | 235000.00 |
Date | December 31, 2018 | October 6, 2023 | December 31, 2024 | |
Comment |
Volume of pollution loads (BOD) discharges reduced in water bodies in the JPMR | Value | 3200.00 | 3200.00 | 9600.00 |
Date | December 31, 2018 | October 6, 2023 | December 31, 2024 | |
Comment |
Hydromet stations operational and feeding into the water information system | Value | 10.00 | 83.00 | 83.00 |
Date | December 31, 2018 | October 6, 2023 | December 31, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Establishment and Functioning of Non-Revenue Water Management Program in CAGEPA | Value | No | Yes | Yes |
Date | December 31, 2018 | October 6, 2023 | December 30, 2022 | |
Comment |
Operation, Management and Emergency Preparedness Plans elaborated for existing dams in the Paraíba river basin | Value | 0.00 | 3.00 | 3.00 |
Date | December 31, 2018 | October 6, 2023 | December 31, 2023 | |
Comment |
Establishment of social and environmental risk management system in CAGEPA | Value | No | Yes | Yes |
Date | December 31, 2018 | October 6, 2023 | December 30, 2022 | |
Comment |
Reduction of the time lost from routine activities because of waterborne and gastrointestinal diseases - MEN | Value | 3.15 | 3.15 | 2.30 |
Date | December 31, 2018 | October 6, 2023 | December 31, 2024 | |
Comment |
Reduction of the gender gap in time spent with household workloads (including fetching water to the household) | Value | 73.00 | 73.00 | 53.00 |
Date | June 30, 2020 | October 6, 2023 | June 30, 2025 | |
Comment |
Level of beneficiary satisfaction with project activities in the Transparaíba Water Supply System | Value | 0.00 | 0.00 | 80.00 |
Date | December 31, 2018 | October 6, 2023 | June 30, 2025 | |
Comment |
Grievances and claims addressed and resolved within the agreed time frame | Value | 0.00 | 100.00 | 80.00 |
Date | December 31, 2018 | October 6, 2023 | June 30, 2025 | |
Comment |
Reduction of the time lost from routine activities because of waterborne and gastrointestinal diseases - WOMEN | Value | 3.48 | 3.48 | 2.30 |
Date | December 31, 2018 | October 6, 2023 | December 31, 2024 | |
Comment |
AESA draft resolution with revised criteria for water rights is submitted to the State Water Resources Council | Value | No | No | Yes |
Date | December 31, 2018 | October 6, 2023 | December 31, 2022 | |
Comment |
Increased water treatment capacity in the Agreste and Borborema Regions | Value | 0.00 | 0.00 | 23000000.00 |
Date | December 31, 2018 | October 6, 2023 | December 31, 2024 | |
Comment |
AESA draft resolution with revised bulk water charges submitted to the State Waer Resources Council | Value | No | No | Yes |
Date | December 31, 2018 | October 6, 2023 | December 31, 2023 | |
Comment |
Water distribution sectors zones implemented in João Pessoa Metropolitan Region | Value | 0.00 | 0.00 | 29.00 |
Date | December 31, 2018 | October 6, 2023 | December 31, 2024 | |
Comment |
Updated Paraiba River Basin plan submitted to the Paraiba River Basin Committee | Value | No | No | Yes |
Date | December 31, 2018 | October 6, 2023 | December 31, 2023 | |
Comment |
Energy efficiency increased in the wastewater system in João Pessoa Metropolitan Region | Value | 8.90 | 8.90 | 4.10 |
Date | December 31, 2018 | October 6, 2023 | June 30, 2025 | |
Comment |
Number of dams prioritized for future design in the Piranhas-Açu Basin | Value | 0.00 | 0.00 | 3.00 |
Date | December 31, 2018 | October 6, 2023 | December 31, 2024 | |
Comment |