Benin Second Fiscal Reform and Growth DPF

Abstract*

The fiscal reform and growth development policy financing (DPF) series aims at supporting the government’s effort to implement its government action plan (GAP) over the period 2016-2021. The operation continues supporting the reforms started under the same the two pillars of the first operation of this DPF series, with the inclusion of a third pillar on social services. The first pillar continues to focus on strengthening fiscal management. The second...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The program development objectives of this FRG series are to: 1) strengthen fiscal management; 2) increase agricultural productivity and strengthen the financial viability of the power sector; and 3) improve equitable access to education and health services.

Key Details

Project Details

  • P166115

  • Closed

  • Andrea Coppola

  • The Republic of Benin

  • Benin

  • April 23, 2018

  • (as of board presentation)

    August 30, 2018

  • November 16, 2018

  • US$ 30.00 million

  • Ministry of Economy and Finance

  • Western and Central Africa

  • 2019

  • US$ 15.00 million

  • N/A

  • Not Applicable

  • June 30, 2019

  • BANK APPROVED

  • P160700

  • March 6, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Guarantee 180.00
IDA Credit 15.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 15.00
IBRD + IDA Commitment 15.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 30.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 6, 2023 IDA-63070 Int Charges 52,082.94
Aug 1, 2021 IDA-63070 Int Charges 57,575.93
Aug 1, 2021 IDA-63070 Int Charges 57,575.93
Aug 1, 2020 IDA-63070 Int Charges 57,326.79
Aug 1, 2020 IDA-63070 Int Charges 57,326.79
Feb 1, 2021 IDA-63070 Int Charges 58,446.68
Feb 1, 2021 IDA-63070 Int Charges 58,446.68
Dec 5, 2018 IDA-63070 Loan Disb 14,647,950.00
Aug 1, 2019 IDA-63070 Int Charges 16,605.42
Aug 1, 2019 IDA-63070 Int Charges 16,605.42
Aug 1, 2019 IDA-63070 Int Charges 53,374.56
Aug 1, 2019 IDA-63070 Int Charges 53,374.56
Feb 1, 2020 IDA-63070 Int Charges 53,391.49
Aug 12, 2024 IDA-63070 Int Charges 52,856.94
Aug 30, 2018 IDA-63070 Loan Commitment 15,000,000.00
Feb 1, 2020 IDA-63070 Int Charges 53,391.49
Aug 12, 2024 IDA-63070 Int Charges 52,856.94
Feb 1, 2024 IDA-63070 Int Charges 52,288.54
Feb 1, 2024 IDA-63070 Int Charges 52,288.54
Aug 1, 2023 IDA-63070 Int Charges 53,127.84
Aug 1, 2023 IDA-63070 Int Charges 53,127.84
Aug 2, 2022 IDA-63070 Int Charges 49,473.11
Aug 2, 2022 IDA-63070 Int Charges 49,473.11
Feb 1, 2022 IDA-63070 Int Charges 54,535.56
Feb 1, 2022 IDA-63070 Int Charges 54,535.56
Feb 6, 2023 IDA-63070 Int Charges 52,082.94

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-14-2020
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 02-22-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of agro-ecological zone-specific experiments launchedValue022>15
    DateDecember 30, 2016December 31, 2019December 31, 2019
    Comment
  • Moving average (three years) of the quantity (tons) of processed cashew (C).Value5600.005920.008500.00
    DateDecember 30, 2016December 31, 2019December 31, 2019
    Comment
  • Processed pineapple (P)Value52000.00177735.000.00
    Date
    Comment
  • Tax expenditures associated with tax exemptions granted to cell phone companies (CFAF billion).Value17.50<1
    DateDecember 30, 2016December 31, 2019December 31, 2019
    Comment
  • Share of non-customs taxes paid through the banking system or the e-payment system.Value0.0070.0065.00
    DateDecember 30, 2016December 31, 2019December 31, 2019
    Comment
  • Percentage of civil servants’ salaries and benefits processed through the unified wage management systemValue0Only new civil servants from 2016 onward (exact nu>80
    DateDecember 30, 2016December 31, 2019December 31, 2019
    Comment
  • Share of payments of pensions (above CFAF 50,000), scholarships, and civil servants’ benefits processed through the banking system.Value090>80%
    DateDecember 30, 2016December 31, 2019December 31, 2019
    Comment
  • Processed rice (R).Value33300.00254100.000.00
    Date
    Comment
  • Share of cashew (C) samples tested by LCSSA which meet international standards.Value88.6094.0090.00
    DateDecember 30, 2016December 31, 2019December 31, 2019
    Comment
  • Pineapple (P)Value88.1097.000.00
    Date
    Comment
  • SBEE’s arrears with CEB (billions of CFAF)Value39.211.82<10
    DateDecember 30, 2016December 31, 2019December 31, 2019
    Comment
  • SBEE’s revenue collection rate from all public-sector institutions.Value5.0080.0050.00
    DateDecember 30, 2016December 31, 2019December 31, 2019
    Comment
  • Percentage of revenue protected through the installation of smart energy meters for large consumers.Value0.000.0040.00
    DateDecember 31, 2017December 31, 2019December 31, 2019
    Comment
  • Percentage of newly recruited teacher deployed in communes with pupils/teacher ratio higher than the national average.Value65.0065.0090.00
    DateDecember 30, 2016December 31, 2019December 31, 2019
    Comment
  • Percentage of newly recruited health personnel deployed in Priority Health Precincts.Value31.000.0070.00
    DateDecember 31, 2018December 31, 2019December 31, 2019
    Comment