Skip to Main Navigation

Disaster Risk Management Development Policy Loan with a Catastrophe Deferred Drawdown Option

Abstract*

The Program Development Objective (PDO) of the Building Disaster and Climate Resilience Program Project for Romania is to strengthen Romania’s institutional and legal framework to effectively manage the physical, social and fiscal impacts of natural disasters and climate change.This objective will be achieved through reforms under two pillars: i) Strengthen the Borrower’s national framework for disaster risk management and (ii) Strengthen the Borrower’s...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Program Development Objective (PDO) is to strengthen Romania’s institutional and legal framework to effectively manage the physical, social and fiscal impacts of natural disasters and climate change

Key Details

Project Details

  • P166303

  • Closed

  • Alanna Simpson , Tafadzwa Dube

  • Ministry of Finance

  • Romania

  • December 29, 2017

  • (as of board presentation)

    June 26, 2018

  • December 20, 2018

  • US$ 493.00 million

  • Ministry of Development, Public Works and Administration,Ministry of Internal Affairs - Department of Emergency Situations,Ministry of Finance,Ministry of Internal Affairs - General Inspectorate of Emergency Situations

  • Europe and Central Asia

  • 2018

  • US$ 493.06 million

  • N/A

  • Not Applicable

  • December 31, 2021

  • BANK APPROVED

  • October 12, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 493.06

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 493.06
IDA Commitment N/A
IBRD + IDA Commitment 493.06
Lending Instrument
Grant Amount N/A
Total Project Cost** 493.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 26, 2018 IBRD-88790 Loan Commitment 493,060,000.00
Nov 1, 2023 IBRD-88790 Int Charges 5,682,325.00
Nov 1, 2023 IBRD-88790 Int Charges 5,682,325.00
May 1, 2024 IBRD-88790 Int Charges 6,213,625.50
May 1, 2024 IBRD-88790 Int Charges 6,213,625.50
Nov 1, 2022 IBRD-88790 Int Charges 1,432,252.90
Nov 1, 2022 IBRD-88790 Int Charges 1,432,252.90
May 1, 2023 IBRD-88790 Int Charges 4,074,004.20
May 1, 2023 IBRD-88790 Int Charges 4,074,004.20
May 1, 2022 IBRD-88790 Int Charges 1,189,853.80
May 1, 2022 IBRD-88790 Int Charges 1,189,853.80
May 1, 2021 IBRD-88790 Int Charges 1,372,623.50
May 1, 2021 IBRD-88790 Int Charges 1,372,623.50
Nov 1, 2021 IBRD-88790 Int Charges 1,336,636.80
Nov 1, 2021 IBRD-88790 Int Charges 1,336,636.80
Nov 1, 2020 IBRD-88790 Int Charges 297,337.25
Nov 1, 2020 IBRD-88790 Int Charges 1,765,995.20
Nov 1, 2020 IBRD-88790 Int Charges 1,765,995.20
Feb 14, 2019 IBRD-88790 Fee Charges 2,253,700.00
Mar 27, 2020 IBRD-88790 Loan Disb 220,300,000.00
Mar 27, 2020 IBRD-88790 Loan Disb -220,300,000.00
Mar 27, 2020 IBRD-88790 Loan Disb 220,300,000.00
Feb 14, 2020 IBRD-88790 Loan Disb -216,750,000.00
Feb 14, 2020 IBRD-88790 Loan Disb 216,750,000.00
Feb 14, 2020 IBRD-88790 Loan Disb 216,750,000.00
May 1, 2020 IBRD-88790 Int Charges 615,419.06

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2021-08-09
Program Management Satisfactory 2021-08-09
Progress towards achievement of PDO Satisfactory 2021-08-09
Monitoring and Evaluation Satisfactory 2021-08-09

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-07-2022
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-26-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • B1. The national building code for seismic risk in existing buildings is strengthened.ValueNoYesYes
    DateMay 25, 2018November 30, 2022December 31, 2021
    Comment
  • A.1. The Government of Romania has reported on progress achieved under the international Sendai Framework for Disaster Risk Reduction.Value0.004.001.00
    DateMay 25, 2018November 30, 2022December 31, 2021
    Comment
  • B2. Disaster risk reduction action plans are prepared and approved by the relevant responsible authorities.Value0.007.003.00
    DateMay 25, 2018November 30, 2022December 31, 2021
    Comment
  • A.2. Romanian citizens have enhanced understanding of the potential impacts of disasters and how they can prevent, prepare and respond to disasters through public awareness campaigns, drills and digitValue0.006.006.00
    DateMay 25, 2018November 30, 2022December 31, 2021
    Comment
  • B3. The fiscal and budgetary strategy is informed by main disaster risks and their potential fiscal impact, taking into consideration publicly available Ro-Risk data.ValueNoYesYes
    DateMay 25, 2018November 30, 2022December 31, 2021
    Comment
  • A.3. Reports are available annually on the impact of disasters in Romania.Value0.004.003.00
    DateMay 25, 2018November 30, 2022December 31, 2021
    Comment