Timor-Leste - Timor Leste Road Climate Resilience Proj (English)May 2, 2024ICRR0023845Implementation Completion Report Review
Timor-Leste - Road Climate Resilience Project (English)November 29, 2023ICR6223Implementation Completion and Results Report
Timor-Leste - EAST ASIA AND PACIFIC - P125032 - Timor Leste Road Climate Resilience Project - Audited Financial Statement (English)October 20, 2023SCA0090468Auditing Document
Disclosable Version of the ISR - Timor Leste Road Climate Resilience Project - P125032 - Sequence No : 25 (English)December 19, 2022ISR54413Implementation Status and Results Report
Timor-Leste - EAST ASIA AND PACIFIC - P125032 - Timor Leste Road Climate Resilience Project - Audited Financial Statement (English)November 16, 2022SCA0072367Auditing Document
Timor-Leste - EAST ASIA AND PACIFIC - P125032 - Timor Leste Road Climate Resilience Project - Audited Financial Statement (English)November 16, 2022SCA0072367Auditing Document
Disclosable Version of the ISR - Timor Leste Road Climate Resilience Project - P125032 - Sequence No : 24 (English)September 12, 2022ISR52733Implementation Status and Results Report
Timor-Leste - EAST ASIA AND PACIFIC - P125032 - Timor Leste Road Climate Resilience Project - Audited Financial Statement (English)June 28, 2022SCA0066447Auditing Document
Disclosable Version of the ISR - Timor Leste Road Climate Resilience Project - P125032 - Sequence No : 23 (English)May 19, 2022ISR51308Implementation Status and Results Report
Timor-Leste - EAST ASIA AND PACIFIC- P125032- Timor Leste Road Climate Resilience Project - Procurement Plan (English)April 3, 2022STEP62800Procurement Plan
Disclosable Version of the ISR - Timor Leste Road Climate Resilience Project - P125032 - Sequence No : 22 (English)November 12, 2021ISR48945Implementation Status and Results Report
Disclosable Restructuring Paper - Timor Leste Road Climate Resilience Project - P125032 (English)November 2, 2021RES48770Project Paper
Disclosable Restructuring Paper - Timor Leste Road Climate Resilience Project - P125032 (English)June 7, 2021RES46745Project Paper
Disclosable Version of the ISR - Timor Leste Road Climate Resilience Project - P125032 - Sequence No : 21 (English)May 12, 2021ISR46654Implementation Status and Results Report
Timor-Leste - EAST ASIA AND PACIFIC - P125032 - Timor Leste Road Climate Resilience Project - Audited Financial Statement (English)February 18, 2021SCA0014176Auditing Document
Disclosable Restructuring Paper - Timor Leste Road Climate Resilience Project - P125032 (English)December 10, 2020RES44425Project Paper
Disclosable Version of the ISR - Timor Leste Road Climate Resilience Project - P125032 - Sequence No : 20 (English)November 19, 2020ISR44107Implementation Status and Results Report
Disclosable Version of the ISR - Timor Leste Road Climate Resilience Project - P125032 - Sequence No : 19 (English)May 29, 2020ISR41995Implementation Status and Results Report
Timor-Leste - EAST ASIA AND PACIFIC- P125032- Timor Leste Road Climate Resilience Project - Procurement Plan (English)March 2, 2020STEP30579Procurement Plan
Timor-Leste - Road Climate Resilience Project : INT Redacted Report (English)March 1, 2020146567Board Report