Power Rehabilitation and Extension Project

Abstract*

The project objectives are to: (a) support the institutional strengthening of the Societe Beninoise d'Electricite et d'Eau, particularly its management, planning, engineering and financial operations; and (b) help meet increased demand for electricity through improving and extending distribution in selected markets. The project will comprise the following elements: (a) the rehabilitation and extension of the Cotonou, Porto Novo and Abomey/Bohicon...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

REHABILITATION AND EXPANSION OF THE COTONOU, PORTO-NOVO AND ABOMEY/ BOHICON AREA DISTRIBUTION SYSTEMS, AND TA/TRAINING TO STRENGTHEN SECTOR INSTITUTIONS (MAINLY SBEE); INCLUDING DIAGNOSTIC STUDY

Key Details

Project Details

  • P000108

  • Closed

  • Said R. Mikhail

  • N/A

  • Benin

  • June 27, 1991

  • (as of board presentation)

    June 27, 1991

  • June 29, 1992

  • US$ 28.20 million

  • B

  • Not Applicable

  • June 30, 2000

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 15.00
FRANCE: French Agency for Development 13.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 15.00
IBRD + IDA Commitment 15.00
Lending Instrument
Grant Amount 13.20
Total Project Cost** 36.50

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 27, 1991 IDA-22840 Loan Commitment 15,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-27-2001PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.