Antananarivo Plain Development

Abstract*

The Antananarivo Plain Development Project for Madagascar aims to improve the living conditions of the low income population living in the low lying areas of the city and in the Antananarivo plain, and to increase the productivity of the industries and of the farms in the plain. To reach these objectives, the project will specifically: a) provide a 100 year flood protection to the suburbs of Antananarivo; b) improve, rehabilitate and expand the drainage...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

FOLLOW UP WATER SUPPLY AND SANITATION I, FLOOD CONTROL OF ANTANANARIVOPLAIN, DRAINAGE AND IRRIGATION, AND INSTITUTIONAL STRENGTHENING FORFLOOD CONTROL AND SANITATION; URBANIZATION DEVELOPMENT AND MANAGEMENT

Key Details

Project Details

  • P001512

  • Closed

  • Arnaud Marie Guinard

  • N/A

  • Madagascar

  • March 29, 1990

  • (as of board presentation)

    March 29, 1990

  • January 31, 1991

  • US$ 52.80 million

  • B

  • Not Applicable

  • September 30, 1999

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
FRANCE: FUND FOR AID AND COOP. 0.80
FRANCE: French Agency for Development 21.50
IDA Credit 30.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 30.50
IBRD + IDA Commitment 30.50
Lending Instrument
Grant Amount 22.30
Total Project Cost** 68.60

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 29, 1990 IDA-21170 Loan Commitment 30,500,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 07-27-2000PROJECT PERFORMANCE ASSESSMENT REPORT: 06-30-2001
Outcome RatingModerately Satisfactory Moderately Unsatisfactory
Risk To Development OutcomeNot RatedNot Rated
Bank PerformanceUnsatisfactoryUnsatisfactory
Borrower PerformanceSatisfactoryUnsatisfactory
Government PerformanceUnsatisfactorySatisfactory
Implementing AgencySatisfactoryNot Rated
Icr QualitySatisfactoryNot Rated
M&e QualityNot RatedNot Rated

Results Framework