Skip to Main Navigation

MZ-Agr Sec Pep (FY99)

Abstract*

The Agricultural Sector Expenditure Program (PROAGRI) aims at improving public expenditure, securing a sustainable and equitable growth in the rural sector, reducing poverty and improving food security, while protecting the environment. The program's components are grouped into three subprograms: 1) the institutional development will focus on an analysis of the structure of the Ministry of Agriculture and Fisheries (MAP), its decision-making, and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

SUPPORT TO THE NATIONAL AGRICULTURAL INVESTMENT PROGRAM.THE PROGRAM WILL FOCUS ON (I) AGRICULTURE RESEARCH AND EXTENSION (II) PILOT LAND DEMARCATION, ADJUDICATION AND CADASTRE &(III)INSTITUTIONAL REFORM AND MODERNIZATION OF THE MIN. OF AGRIC. & FISHERIES AND THE DEVELOPMENT OF ITS HUMAN RESOURCES AND MANAGEMENT SYSTEM. PROGRAM WOULD ALSO INCLUDE PRIORITY REFORMS IN THE SECTOR POLICY ENVIRONMENT.

Key Details

Project Details

  • P001799

  • Closed

  • Daniel Liborio Da Cruz Sousa

  • N/A

  • Mozambique

  • November 30, 1998

  • (as of board presentation)

    February 18, 1999

  • August 12, 1999

  • US$ 30.00 million

  • B

  • Not Applicable

  • December 31, 2006

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 30.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 30.00
IBRD + IDA Commitment 30.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 216.50

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 6, 2016 IDA-31710 Loan Repay 137,244.17
Sep 6, 2016 IDA-31710 Int Charges 5.74
Sep 6, 2016 IDA-31710 Int Charges 5.74
Sep 6, 2016 IDA-31710 Int Charges 43,691.07
Mar 20, 2018 IDA-31710 Int Charges 3,441.10
Mar 20, 2018 IDA-31710 Loan Repay 142,941.77
Mar 20, 2018 IDA-31710 Int Charges 40,444.53
Mar 20, 2018 IDA-31710 Int Charges 40,444.53
Sep 1, 2017 IDA-31710 Int Charges 40,101.68
Sep 1, 2017 IDA-31710 Int Charges 288.09
Sep 1, 2017 IDA-31710 Int Charges 288.09
Sep 1, 2017 IDA-31710 Loan Repay 139,639.36
Sep 25, 2018 IDA-31710 Int Charges 3,397.03
Sep 25, 2018 IDA-31710 Int Charges 3,397.03
Sep 25, 2018 IDA-31710 Loan Repay 138,319.19
Sep 25, 2018 IDA-31710 Int Charges 54.75
Sep 25, 2018 IDA-31710 Int Charges 54.75
Sep 25, 2018 IDA-31710 Int Charges 42,014.98
Sep 25, 2018 IDA-31710 Int Charges 42,014.98
Mar 20, 2018 IDA-31710 Int Charges 3,441.10
Sep 16, 2019 IDA-31710 Int Charges 3.11
Sep 16, 2019 IDA-31710 Int Charges 3.11
Sep 16, 2019 IDA-31710 Loan Repay 270,133.50
Mar 4, 2014 IDA-31710 Int Charges 50,590.42
Mar 4, 2014 IDA-31710 Int Charges 50,590.42
Mar 4, 2014 IDA-31710 Int Charges 1,763.65
Mar 4, 2014 IDA-31710 Int Charges 1,763.65
Mar 4, 2014 IDA-31710 Loan Repay 152,329.73
Sep 1, 2013 IDA-31710 Loan Repay 3,940.52
Sep 1, 2013 IDA-31710 Loan Repay 145,344.95
Sep 1, 2013 IDA-31710 Int Charges 49,215.82
Sep 1, 2013 IDA-31710 Int Charges 49,215.82
Sep 1, 2014 IDA-31710 Int Charges 806.62
Mar 1, 2015 IDA-31710 Loan Repay 3,956.85
Sep 1, 2014 IDA-31710 Loan Repay 149,590.88
Mar 5, 2015 IDA-31710 Loan Repay 65,143.44
Mar 5, 2015 IDA-31710 Loan Repay 68,591.10
Mar 5, 2015 IDA-31710 Int Charges 45,429.29
Mar 5, 2015 IDA-31710 Int Charges 45,429.29
Sep 1, 2014 IDA-31710 Int Charges 806.62
Sep 1, 2014 IDA-31710 Int Charges 9.34
Sep 1, 2014 IDA-31710 Int Charges 9.34
Sep 1, 2014 IDA-31710 Int Charges 49,926.52
Sep 1, 2014 IDA-31710 Int Charges 49,926.52
Sep 1, 2015 IDA-31710 Loan Repay 6,719.80
Sep 1, 2015 IDA-31710 Loan Repay 131,982.64
Sep 1, 2015 IDA-31710 Int Charges 11.23
Sep 1, 2015 IDA-31710 Int Charges 11.23
Sep 1, 2015 IDA-31710 Int Charges 44,507.38
Sep 1, 2015 IDA-31710 Int Charges 44,507.38
Sep 6, 2016 IDA-31710 Int Charges 43,691.07
Mar 3, 2016 IDA-31710 Int Charges 731.36
Mar 3, 2016 IDA-31710 Int Charges 731.36
Mar 3, 2016 IDA-31710 Loan Repay 136,196.10
Mar 3, 2016 IDA-31710 Int Charges 43,923.71
Mar 3, 2016 IDA-31710 Int Charges 43,923.71
Mar 17, 2023 IDA-31710 Int Charges -43.21
Mar 17, 2023 IDA-31710 Int Charges -43.21
Mar 17, 2023 IDA-31710 Int Charges -30,730.18
Mar 17, 2023 IDA-31710 Int Charges -30,730.18
Mar 17, 2023 IDA-31710 Loan Repay -25,826.78
Mar 7, 2024 IDA-31710 Int Charges 29,526.62
Mar 7, 2024 IDA-31710 Int Charges 29,526.62
Mar 1, 2024 IDA-31710 Loan Repay 2,316.81
Mar 7, 2024 IDA-31710 Int Charges 103.90
Mar 7, 2024 IDA-31710 Int Charges 103.90
Sep 20, 2023 IDA-31710 Loan Repay 41,105.20
Sep 20, 2023 IDA-31710 Int Charges 169.34
Feb 18, 1999 IDA-31710 Loan Commitment 16,102,819.00
Feb 18, 1999 IDA-3171A Loan Commitment 13,897,181.00
Mar 7, 2024 IDA-31710 Loan Repay 260,130.66
Mar 1, 2022 IDA-31710 Loan Repay 942.57
Mar 17, 2022 IDA-31710 Loan Repay 271,622.30
Mar 17, 2022 IDA-31710 Int Charges 112.76
Mar 17, 2022 IDA-31710 Int Charges 112.76
Mar 17, 2022 IDA-31710 Int Charges 34,751.33
Mar 17, 2022 IDA-31710 Int Charges 34,751.33
Mar 1, 2023 IDA-31710 Loan Repay 6,098.89
Apr 3, 2023 IDA-31710 Loan Repay 258,849.34
Apr 3, 2023 IDA-31710 Int Charges 43.55
Apr 3, 2023 IDA-31710 Int Charges 43.55
Apr 3, 2023 IDA-31710 Int Charges 28,749.34
Apr 3, 2023 IDA-31710 Int Charges 28,749.34
Sep 1, 2022 IDA-31710 Loan Repay 3,623.74
Sep 9, 2022 IDA-31710 Loan Repay 252,993.47
Sep 9, 2022 IDA-31710 Int Charges 85.25
Sep 9, 2022 IDA-31710 Int Charges 85.25
Sep 9, 2022 IDA-31710 Int Charges 31,756.82
Sep 9, 2022 IDA-31710 Int Charges 31,756.82
Sep 20, 2023 IDA-31710 Int Charges 169.34
Sep 20, 2023 IDA-31710 Int Charges 30,228.17
Sep 20, 2023 IDA-31710 Int Charges 30,228.17
Sep 20, 2023 IDA-31710 Loan Repay 26,546.81
Sep 20, 2023 IDA-31710 Int Charges 2,993.47
Sep 20, 2023 IDA-31710 Int Charges 2,993.47
Sep 20, 2023 IDA-31710 Loan Repay 16,241.63
Sep 20, 2023 IDA-31710 Loan Repay 176,131.67
Mar 17, 2023 IDA-31710 Int Charges 43.21
Mar 17, 2023 IDA-31710 Int Charges 43.21
Mar 17, 2023 IDA-31710 Loan Repay 231,042.05
Mar 17, 2023 IDA-31710 Int Charges 30,730.18
Mar 17, 2023 IDA-31710 Int Charges 30,730.18
Mar 17, 2023 IDA-31710 Loan Repay 25,826.78
Mar 17, 2023 IDA-31710 Loan Repay -231,042.05
Mar 7, 2019 IDA-31710 Int Charges 41,103.83
Mar 7, 2019 IDA-31710 Int Charges 41,103.83
Mar 7, 2019 IDA-31710 Loan Repay 273,705.30
Mar 7, 2019 IDA-31710 Int Charges 68.51
Mar 7, 2019 IDA-31710 Int Charges 68.51
Mar 1, 2019 IDA-31710 Loan Repay 340.36
Mar 1, 2020 IDA-31710 Loan Repay 3,871.67
Mar 17, 2020 IDA-31710 Loan Repay 265,782.84
Mar 17, 2020 IDA-31710 Int Charges 84.27
Mar 17, 2020 IDA-31710 Int Charges 84.27
Mar 17, 2020 IDA-31710 Int Charges 38,424.11
Mar 17, 2020 IDA-31710 Int Charges 38,424.11
Sep 16, 2019 IDA-31710 Int Charges 33.73
Sep 16, 2019 IDA-31710 Int Charges 33.73
Sep 16, 2019 IDA-31710 Int Charges 39,507.30
Sep 16, 2019 IDA-31710 Int Charges 39,507.30
Mar 11, 2021 IDA-31710 Int Charges 7,308.40
Mar 11, 2021 IDA-31710 Int Charges 7,308.40
Mar 11, 2021 IDA-31710 Loan Repay 282,086.03
Mar 11, 2021 IDA-31710 Int Charges 46.47
Mar 11, 2021 IDA-31710 Int Charges 46.47
Sep 1, 2020 IDA-31710 Loan Repay 3,224.47
Sep 9, 2020 IDA-31710 Loan Repay 274,433.53
Sep 9, 2020 IDA-31710 Int Charges 91.23
Sep 9, 2020 IDA-31710 Int Charges 91.23
Sep 9, 2020 IDA-31710 Int Charges 31,327.94
Sep 9, 2020 IDA-31710 Int Charges 31,327.94
Sep 1, 2021 IDA-31710 Loan Repay 1,981.24
Sep 21, 2021 IDA-31710 Loan Repay 277,759.03
Sep 21, 2021 IDA-31710 Int Charges 58.28
Sep 21, 2021 IDA-31710 Int Charges 58.28
Sep 21, 2021 IDA-31710 Int Charges 36,715.57
Sep 21, 2021 IDA-31710 Int Charges 36,715.57
Mar 11, 2021 IDA-31710 Int Charges 38,081.91
Mar 11, 2021 IDA-31710 Int Charges 38,081.91
Sep 1, 2017 IDA-31710 Int Charges 40,101.68
Sep 1, 2017 IDA-31710 Int Charges 5.83
Sep 1, 2017 IDA-31710 Int Charges 5.83
Mar 3, 2017 IDA-31710 Loan Repay 132,651.34
Mar 3, 2017 IDA-31710 Int Charges 13.77
Mar 3, 2017 IDA-31710 Int Charges 13.77
Mar 3, 2017 IDA-31710 Int Charges 41,511.96
Mar 3, 2017 IDA-31710 Int Charges 41,511.96
Mar 3, 2017 IDA-31710 Int Charges 187.17
Mar 3, 2017 IDA-31710 Int Charges 187.17
Sep 1, 2016 IDA-31710 Loan Repay 433.03

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Satisfactory 2006-12-26
Monitoring and Evaluation Moderately Satisfactory 2006-12-26
Procurement Moderately Unsatisfactory 2006-12-26
Counterpart Funding Satisfactory 2006-12-26
Overall Implementation Progress (IP) Satisfactory 2006-12-26
Progress towards achievement of PDO Satisfactory 2006-12-26
Project Management Satisfactory 2006-12-26
Financial Management Satisfactory 2006-12-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-19-2007
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceSubstantial
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-17-2007PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • MADER/MINAG institutionally transformedValueMAP (Ministry of Agriculture And Fisheries) used tCentral driectorates reduced from 8 to four . FourMAP/MADER/MINAG reestructured
    DateOctober 1, 1999November 30, 2006June 30, 2004
    Comment
  • No. of and type of staff employed by MINAG and level of qualificationValueIn 2001, MADER had 5297 permanent staff, of whom 8Relative to 2001, MINAG (2006) has reduced its peTotal MINAG staff downsized and level of qualifcat
    DateJanuary 1, 1999December 5, 2006June 30, 2004
    Comment
  • % of budget allocated to Provinces& districtsValueProvincial budgets are 42.5% of the total budgetIn ave.& actual expenitures terms, along Phase 1 (60% of the PROAGRI I Budget allocated to provinces
    DateJune 1, 1999June 30, 2006November 30, 2005
    Comment
  • % of techncial services budget contracted outValue0% of extension services budget contracted out.Plans (2002-2007) indicated propects to spend US1Experiment various types of arrangements on outsou
    DateJanuary 1, 1999May 31, 2006June 30, 2004
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Progress report by FM technical assistance team and Financial Audits Management letters reporting progress in development of FM system and financial prudenceValue MADER operating through an outdated FM system andAccounting & FM application in use is in its 6th vArco-iris system generates financial reports for M
    DateJanuary 1, 2000November 30, 2006June 30, 2005
    Comment
  • 1.2 Implementation manual detailing budgeting, EIA, financial management, and M&E procedures.ValueNoneNwe Plann.& Budg. software used for 2007 Plan & BuMINAG's Planning & Budgeting and financial Mangeme
    DateJune 30, 1998May 31, 2006November 30, 2005
    Comment
  • Number of staff retrenchedValueNo funds for retrenchement. Aged employees witho1075 staff (20% of total staff existing in 1999) By the end of 2006, aorund 26% of the total num
    DateJune 30, 2001November 30, 2006June 30, 2005
    Comment
  • Adequate statistical data collected in order to monitor PROAGRI performance and to serve as reference to policy formulation.ValueOnly One agricultural survey (1996) conducted befoAg. Census 1999-2000 completed & ag.surveys conducMINAG to have developed and fully deployed an inte
    DateDecember 31, 1998May 31, 2006September 15, 2005
    Comment