Development Objective

ASSIST GOM TO STRENGTHEN ECONOMIC MANAGEMENT AND TO IMPLEMENT REFORMS AT THE INSTITUTIONAL LEVEL SO AS TO FOSTER SUPPLY RESPONSE FROM MARKET FORCES.

Key Details

Project Details

  • P001874

  • Closed

  • Miquel J. Saponara

  • N/A

  • Mauritania

  • May 6, 1996

  • (as of board presentation)

    June 20, 1996

  • July 30, 1996

  • US$ 38.00 million

  • N/A

  • Not Applicable

  • December 31, 1999

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 20.00
EC: EUROPEAN UNION 18.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 20.00
IBRD + IDA Commitment 20.00
Lending Instrument
Grant Amount 18.00
Total Project Cost** 19.30

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 15, 1997 IDA-28872 Loan Commitment 400,000.00
Nov 18, 1999 IDA-28874 Loan Commitment 137,000.00
Nov 14, 1996 IDA-28871 Loan Commitment 600,000.00
Jun 20, 1996 IDA-28870 Loan Commitment 20,000,000.00
Feb 26, 1999 IDA-28873 Loan Commitment 136,991.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-08-2000PROJECT PERFORMANCE ASSESSMENT REPORT: 07-01-2004
Outcome RatingSatisfactory Moderately Satisfactory
Risk To Development OutcomeNot RatedNot Rated
Bank PerformanceSatisfactorySatisfactory
Borrower PerformanceSatisfactorySatisfactory
Government PerformanceSatisfactorySatisfactory
Implementing AgencySatisfactoryNot Rated
Icr QualitySatisfactoryNot Rated
M&e QualityNot RatedNot Rated

Results Framework

No data available.