Rwanda Energy Sector Rehabilitation and Urban Waste Management

Abstract*

The overall objective of the project is to promote rational energy policies and to establish the basis for efficient utilization of Rwanda's energy resources, while minimizing adverse environmental implications. The project comprises two main components: (a) strengthening of the institutional regulatory and policy environment; and (b) rehabilitation of key infrastructure in the power subsector. The first component will include: (i) restructuring the...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

REHABILITATION MV TRANSMISSION AND DISTRIBUTION NETWORKS; DISTRIBUTIONEXPANSION BASED ON POLICIES TO IMPROVE AFFORDABILITY. ASSISTANCE TO(ELECTROGAZ) FOR RESTRUCTURING AND STRENGTHENING OF POWER PLANNING.PRICING POLICY MEASURES FOR PETROLEUM PRODUCTS, WOODFUEL AND SOLARSYSTEMS.

Key Details

Project Details

  • P002241

  • Closed

  • Yuriko Sakairi

  • N/A

  • Rwanda

  • February 9, 1993

  • (as of board presentation)

    February 9, 1993

  • January 21, 1994

  • US$ 26.00 million

  • B

  • Not Applicable

  • December 31, 2001

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 26.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 26.00
IBRD + IDA Commitment 26.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 26.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 9, 1993 IDA-24560 Loan Commitment 26,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-21-2003PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a