Abstract*

The proposed project will consist of: (a) two systemwide components, to assist the Ministry of Railways on a pilot basis to introduce recent technology and advanced materials in the maintenance and rehabilitation of track, and to meet the shortage of critically-needed items of material, components, and equipment for rehabilitation of locomotives and rolling stock; (b) two capacity expansion components, to complete double-tracking of the 944 Km Zhegan...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

EXPANSION OF A MAJOR RAILWAY FREIGHT TERMINAL AND CLASSIFICATION YARDAND OTHER OPERATIONAL AND CAPACITY ENHANCING INVESTMENTS.

Key Details

Project Details

  • P003486

  • Closed

  • Udo Marggraf

  • N/A

  • China

  • September 24, 1991

  • (as of board presentation)

    September 24, 1991

  • January 9, 1992

  • US$ 330.00 million

  • B

  • Not Applicable

  • December 31, 1998

  • BANK APPROVED

  • March 11, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 330.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 330.00
IDA Commitment N/A
IBRD + IDA Commitment 330.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 1530.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 24, 1991 IBRD-3406A Loan Commitment 33,731,460.00
Sep 24, 1991 IBRD-3406S Loan Commitment 290,863,872.00
Sep 24, 1991 IBRD-34060 Loan Commitment 5,404,656.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-30-1999PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.