The objectives of the Shanghai-Zheijiang Highway Project are: 1) to increase highway capacity in the Shanghai-Hangzhou corridor in order to relieve existing congestion and promote economic development; 2) to improve road safety in northern Zhejiang; and 3) to develop highway sector institutional capability in Shanghai and Zhejiang. The project consists of four main components: (1) the construction of the Shanghai-Hangzhou Expressway, a 130 km divided...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

CONSTRUCTION OF THE SHANGHAI-ZHEJIANG EXPRESSWAY, EQUIPMENT PROCURE-MENT, STAFF TRAINING, CVIL WORKS IMPROVEMENTS AND TECHNICALASSISTANCE/TRAINING FOR ROAD SAFETY.

Key Details

Project Details

  • P003569

  • Closed

  • Yasuhiro Kawabata

  • N/A

  • China

  • October 31, 1994

  • (as of board presentation)

    August 1, 1995

  • January 30, 1996

  • US$ 260.00 million

  • A

  • Not Applicable

  • December 31, 2001

  • BANK APPROVED

  • March 11, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 260.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 260.00
IDA Commitment N/A
IBRD + IDA Commitment 260.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 614.02

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 1, 1995 IBRD-39290 Loan Commitment 260,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-27-2002PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework