Skip to Main Navigation

Railway VI

Abstract*

The main objectives of the project are to support the Ministry of Railways (MOR's) effort in undertaking: (a) railway policy and management initiatives; (b) institutional development of the railway system; (c) expansion of railway capacity; and (d) modernization of railway technology on a systemwide basis. The project consists of: (1) a policy component, comprising: (a) the application of the decision support system to determine high-priority capacity...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

TO SUPPORT RAILWAY POLICY INITIATIVES; SUPPORT RAILWAY CAPACITYEXPANSION; & BROADEN SCOPE OF SYSTEMS-WIDE TECHNOLOGICAL MODERNI-ZATION. COMPRISES A) POLICY COMPONENT; B) INVEST. COMPONENT ONCAPACITY EXPANSION, TRACK & EQUIP. MAINTENANCE, TELECOM MODERNI-ZATION, TRANSP. MGT INFO SYSTEM, PILOT TRANSP.; C) TECH. ASST. COMP.

Key Details

Project Details

  • P003570

  • Closed

  • Richard G. Scurfield

  • N/A

  • China

  • March 25, 1993

  • (as of board presentation)

    March 25, 1993

  • July 14, 1993

  • US$ 420.00 million

  • B

  • Not Applicable

  • June 30, 2001

  • BANK APPROVED

  • March 11, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 420.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 420.00
IDA Commitment N/A
IBRD + IDA Commitment 420.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 1183.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 15, 2013 IBRD-35810 Loan Repay 1,012,614.25
Nov 15, 2013 IBRD-35810 Int Charges 38,537.44
Mar 25, 1993 IBRD-35810 Loan Commitment 420,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 07-29-2002PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.