Abstract*

The Chongqing Industrial Pollution Control and Reform Project supports the Bank's lending strategy in China within a policy framework that focuses on enhanced industrial pollution control linked to enterprise reform and technological restructuring. Moreover, the project supports the government of China's efforts to help relatively underdeveloped regions in the interior catch up with the country's faster growing coastal areas. To achieve these objectives...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

SUPPORT CHONGQING MUNICIPALITY IN DEVELOPING AN INDUSTRIAL POLICY,STRATEGY AND ACTION TO ACHIEVE SIGNIFICANT ENTERPRISE REFORM,RESTRUCTURING OF MAJOR SUBSECTORS AND DEVELOPMENT OF A COMPLETITIVEMARKET STRUCTURE, AND ADOPTION OF SOUND POLLUTION CONTROL POLICY,REGULATORY AND INFRASTRUCTURE FRAMEWORK.

Key Details

Project Details

  • P003646

  • Closed

  • Wiebe Moes

  • N/A

  • China

  • March 14, 1995

  • (as of board presentation)

    June 18, 1996

  • March 7, 1997

  • US$ 8.00 million

  • B

  • January 15, 2013

  • June 30, 2003

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 8.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 8.00
IDA Commitment N/A
IBRD + IDA Commitment 8.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 8.00

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 18, 1996 IBRD-40450 Loan Commitment 170,000,000.00
Mar 15, 2016 IBRD-40450 Int Charges 1,512.86
Mar 15, 2016 IBRD-40450 Loan Repay 176,500.00
Sep 15, 2014 IBRD-40450 Int Charges 0.01
Sep 15, 2014 IBRD-40450 Int Charges 2,375.89
Sep 15, 2014 IBRD-40450 Loan Repay 162,000.00
Mar 15, 2015 IBRD-40450 Int Charges 2,002.75
Mar 15, 2015 IBRD-40450 Loan Repay 166,800.00
Sep 15, 2015 IBRD-40450 Int Charges 1,821.90
Sep 15, 2015 IBRD-40450 Loan Repay 171,500.00
Sep 15, 2016 IBRD-40450 Int Charges 1,147.56
Sep 15, 2016 IBRD-40450 Loan Repay 184,038.60
Sep 15, 2013 IBRD-40450 Int Charges 3,831.90
Sep 15, 2013 IBRD-40450 Loan Repay 153,100.00
Mar 15, 2014 IBRD-40450 Int Charges 3,020.77
Mar 15, 2014 IBRD-40450 Loan Repay 157,500.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 07-01-2004PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a