Skip to Main Navigation

PUSRI IV

Abstract*

The detailed engineering, construction and startup of a fertilizer plant at Palembang, Sumatera, to manufacture about 1,000 TPD (tons per day) of ammonia and 1,725 TPD of urea; training of PUSRI's staff and staff employed in the national fertilizer industry in Indonesia in the operation and maintenance of plant, as well as in financial and accounting procedures. The plant's facilities would include: (1) a single-train ammonia unit with a capacity...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Key Details

Project Details

  • P003751

  • Closed

  • N/A

  • Indonesia

  • N/A

  • (as of board presentation)

    May 11, 1976

  • September 10, 1976

  • US$ 0.00 million

  • N/A

  • Not Applicable

  • N/A

  • BANK APPROVED

  • N/A

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount N/A
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-28-1985PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceNot RatedN/a
Borrower PerformanceNot RatedN/a
Government PerformanceNot RatedN/a
Implementing AgencyNot RatedN/a
Icr QualityNot RatedN/a
M&e QualityNot RatedN/a

Results Framework

No data available.